Morse High School Whole Site Modernization Ph IV - Construction Services.pdf
PDF 280 KB Posted
- Solicitation number
- LB27-0411-50-00-G1
- Issued by
- San Diego County, San Diego City, California
About this file
This is a Request for Proposals (RFP) document issued by the San Diego Unified School District for construction services related to the Morse High School Whole Site Modernization Phase IV project. The District is utilizing a Lease-Leaseback (LLB) competitive selection process under Education Code 17406 to award the contract based on best value. The project encompasses all labor, materials, transportation, equipment, and services necessary for the whole site modernization. A mandatory site walk is scheduled for Thursday, November 5, 2026, at 9:00 AM at Morse High School (6905 Skyline Drive, San Diego, CA 92114), with preregistration required through sandiegounified.org/sitewalks. Prequalification applications are due Tuesday, December 8, 2026, at 2:00 PM, Requests for Information (RFIs) are due Tuesday, December 1, 2026, at 2:00 PM, and proposals are due Tuesday, January 5, 2027, at 2:00 PM. The construction services contract term is 21 months. Failure to attend the mandatory site walk or extreme tardiness will render a contractor's proposal ineligible.
The project budget is estimated between $45 million and $47 million. Only Licensed and Bonded (LLB) Prime Contractors from Group J listed in the RFP are eligible to submit proposals. Prevailing wage requirements apply to this public works project, with the applicable prevailing wage determination established as of the first bid advertisement date and remaining in effect for the full duration of the project and all authorized change orders. The District reserves the right to reject any and all proposals and to waive minor irregularities. Proposal documents may be downloaded free of charge from sandiegousdplans.com or purchased in printed format from Crisp Imaging for a refundable $500 per set. The project is identified as DSA #04-125015 and LB27-0411-50-00-G1. Prequalification, SB 854 compliance with the California Department of Industrial Relations, Project Stabilization Agreement, Skilled & Trained Workforce requirements, Disabled Veteran Business (DVB) requirements, Emerging Business Enterprises (EBE) goals, bonds, and insurance are mandatory requirements detailed in the RFP.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOR THE SAFETY OF OUR STUDENTS, ATTENDEES OF SITE WALK MUST ABIDE BY THE FOLLWING:
• Leaving the walk before it has concluded: if you need to leave the site walk before it has ended, locate the Contract
PROPOSAL SUBMISSION: Each proposal shall be in accordance with all terms, conditions, plans, specifications, and any other documents that comprise the RFP. Contractors interested in submitting a Proposal must go to https://www.planetbids.com/portal/portal.cfm?CompanyID=43764 then search under “Bid Opportunities” for the RFP. For new vendors, register under “New Vendor Registration”.
ineligible. Attendees shall meet in front of the main office of Morse HS, 6905 Skyline Dr., San Diego, CA 92114.
All attendees must preregister with the District prior to attending the site walk at sandiegounified.org/sitewalks.
• Photographs: when taking pictures of the site, please make sure students are not in the frame.
• Restrooms: please use a "Staff Only" restroom - student restrooms are not open to adults.
• Conduct: when walking through the campus, stay together as a group and keep your voices down. Class is in session.
• Sundt Construction Inc. • Turner Construction Company
PROPOSAL DOCUMENTS: The RFP and associated documents may be downloaded free of charge at the District’s online Planroom at sandiegousdplans.com (click on Public Jobs to view all current bids). Contractors may purchase printed documents at Crisp Imaging for a refundable payment of Five Hundred Dollars ($500) per set or CD/USB drives for a non-refundable payment ($2 - $10). Please pay by check to San Diego Unified School District. Refunds will be processed by District only if the Documents, including addenda, are returned intact and in good order to Crisp Imaging within ten (10) days of the issuance of the Final Results on the day after Board Award. Crisp Imaging, 9240 Trade Place, Suite 300, San Diego, CA 92126,
(858) 535-0607.
RFP REQUIREMENTS: Refer to the RFP for information on requirements such as prequalification; SB 854 / California Department of Industrial Relations (DIR); Project Stabilization Agreement (PSA); Skilled & Trained Workforce; Disabled Veteran Business (DVB) requirements and Emerging Business Enterprises (EBE) goals; bonds and insurance.
MANDATORY SITE WALK: Failure to attend, extreme tardiness or failure to sign in will render the Contractor’s Proposal
• C.W. Driver LLC • Erickson-Hall Construction Co. • Flint Design Build LLC dba Flint
• PCL Construction Services Inc. • SOLPAC Construction Inc. dba Soltek Pacific • Swinerton Builders
ELIGIBLE BIDDERS: * Only LLB Prime Contractors from Group J listed below may submit proposals to District. Please visit sandiegounified.org/LLB-Outreach for each LLB Prime Contractor’s contact information.
• Balfour Beatty Construction LLC • Bernards Bros Inc. • Core West Inc.
Prequalification Applications Due Tuesday, December 8, 2026 at 2:00 PM Proposals Due Tuesday, January 5, 2027 at 2:00 PM
Mandatory Site Walk Thursday, November 5, 2026 at 9:00 AM RFIs Due Tuesday, December 1, 2026 at 2:00 PM
Construction Service: 21 Months
DSA #: 04-125015
RFP SCHEDULE: All Contractors must adhere to the RFP Schedule below. If the District modifies this RFP Schedule, it will issue an addendum.
EVENT DEADLINE
Construction Services at Morse HS Whole Site Modernization Ph. IV
LB27-0411-50-00-G1
$45-$47M
PREVAILING WAGE: Prevailing wage requirements apply to all public works projects and must be followed per Exhibit G, Article 17 of the General Conditions of the Master Facilities Lease. The applicable prevailing wage determination during construction is the one in effect on the date the GMP is first published in a newspaper of general circulation. Here, the applicable prevailing wage determination for construction services referenced in the published GMP advertisement is 2026-
Advertisement for Responses to Request for Proposals (RFP) Lease-Leaseback (LLB)*
NOTICE: Notice is hereby given that the San Diego Unified School District (“District”), acting by and through its governing board, will use lease lease-back (LLB), a competitive selection process for award of contract based on best value under Education Code §17406, to electronically receive proposals for the furnishing of all labor, materials, transportation, equipment, and services for:
90 days
SAN DIEGO UNIFIED SCHOOL DISTRICT
George A. Harris III Director, Fiscal Controls and Information Systems Facilities Planning and Construction
08 71 00 Door Hardware
LB27-0411-50-00-G1
The District reserves the right to reject any and all proposals and to waive any minor irregularities or informalities in any proposals or in the bidding process. No LLB Prime Contractor may withdraw his proposal for a period of after the District receives proposals.
Advertisement Dates:
October 27, 2026
November 3, 2026
28 46 21.11 Addressable Fire-Alarm Systems
32 18 13 Synthetic Grass Surfacing 32 84 00 Planting Irrigation
32 84 01 Field Cooling System
11 68 16 Play Structures 28 13 00 Access Control
PROPRIETARY SPECIFICATIONS: Under Public Contract Code §3400(c)(2), the District or its designee, has made a finding that the following particular materials, products, things, or services are designated by specific brand or trade name in order to match other products in use on the Project:
2. The prevailing wage determination established for the Project shall remain applicable for the full duration of the Project, including all Work performed pursuant to authorized Change Orders under the Agreement and shall remain in effect until all contract Work has been substantially completed. The first bid advertisement date for each District defined GMP phase shall establish the applicable prevailing wage determination, regardless of how many times the Prime Contractor published an advertisement. That first bid advertisement to subcontractors shall state the applicable prevailing wage determination for construction services for the duration of that District defined GMP phase. Based on its separate publication of the first bid advertisement date, each District defined GMP phase for construction services may have a different prevailing wage determination. The prevailing wage determination established for each District defined GMP phase shall remain applicable for the full duration of the District defined GMP phase, including all Work performed pursuant to authorized Change Orders under the Agreement, and shall remain in effect until all contract Work has been substantially completed. The following is a link to the Department of Industrial Relations (DIR) website to obtain rate information, and any applicable predetermined increases:
www.dir.ca.gov/oprl/dprewagedetermination.htm.
File details come from the government source that posted it. Updated .