This is a presolicitation notice for a bridge rehabilitation and resurfacing project in Prairie County, Montana. The MT PRAIRIE 2016(3) project is located approximately 5 miles west of Terry City and spans 0.348 miles. The work consists of replacing existing timber decking with a metal grid bridge deck, replacing timber railing with metal bridge rail, performing scour remediation and concrete repair, and grading and resurfacing the adjacent roadway. The estimated price range is between $5,000,000 and $10,000,000, with a tentative solicitation date of Spring/Summer 2026 and a tentative fixed completion date of Fall/Winter 2026.
The scope of work follows FP-14 specifications and includes construction survey and staking, contractor quality control and assurance, contractor sampling and testing, and construction schedules. Major work divisions include clearing and grubbing (0.4 acres), removal of structures and obstructions (including 2,160 linear feet of bridge rail and 1,520 square yards of bridge deck), excavation and embankment (totaling 2,700 cubic yards), placed riprap (2,000 cubic yards), minor crushed aggregate (680 cubic yards), steel structures (382,000 pounds), bridge railing (2,170 linear feet), painting with containment system, soil erosion and sediment control measures, rental equipment, general labor, topsoil and turf establishment (0.3 and 0.4 acres respectively), and temporary traffic control including flaggers, signs, barricades, and drums.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QandA_03-02-2026.pdf | ||
| mta-prairie2016-3_Prelim Letter.pdf | ||
| mt-a-prai201603_ Prelim plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MT PRAIRIE 2016(3), Milwaukee Bridge Resurfacing and Rehabilitation
Prairie County, Montana
This work consists of replacement of existing timber decking with metal grid bridge deck, replacement of existing timber railing with metal bridge rail, performing scour remediation and concrete repair, and grading and resurfacing of the roadway adjacent to the bridge.
Project Location: This project is located approximately 5 Miles west of Terry City, Prairie County, Montana State.
Project Length: 0.348 Mile
Estimated Price Range: Between $5,000,000 and $10,000,000
Tentative Solicitation Date: Spring/ Summer 2026
Tentative Fixed Completion Date: Fall/ Winter 2026
DESCRIPTION OF WORK in US CUSTOMARY UNITS
USING FP-14 SPECS
O n e S ch ed u le
S ch
N am e
A
DIVISION 150 – Project Requirements
152 Construction Survey & Staking (yes/no) Yes
153 Contractor Quality Control and Assurance
(yes/no) Yes
154 Contractor Sampling & Testing (yes/no) Yes
155 Schedules for Construction Contracts
(construction schedules) (yes/no) Yes e S ch ed
N
157 Soil Erosion & Sediment Control (erosion control devices)
- Temporary Soil Tackifier
- Fiber Roll
0.9 ACRE
1800 LNFT
158 Watering for Dust Control LPSM
DIVISION 200 – Earthwork
201 Clearing & Grubbing 0.4 ACRE
202 Additional Clearing & Grubbing (clearing & grubbing) ---
203 Removal of Structures & Obstructions
- Removal of Sign/Marker
- Removal of Sign
- Removal of bridge rail
- Removal of bridge deck
4 EA
2 EA
2160 LNFT
1520 SQYD
204 Excavation & Embankment
- Roadway excavation
- Subexcavation
- Unclassified borrow
100 CUYD
2000 CUYD
600 CUYD
DIVISION 250 – Slope Reinforcement and Retaining Walls
251 Placed Riprap, Method A, Class 5 2000 CUYD
DIVISION 300 – Aggregate and Base Courses
302 Minor Crushed Aggregate 680 CUYD
DIVISION 550 – Bridge Construction
555 Steel Structures (structures, steel) 382,000 LB
556 Bridge Railing 2170 LNFT e S ch ed
N
563 Painting (structures, painting)
- Containment system and worker protection plan
LPSM
575 Minor Bridge Work
- Work Platform
LPSM
DIVISION 600 – Incidental
Construction
619 Fences, Gates, Cattle Guards & Bollard
Posts
- Remove and reset fence
60 LNFT
621 Monuments & Markers (construction survey & staking) (yes/no) No
622 Rental Equipment (yes/no) Yes
623 General Labor (yes/no) Yes
624 Topsoil (landscaping & related items) 0.3 ACRE
625 Turf Establishment
(indicate seeding or mulching separately) 0.4 ACRE
633 Permanent Traffic Control (traffic control devices)
- Sign system
- Object markers
- Delineators
40 SQFT
4 EACH
4 EACH
635 Temporary Traffic Control – Flagger 16 HOUR
635 Temporary Traffic Control – Construction signs 200 SQFT
635 Temporary Traffic Control – Barricade 7 EACH
635 Temporary Traffic Control – Drum 22 EACH