Moriarty ES BP 1.26 Electrical Pre-purchase Addendum No. 1 to Norwich.pdf
PDF 106 KB Posted
- Attached to
- Electrical Equipment, ATS & Generator Purchase
- Solicitation number
- Uncas/Moriarty No1
- Issued by
- Connecticut
About this file
This is Addendum No. 1 to an Invitation to Bid issued by the City of Norwich, Connecticut for Bid Package 1.26 - Electrical Equipment, ATS and Generator Purchase related to Phase 1 of the Moriarty Elementary School project (State Project No. 104-0121N). The project encompasses the procurement and delivery of electrical equipment, automatic transfer switches (ATS), and a generator for the school. A pre-bid meeting was held on November 5, 2025 at 3:30 p.m., with sign-in sheets and minutes attached to this addendum. The deadline for submitting pre-bid requests for information (RFIs) is November 15, 2025, and the bid due date is Tuesday, November 25, 2025 at 2:00 p.m. Bids must be submitted using the Form of Proposal contained in Specification Section 00 42 00 and emailed to the Construction Manager at O&G Industries (cmbids@ogind.com). All bids must be accompanied by the Form of Proposal, bid security (bid bond or certified check), and a CTDAS Update Statement if the bid exceeds $1,000,000.00.
The addendum clarifies critical responsibilities between Phase 1 and Phase 2 electrical contractors regarding equipment installation and delivery. The Phase 1 Electrical contractor is responsible for obtaining the electrical permit, providing a full tank of fuel for the generator after installation, and rigging the switchboard and ATS to their permanent location. The Phase 2 Electrical contractor assumes responsibility for equipment installation, including personnel to receive equipment, bolting sections together, anchoring to the structural slab, and providing fuel at substantial completion. The City of Norwich will waive permit fees except for the State Education Fee, which will be funded by the Owner. Wage and Hour Rates for Phase 1.26 Enabling - Electrical Pre-purchase are provided in the attached documentation, along with CM Prebid RFI responses numbered 1-4 that form part of the required scope of work for all contractors preparing bids.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 1 – November 7, 2025
INVITATION TO BID
MORIARTY ELEMENTARY SCHOOL – PHASE 1
NORWICH, CONNECTICUT
MORIARTY: STATE PROJECT NO: 104-0121 N
ADDENDUM NO. 1
November 7, 2025 https://securecc.smartinsight.co/#/PublicBidProject/833286
THE BID DUE DATE REMAINS
TUESDAY, NOVEMBER 25, 2025 @ 2:00 PM
THE LAST DAY TO SUBMIT PRE-BID REQUESTS FOR INFORMATION
(RFI’S) IS NOVEMBER 15, 2025
PLEASE USE THE FORM OF PROPOSAL CONTAINED IN SPECIFICATION SECTION
00 42 00 FOR SUBMITTING YOUR BID.
EMAIL YOUR BID PROPOSAL TO THE FOLLOWING EMAIL ADDRESS:
Construction Manager, O&G Industries– cmbids@ogind.com
THE FOLLOWING DOCUMENTS MUST ACCOMPANY YOUR BID, OR YOUR
PROPOSAL WILL BE DEEMED NON-RESPONSIVE:
1. FORM OF PROPOSAL
2. BID SECURITY (BID BOND OR CERTIFIED CHECK)
3. CTDAS UPDATE STATEMENT (if bid exceeds $1,000,000.00)
I. REVISIONS TO SPECIFICATIONS
1. Specification Section 00 11 16 – Invitation to Bid
a. Attached to this Addendum No. 1 is the Sign-In Sheet and Pre-Bid Minutes for the Prebid
Meeting held on November 5, 2025 @ 3:30 p.m.
2. Specifications Section 00 24 13 – Bid Packages
a. Bid Package 1.26 – Electrical Equipment, ATS and Generator Purchase
II. SPECIAL INSTRUCTIONS
Add the following Special Instructions:
17. The City of Norwich Permit fees will be waived with the exception of the State Education Fee, which will be funded by the Owner. The Phase 1 Electrical
Addendum No. 1 – November 7, 2025 contractor is responsible for submitting for and obtaining the Electrical Permit for their scope of work.
18. The Phase 1 Electrical contractor shall provide a full tank of fuel for the generator after installation. The Phase 2 Electrical contractor is responsible for providing a full tank of fuel at time of Building substantial completion.
19. The Phase 1 Electrical contractor is responsible for providing the rigging of the
Switchboard and ATS to the permanent location. The Phase 2 Electrical contractor is responsible for installation, e.g. providing personnel to receive the equipment on-site, bolting the equipment sections together and anchoring the equipment sections to the structural slab. The Phase 2 Electrical contractor is responsible for all materials needed for anchorage except for those items specifically identified to be provided by the Phase 1 Electrical contractor in the bill of materials.
3. Specification Section 00 31 13 – Project Scheduling and Phasing
a. Replace page 6 in its entirety. Section 5c table has been updated.
4. Specification Section 00 63 13 – Bidders’ Prebid Requests for Information (Prebid RFI's)
a. Attached to this Addendum No. 1 is CM Prebid RFI No. 1 - 4. MISSING PREBID RFI
RESPONSES SHALL BE INCLUDED IN THE NEXT ADDENDUM. All information contained in these responses is to be used by all contractors in the preparation of their bids and will form part of their scope of work.
5. Specification Section 00 73 43 – Wage and Hour Rates
a. Attached to this Addendum No. 1 is Wage and Hour Rates for 1.26 Enabling – Electrical
Pre-purchase.
II. REVISIONS TO TECHNICAL SPECIFICATIONS
None.
III. REVISIONS TO DRAWINGS
None.
IV. ATTACHMENTS TO ADDENDUM
Description Pages
Specification Section 00 11 16 – Sign-In Sheet and Pre-Bid Minutes 3 Specification Section 00 31 13 – Project Schedule and Phasing 1 Specification Section 00 63 13 – Bidders’ Prebid Requests for Information (Prebid RFI's) 1 Specification Section 00 73 43 – Wage and Hour Rates 9
END OF ADDENDUM NO. 1