20231205 - Mansfield Industry Day Presentation.pdf

PDF 4 MB Posted

Attached to
INDUSTRY DAY - Mike Mansfield Federal Building/Courthouse Seismic Retrofit & Ltd Modernization Design/Build
Solicitation number
Not on record
Issued by

About this file

This document provides an overview of an upcoming design-build solicitation for seismic retrofit and limited modernization work at the Mike Mansfield Federal Building/Courthouse in Butte, Montana. The General Services Administration Public Buildings Service Region 8 will issue the solicitation seeking proposals to perform a full building seismic retrofit, replace the HVAC systems with either air source variable refrigerant flow and electric backup or geothermal water-to-water heat pumps and electric boiler backup, replace building waste and vent and domestic water piping, complete accessibility upgrades, and conduct historic renovation and envelope upgrades including facade repairs and re-roofing. The solicitation is expected to be released in March/April 2024 with technical proposals due in April/May 2024. Up to three offerors will be shortlisted to submit technical and price proposals in Phase 2, with final selection and contract award anticipated in September/October 2024. Evaluation factors include technical approach, qualifications, design concept, key personnel, management plan, and sustainability. Sustainability and project labor agreement factors each account for 15% of the evaluation.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WELCOME

GSA PUBLIC BUILDINGS SERVICE

INDUSTRY DAY

MIKE MANSFIELD FB/CH

SEISMIC RETROFIT & LTD SCOPE

December 5, 2023

Disclaimer Nothing said/provided at this event is binding. Once released, only the solicitation and its attachments shall govern this acquisition.

Project Overview

Steve Janzen Program Manager/COR

Disclaimer

Nothing said/provided at this conference is binding.

Once released, only the solicitation and its attachments shall govern this acquisition.

Mike Mansfield FB/CH

● 400 N. Main St, Butte, MT

Mike Mansfield Seismic Retrofit & Limited Modernization

Project Overview

● History/Background

● Site Context

● Project Goals / Objectives

Building Size

● Building Footprint: 157’ x 122’

(approximate)

● Basement, first floor, second, and third floors

● Second floor mechanical mezzanine on the light court

● Attic Space

● Gross building area: 58,850 sf (approximate)

PROJECT OVERVIEW – History / Background

Studies

● Past studies completed include;

● 2020 GSA R8 Feasibility Study

● Asbestos Re-Inspection Report, Pinyon Environmental, Inc., dated February 28, 2014.

● AHERA Asbestos Survey Report for Renovation Re-Inspection, Weecycle Environmental Consulting, Inc., dated September 1, 2017.

● Building Preservation Plan (BPP) by Andrews & Anderson Architects, dated July 2010-April 2011.

● 2023 Mansfield GSA R8 Program Dev Study and POR

● Upcoming–Seismic Materials & Lab Testing

PROJECT OVERVIEW – History / Background

Building Tenants

PROJECT OVERVIEW – Site Context

Goals & Objectives

● A full building seismic retrofit

● A complete replacement of building HVAC systems with these two options priced as the basis of design

○ air source vrf with zonal electric backup and

○ geothermal water to water heat pumps with electric boiler backup

● Replacement of building waste and vent and domestic water piping

● Accessibility Upgrades

● Historic renovation

○ Building is listed on the Historic Register

● Envelope upgrades including façade repairs and re-roofing

● Other Sustainability items

PROJECT OVERVIEW – Goals & Objectives

Goals & Objectives

● Resiliency, Energy & Sustainability

○ P100 Baseline

○ NetZero Ready

○ Energy Use Intensity Target 16-37

○ LEED v4 Gold

○ Green Proving Ground Technology

○ Stretch Goals / Project Betterments

○ Operations and Maintenance

PROJECT OVERVIEW – Goals & Objectives

Design Build Procurement Overview

Christie VandenDries Contracting Officer

Disclaimer Nothing said/provided at this event is binding. Once released, only the solicitation and its attachments shall govern this acquisition.

CONSTRUCTION

MAGNITUDE

Between $20-$40 Million

● There are no stipends designated for this project.

Stipends

PHASE 1: TECHNICAL PROPOSALS

FY24

SOLICITATION

RELEASE

Phase 1:

Technical Approach Technical Qualifications No Price

Estimated date:

March/April 2024

Synopsis & Solicitation will be published to www.SAM.gov

TECHNICAL

PROPOSALS DUE

Estimated date:

April/May 2024 or 30 days after solicitation released

NOTICE OF SHORT

LIST OFFERORS

Not to exceed 3 offerors to proceed to Phase 2.

Estimated date:

June 2024

Factors:

1. Technical Qualifications (structural, mechanical, seismic, historic)

2. Approach to Design-Build

BOARD REVIEWS

TECHNICAL

PROPOSALS

Contracting Officer is assisted by numerous voting and non-voting members.

Typically includes SMEs across multiple disciplines, Project Manager, CMa

PHASE 2: TECHNICAL & PRICE PROPOSALS

FY24

PHASE 2

TECHNICAL &

PRICE

PROPOSALS DUE

Factors:

1. Design Concept

2. Key Personnel

3. Management Plan

4. Sustainability (15%)

5. Project Labor Agreement (15%)

All evaluation factors other than cost or price, when combined, are significantly more important than cost or price. All factors are scalable.

*Sustainability is a combination of go/no-go & weighted factors.*

SSEB EVALUATES

PROPOSALS

Includes all technical & cost realism analysis

REQUEST FINAL

PROPOSALS

Est. August 2024

FINAL SELECTION

CONTRACT

AWARD

Est. September/October 2024

DISCUSSIONS

CONCLUDE AND

FINAL

SELECTION

Contracting Officer is assisted by numerous voting and non-voting members.

Pay Attention:

● Page limits

● Project limitations

● All factors are addressed in the technical proposal

● ANDs / ORs

● Review LEC Requirements & provide feedback EARLY

A Cautionary Note About Factors

QUESTIONS?

File details come from the government source that posted it. Updated .