MQR.pdf

PDF 196 KB Posted

Attached to
F-16 Manual Trim Panel Federal contract opportunity
Solicitation number
SPRHA4-26-Q-0253
Issued by
Defense Logistics Agency Aviation

About this file

Manufacturing Qualification Requirements Summary

This is a Manufacturing Qualification Requirements document for the Panel, Manual Trim (NSN: 6615-01-450-2802, P/N: 16C0650-803) used in F-16 Aircraft applications, dated September 24, 2020. Potential offerors must satisfy ten qualification requirements to become an approved source: (1) notify the appropriate government Small Business Office or contracting officer of intent to qualify; (2) certify possession of required facilities, equipment, tooling, and inspection capabilities; (3) verify possession of a complete data package including Lockheed Martin Corporation (81755) drawing 16C0650-803 and all change notices; (4) manufacture the item to conform to government requirements and demonstrate compliance with Unique Identification (UID) requirements per DFARS 211.274; (5) prepare and submit a qualification test plan to 416 SCMS/GUEAA for approval, with the offeror bearing all testing expenses and providing at least 45 days' notice before testing; (6) provide a pre-contract award qualification article for form, fit, and function evaluation with notification of pass/fail results within 180 days; (7) acknowledge estimated qualification costs of $100,000.00; (8) acknowledge estimated completion time of 365 days; (9) understand that qualification may be completed before contract award and the award will not be delayed to allow vendors additional qualification time; and (10) achieve full qualification status before contract award eligibility.

The document establishes six Source Qualification Waiver Criteria (QWC) that may allow partial or complete waiver of qualification requirements: QWC1 permits waiver based on written certification of prior government or original equipment manufacturer supply; QWC2 allows qualified sources to extend qualification from right-hand to left-hand mirror-image articles; QWC3 qualifies assembly suppliers to provide subassemblies and components; QWC4 permits qualified sources of earlier dash numbers to qualify for other dash numbers of the same basic part number without increased complexity; QWC5 allows qualified sources of similar items to qualify for the required item with engineering authority verification of no increased complexity or criticality; and QWC6 permits previously qualified sources that have undergone business changes to requalify if they maintain equivalent facilities, tooling, equipment, and personnel and use original manufacturing materials. Post-contract award first article exhibits may still be required regardless of qualification or waiver status.

View the file

Other files for this federal contract opportunity

Other files attached to F-16 Manual Trim Panel, newest first.
File Type Posted
SPRHA426Q0253.pdf PDF
CDRLCPP.pdf PDF
SOW.pdf PDF
EDL.pdf PDF
EDR.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MANUFACTURING QUALIFICATION REQUIREMENTS

NSN: 6615-01-450-2802

P/N: 16C0650-803 Noun: Panel, Manual Trim Application: F-16 Aircraft

24-Sep-20 Section C 1/3

SECTION C:

1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE

a. Prequalification Notice/Sources Sought: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this Panel, Manual Trim.

b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to manufacture, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

c. Data Verification: The offeror must verify that he has a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession including, at a minimum Lockheed Martin Corporation (81755) drawing 16C0650-803. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.

d. Manufacture/Process Verification: The offeror must manufacture this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 416 SCMS/GUEAA. The offeror shall also identify its sources for materials and its standards for internally used processes.

e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 416 SCMS/GUEAA for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by Drawing 16C0650-803 and all other related drawings. After completion of the approved qualification testing, the offeror shall be required to submit a complete test report of the results to 416 SCMS/GUEAA for their review and approval prior to the contract award. The government retains the right to exercise the option to inspect the testing processes, including on-site witnessing of any or all documented testing. To allow accomplishing this, the offeror shall notify the government at least 45 days in advance of the occurrence of any testing that will be used as a basis for qualification. The offeror’s facilities shall be made available for government inspection during these tests.

f. Qualification Article Verification: The offeror must provide, at their own expense, a pre-contract award qualification article for evaluation by the government. This article must comply with all of the requirements of Drawing 16C0650-803. This article shall be subjected to a form, fit, and function evaluation to demonstrate compatibility with the weapon system and to evaluate the

P/N: 16C0650-803

24-Sep-20 Section C 2/3 manufacturing capability of the offeror. Offerors will be notified whether or not their qualification article passed or failed the required qualification testing within 180 days of submitting a product for qualification testing. Note that successful completion of the qualification testing does not guarantee any contract award. If the offeror is deemed qualified and awarded the contract, a post-contract award first article exhibit may be required to verify production capability.

g. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified: $100,00.00.

h. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 365 days. This is based on complexity of the Panel, Manual Trim and other factors.

i. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.

j. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved source for this item. Approval, however, does not guarantee subsequent contract award.

P/N: 16C0650-803

24-Sep-20 Section C 3/3

2. SOURCE QUALIFICATION WAIVER REQUIREMENTS

Sources who meet any of the following source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:

a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).

b. QWC2: The potential source is qualified on the right-hand article and requests to be qualified on the left-hand article. If the right-and left-hand articles are mirror images of each other, then approval can generally be given.

c. QWC3: A source qualified to provide an assembly is usually qualified to provide subassemblies, major components, and items of that assembly.

d. QWC4: A source qualified to provide earlier dash numbers of a basic P/N may be qualified to provide other dash numbers of that same basic P/N, provided there is no increase in complexity, criticality, or other relevant requirements.

e. QWC5: A source qualified to provide a similar or like item can be qualified to provide the required item. However, for approval, the engineering authority must verify that there is no increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written proof, such as purchase orders, shipping documents, etc., to show that the similar item was provided to the original equipment manufacturer or DoD.

f. QWC6: A source previously qualified to provide an item, but which has been purchased, sold, merged, absorbed, reformed, split, etc., may qualify if it can be established that the qualification is currently with the requester and that the requester has the same or equivalent facilities, tooling, equipment, personnel, and utilizes the original forging, castings, etc., in the manufacturing process.

File details come from the government source that posted it. Updated .