About this file

CDRL Entitled Progress/Final Report - 6 NOV 2015

View the file

Other files for this federal contract opportunity

Other files attached to Electromagnetic Command and Control (EMC2), newest first.
File Type Posted
ORDER_0001_CDRL.pdf PDF
SOW_EMC2_IDIQ_2015-11-05_FINAL.pdf PDF
COR_Appointment_Letter_01_NOV_2014.pdf PDF
N00014-16-R-0012.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST

(2 Data Items)

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

To be completed at order award

A TDP TM OTHER X

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

To Be completed at order award To be completed at order award

To be completed at order award

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A001 Progress Reports (Technical and Financial)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

TOTAL PRICE

To be completed at order award To be completed at order award

7. DD 250 REQ 9. DIST STATEMENT 10 FREQUENCY 12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

TBD

REQUIRED

See Block 16 See Block 16

See Block

a. ADDRESSEE

b. COPIES

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT

Draft Final

N/A See Block 16

SUBMISSION

See Block 16 Reg Repro

16. REMARKS

Nontechnical reports may be provided in contractor format.

Technical reports shall be in the format described in Section D.

Must include contract number, project title, total contract amount, costs incurred during the performance period, costs incurred to date, estimate to complete, schedule of deliveries or milestones, actual dates of delivery or completion of milestone, brief summary of progress and major accomplishments, explanation of any anticipated problems and actions being take to correct problems.

Block 9: To Be Determined (TBD) at order award

Block 10: To Be Determined (TBD) at order award

Block 11: To Be Determined (TBD)at order award

Block 12: To Be Determined (TBD)at order award

Block 13: To Be Determined (TBD)at order award

15. TOTAL

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A002 Final Report

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

TOTAL PRICE

To be completed at order award To be completed at order award

7. DD 250 REQ 9. DIST STATEMENT 10 FREQUENCY 12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

TBD

REQUIRED

See Block 16 See Block 16

See Block

a. ADDRESSEE

b. COPIES

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT

Draft Final

N/A See Block 16.

SUBMISSION

See block 16 Reg Repro

16. REMARKS

Inspection and acceptance is required by the Program Officer at destination. The receiving report in WAWF shall be used as a

Material Inspection and Receiving Report in lieu of a DD Form 250.

Information copies shall be sent to the appropriate parties in accordance with Enclosure Number 1. This report shall include a description of all tasks performed, accomplishments of the program, make recommendations for future technology or research, and contain a breakdown of all contract costs. Final report shall be in the format described in Section D.

Block 9: To Be Determined (TBD) at order award

Block 10: To Be Determined (TBD) at order award

Block 11: To Be Determined (TBD) at order award

Block 12: To Be Determined (TBD) at order award

Block 13: To Be Determined (TBD) at order award

15. TOTAL

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

(Project Officer) (fill-in)