This is a Manufacturing Qualification Requirements document for a Master Interconnect Assembly-Remote Interface Unit (P/N 16E1628-5, NSN 1280010874370) used in F-16 aircraft applications. Effective November 21, 2025, the document outlines mandatory qualification standards and optional waiver criteria for potential suppliers seeking to manufacture this component for the government.

Offerors must satisfy ten core qualification requirements: provide prequalification notice to the appropriate government office; certify possession of required manufacturing, inspection, testing, packaging, and storage facilities available for government evaluation; verify a complete data package including all procedures, drawings, and specifications (minimum Lockheed Martin drawing 16E1628 with change notices); manufacture items conforming to ESA-approved engineering data and DFARS Unique Identification requirements; prepare and submit a government-approved qualification test plan detailing verification of all performance, environmental, mechanical, and quality requirements; provide a pre-contract award qualification article at the offeror's expense for form, fit, and function evaluation; and submit complete test reports prior to contract award. The government retains the right to witness testing on-site with a required 30-day advance notification. Estimated qualification costs are $65,000 with an estimated completion timeframe of 365 days. Offerors will receive notification of qualification article pass/fail status within 180 days of submission. Full qualification before the contract award date is mandatory for contract eligibility, though approval does not guarantee contract award. Additionally, five Source Qualification Waiver Criteria (QWC1-QWC5) allow potential sources to request partial or full waiver of requirements based on prior government supply history, assembly qualification status, earlier dash number production, similar item qualification, or acquisition/reorganization scenarios with equivalent facilities and processes.

View the file

Other files

File Type Posted
SPRHA426Q0978.pdf PDF
EDL.pdf PDF
CDRLCPP.pdf PDF
Packaging.pdf PDF
SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MANUFACTURING QUALIFICATION REQUIREMENTS

NSN: 1280010874370

P/N: 16E1628-5 Noun: MASTER INTERCONNECT ASSY-REMOTE INTFC UNIT Application: F-16

21 Nov 2025 Section C 1/2

SECTION C:

1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE

a. Prequalification Notice/Sources Sought: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this MASTER INTERCONNECT

ASSY-REMOTE INTFC UNIT.

b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to manufacture, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

c. Data Verification: The offeror must verify that he has a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession including, at a minimum Lockheed Martin(81755) drawing 16E1628. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.

d. Manufacture/Process Verification: The offeror must manufacture this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 416th SCMS/GUEAA. The offeror shall also identify its sources for materials and its standards for internally used processes.

e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 416th SCMS/GUEAA for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by Drawing 16E1628. After completion of the approved qualification testing, the offeror shall be required to submit a complete test report of the results to 416th SCMS/GUEAA for their review and approval prior to the contract award. The government retains the right to exercise the option to inspect the testing processes, including on-site witnessing of any or all documented testing. To allow accomplishing this, the offeror shall notify the government at least 30 days in advance of the occurrence of any testing that will be used as a basis for qualification. The offeror’s facilities shall be made available for government inspection during these tests.

P/N: 16E1628-5

21 Nov 2025 Section C 2/2

f. Qualification Article Verification: The offeror must provide, at their own expense, a pre-contract award qualification article for evaluation by the government. This article must comply with all of the requirements of Drawing 16E1628. This article shall be subjected to a form, fit, and function evaluation to demonstrate compatibility with the weapon system and to evaluate the manufacturing capability of the offeror. Offerors will be notified whether or not their qualification article passed or failed the required qualification testing within 180 days of submitting a product for qualification testing. Note that successful completion of the qualification testing does not guarantee any contract award. If the offeror is deemed qualified and awarded the contract, a post-contract award first article exhibit may be required to verify production capability.

g. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified: $65,000.

h. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 365 days. This is based on complexity of the MASTER INTERCONNECT ASSY-REMOTE INTFC UNIT and other factors.

i. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.

j. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved source for this item. Approval, however, does not guarantee subsequent contract award.

P/N: 16E1628-5

21 Nov 2025 Section C 1/1

2. SOURCE QUALIFICATION WAIVER REQUIREMENTS

Sources who meet any of the following source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:

a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).

b. QWC2: A source qualified to provide an assembly is usually qualified to provide subassemblies, major components, and items of that assembly.

c. QWC3: A source qualified to provide earlier dash numbers of a basic P/N may be qualified to provide other dash numbers of that same basic P/N, provided there is no increase in complexity, criticality, or other relevant requirements.

d. QWC4: A source qualified to provide a similar or like item can be qualified to provide the required item. However, for approval, the engineering authority must verify that there is no increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written proof, such as purchase orders, shipping documents, etc., to show that the similar item was provided to the original equipment manufacturer or DoD.

e. QWC5: A source previously qualified to provide an item, but which has been purchased, sold, merged, absorbed, reformed, split, etc., may qualify if it can be established that the qualification is currently with the requester and that the requester has the same or equivalent facilities, tooling, equipment, personnel, and utilizes the original forging, castings, etc., in the manufacturing process.