Motor and Rigging_ SOW Final.pdf
PDF 73 KB Posted
- Attached to
- 45 SFS Boat Motor & Rigging
- Solicitation number
- FA252126QB033
About this file
This Statement of Work (SOW) describes the replacement and installation of a 250 horsepower outboard engine on a 2019 23' Lake Assault Aluminum Patrol boat. The contractor shall provide all personnel, equipment, tools, materials, supervision, and labor to perform a complete, turnkey engine replacement on a government-furnished vessel. The work must be completed within 90 days from the date the vessel is delivered to the contractor's facility. All work shall be performed at an approved and certified service facility, with proof of current certification required prior to award. For locations within 120 miles, the government will coordinate vessel drop-off with at least 3 days' notice; for locations beyond 120 miles, the vendor is responsible for pick-up and delivery coordination.
The engine specifications require a new 250 HP four-stroke outboard with a 25-inch shaft from a reputable manufacturer in the current model year. The contractor must supply and install a complete rigging package including digital throttle and shift controls, control box, key switch, main wiring harness, new multi-function digital gauges, a new stainless-steel propeller sized for optimal performance, and a fuel/water separator filter. The new engine must integrate with the vessel's existing hydraulic steering system, with the contractor responsible for supplying any necessary fittings, hoses, or fluid. Installation requirements include professional removal and disposal of the old engine, transom inspection and preparation, engine mounting using new stainless-steel hardware per manufacturer specifications, secure routing of all cables and fuel lines, and comprehensive operational testing including flush hose and on-water testing. The bidder must be an authorized dealer and certified service center with factory-certified technicians; proof of all certifications must be submitted with the quote and remain valid throughout performance. The contractor shall provide the manufacturer's warranty on the engine and parts plus a minimum one-year warranty on installation labor, deliver all documentation and the original invoice upon completion, bear responsibility for any vessel damage caused during work, and ensure legal disposal of the old engine and debris. The government will conduct final acceptance upon successful completion of all operational tests, with any deficiencies corrected by the contractor at no additional cost.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 26QB033 Sources Sought.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
250 HP Outboard Engine Replacement and Install
February 17, 2026
1. Objective:
The objective is to procure and install one (1) new 250 horsepower (HP) outboard engine with a 25-inch shaft on a 2019 23’ Lake Assault Aluminum Patrol boat. This includes the engine, all associated rigging components/electrical, and the labor to de-rig the old engine and install the new one on a government-provided vessel.
2. Scope of Work:
The contractor shall provide all personnel, equipment, tools, materials, supervision, and any other items required to perform a complete, turnkey engine replacement.
3. Technical Requirements:
The engine, components, and installation must be fully operational upon acceptance. All parts and components must be new; reconditioned or used parts will not be accepted.
3.1. Required Engine & Component Specifications
1. Outboard Engine | Horsepower: 250 HP; Shaft Length: 25-inch; Type: Four-Stroke;
Condition: New, current model year from a reputable manufacturer.
2. Engine Rigging | Must include new digital throttle and shift (DTS) or equivalent electronic controls, control box, key switch, main wiring harness, and all necessary cabling.
3. Instrumentation | New multi-function digital gauge(s) compatible with the engine, displaying RPM, speed, fuel level, engine hours, trim, and all critical engine diagnostics and alerts.
4. Propeller | A new stainless-steel propeller, sized appropriately for the vessel and engine combination to achieve optimal performance. The contractor shall recommend the final pitch and diameter.
5. System Integration| The new engine must be integrated with the vessel's existing hydraulic steering system. The contractor is responsible for supplying any new fittings, hoses, or fluid required.
6. Fuel System | The engine will be connected to the existing fuel tank. The installation must include a new fuel/water separator filter.
3.2. Installation Requirements
1. De-Rigging | Professionally remove and prepare for disposal one (1) existing outboard engine, its controls, and all associated rigging from the government vessel.
2. Transom Preparation | Inspect the vessel's transom for integrity. Clean and properly seal all existing mounting holes. Drill new holes as required for the new engine installation.
3. Engine Mounting | Mount the new 250 HP outboard engine to the vessel's transom using new stainless-steel mounting hardware in accordance with the manufacturer's specifications. |
4. Rigging Installation| Route and connect all control cables, wiring harnesses, and fuel lines neatly and securely, ensuring they are protected from chafing or damage. |
5. System Testing | After installation is complete, conduct a comprehensive operational test of the engine and all systems. This shall include testing on a flush hose and a final on-water test to check for leaks, proper shifting, throttle response, and full functionality of all gauges and controls. |
4. Delivery and Installation
a. Timeline: All work shall be completed within 90 days from the date the vessel is delivered to the contractor's facility. Delivery, work and products required shall be included in the vendor’s quote.
b. Location of Work: The contractor shall perform all their work at an approved and certified service facility. Proof of the facility’s current certification shall be submitted with the quote prior to award, and the facility’s certification must remain valid for the full period of performance.
c. Coordination: The government will coordinate the vessel drop-off no less than 3 days in advance if within 120 miles. If not within 120-mile radius, pick-up and delivery will be coordinated by the vendor.
d. Work Hours: Work may be performed during the contractor's normal business hours.
5. Contractor Requirements
5.1. Qualifications: The Bidder shall be an authorized dealer and certified service center for the brand of engine being proposed. Technicians performing the installation must be factory‑certified on the proposed engine model. Proof of all required dealer, service center, and technician certifications shall be submitted with the quote and must remain valid for the entire period of performance.
5.2. Documentation: Upon completion, the contractor shall provide the owner's manual, all associated engine documentation, and the original invoice.
5.3. Warranty: The contractor shall provide the full manufacturer's warranty on the engine and all parts. A minimum one-year warranty on installation labor will also be provided.
5.4. Responsibility: The contractor is responsible for the proper removal of the old engine and the complete and correct installation of the new engine. Any damage to the vessel caused by the contractor's personnel or equipment during the work shall be repaired at the contractor's expense.
6. Government Furnished Items The government will deliver the vessel to the contractor's facility, enabling the contractor to perform the required work.
7. Old Engine & Debris Control The contractor shall be responsible for the legal disposal of the old engine, all old rigging components, packaging materials, and any other debris associated with the installation.
8. Acceptance The government will conduct final acceptance upon successful completion of all operational tests. Any deficiencies identified during acceptance shall be corrected by the contractor at no additional cost.