CDRL Entitled Progress/Final Report - 6 NOV 2015
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ORDER_0001_CDRL.pdf | ||
| SOW_EMC2_IDIQ_2015-11-05_FINAL.pdf | ||
| COR_Appointment_Letter_01_NOV_2014.pdf | ||
| N00014-16-R-0012.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST
(2 Data Items)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
To be completed at order award
A TDP TM OTHER X
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
To Be completed at order award To be completed at order award
To be completed at order award
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A001 Progress Reports (Technical and Financial)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
To be completed at order award To be completed at order award
7. DD 250 REQ 9. DIST STATEMENT 10 FREQUENCY 12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
TBD
REQUIRED
See Block 16 See Block 16
See Block
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Draft Final
N/A See Block 16
SUBMISSION
See Block 16 Reg Repro
16. REMARKS
Nontechnical reports may be provided in contractor format.
Technical reports shall be in the format described in Section D.
Must include contract number, project title, total contract amount, costs incurred during the performance period, costs incurred to date, estimate to complete, schedule of deliveries or milestones, actual dates of delivery or completion of milestone, brief summary of progress and major accomplishments, explanation of any anticipated problems and actions being take to correct problems.
Block 9: To Be Determined (TBD) at order award
Block 10: To Be Determined (TBD) at order award
Block 11: To Be Determined (TBD)at order award
Block 12: To Be Determined (TBD)at order award
Block 13: To Be Determined (TBD)at order award
15. TOTAL
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A002 Final Report
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
To be completed at order award To be completed at order award
7. DD 250 REQ 9. DIST STATEMENT 10 FREQUENCY 12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
TBD
REQUIRED
See Block 16 See Block 16
See Block
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Draft Final
N/A See Block 16.
SUBMISSION
See block 16 Reg Repro
16. REMARKS
Inspection and acceptance is required by the Program Officer at destination. The receiving report in WAWF shall be used as a
Material Inspection and Receiving Report in lieu of a DD Form 250.
Information copies shall be sent to the appropriate parties in accordance with Enclosure Number 1. This report shall include a description of all tasks performed, accomplishments of the program, make recommendations for future technology or research, and contain a breakdown of all contract costs. Final report shall be in the format described in Section D.
Block 9: To Be Determined (TBD) at order award
Block 10: To Be Determined (TBD) at order award
Block 11: To Be Determined (TBD) at order award
Block 12: To Be Determined (TBD) at order award
Block 13: To Be Determined (TBD) at order award
15. TOTAL
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
(Project Officer) (fill-in)
DD FORM 1423-2, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page 1 of 1 Page