20231205 - Mansfield Industry Day Presentation.pdf
PDF 4 MB Posted
- Attached to
- INDUSTRY DAY - Mike Mansfield Federal Building/Courthouse Seismic Retrofit & Ltd Modernization Design/Build
- Solicitation number
- Not on record
About this file
This document provides an overview of an upcoming design-build solicitation for seismic retrofit and limited modernization work at the Mike Mansfield Federal Building/Courthouse in Butte, Montana. The General Services Administration Public Buildings Service Region 8 will issue the solicitation seeking proposals to perform a full building seismic retrofit, replace the HVAC systems with either air source variable refrigerant flow and electric backup or geothermal water-to-water heat pumps and electric boiler backup, replace building waste and vent and domestic water piping, complete accessibility upgrades, and conduct historic renovation and envelope upgrades including facade repairs and re-roofing. The solicitation is expected to be released in March/April 2024 with technical proposals due in April/May 2024. Up to three offerors will be shortlisted to submit technical and price proposals in Phase 2, with final selection and contract award anticipated in September/October 2024. Evaluation factors include technical approach, qualifications, design concept, key personnel, management plan, and sustainability. Sustainability and project labor agreement factors each account for 15% of the evaluation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WELCOME
GSA PUBLIC BUILDINGS SERVICE
INDUSTRY DAY
MIKE MANSFIELD FB/CH
SEISMIC RETROFIT & LTD SCOPE
December 5, 2023
Disclaimer Nothing said/provided at this event is binding. Once released, only the solicitation and its attachments shall govern this acquisition.
Project Overview
Steve Janzen Program Manager/COR
Disclaimer
Nothing said/provided at this conference is binding.
Once released, only the solicitation and its attachments shall govern this acquisition.
Mike Mansfield FB/CH
● 400 N. Main St, Butte, MT
Mike Mansfield Seismic Retrofit & Limited Modernization
Project Overview
● History/Background
● Site Context
● Project Goals / Objectives
Building Size
● Building Footprint: 157’ x 122’
(approximate)
● Basement, first floor, second, and third floors
● Second floor mechanical mezzanine on the light court
● Attic Space
● Gross building area: 58,850 sf (approximate)
PROJECT OVERVIEW – History / Background
Studies
● Past studies completed include;
● 2020 GSA R8 Feasibility Study
● Asbestos Re-Inspection Report, Pinyon Environmental, Inc., dated February 28, 2014.
● AHERA Asbestos Survey Report for Renovation Re-Inspection, Weecycle Environmental Consulting, Inc., dated September 1, 2017.
● Building Preservation Plan (BPP) by Andrews & Anderson Architects, dated July 2010-April 2011.
● 2023 Mansfield GSA R8 Program Dev Study and POR
● Upcoming–Seismic Materials & Lab Testing
PROJECT OVERVIEW – History / Background
Building Tenants
PROJECT OVERVIEW – Site Context
Goals & Objectives
● A full building seismic retrofit
● A complete replacement of building HVAC systems with these two options priced as the basis of design
○ air source vrf with zonal electric backup and
○ geothermal water to water heat pumps with electric boiler backup
● Replacement of building waste and vent and domestic water piping
● Accessibility Upgrades
● Historic renovation
○ Building is listed on the Historic Register
● Envelope upgrades including façade repairs and re-roofing
● Other Sustainability items
PROJECT OVERVIEW – Goals & Objectives
Goals & Objectives
● Resiliency, Energy & Sustainability
○ P100 Baseline
○ NetZero Ready
○ Energy Use Intensity Target 16-37
○ LEED v4 Gold
○ Green Proving Ground Technology
○ Stretch Goals / Project Betterments
○ Operations and Maintenance
PROJECT OVERVIEW – Goals & Objectives
Design Build Procurement Overview
Christie VandenDries Contracting Officer
Disclaimer Nothing said/provided at this event is binding. Once released, only the solicitation and its attachments shall govern this acquisition.
CONSTRUCTION
MAGNITUDE
Between $20-$40 Million
● There are no stipends designated for this project.
Stipends
PHASE 1: TECHNICAL PROPOSALS
FY24
SOLICITATION
RELEASE
Phase 1:
Technical Approach Technical Qualifications No Price
Estimated date:
March/April 2024
Synopsis & Solicitation will be published to www.SAM.gov
TECHNICAL
PROPOSALS DUE
Estimated date:
April/May 2024 or 30 days after solicitation released
NOTICE OF SHORT
LIST OFFERORS
Not to exceed 3 offerors to proceed to Phase 2.
Estimated date:
June 2024
Factors:
1. Technical Qualifications (structural, mechanical, seismic, historic)
2. Approach to Design-Build
BOARD REVIEWS
TECHNICAL
PROPOSALS
Contracting Officer is assisted by numerous voting and non-voting members.
Typically includes SMEs across multiple disciplines, Project Manager, CMa
PHASE 2: TECHNICAL & PRICE PROPOSALS
FY24
PHASE 2
TECHNICAL &
PRICE
PROPOSALS DUE
Factors:
1. Design Concept
2. Key Personnel
3. Management Plan
4. Sustainability (15%)
5. Project Labor Agreement (15%)
All evaluation factors other than cost or price, when combined, are significantly more important than cost or price. All factors are scalable.
*Sustainability is a combination of go/no-go & weighted factors.*
SSEB EVALUATES
PROPOSALS
Includes all technical & cost realism analysis
REQUEST FINAL
PROPOSALS
Est. August 2024
FINAL SELECTION
CONTRACT
AWARD
Est. September/October 2024
DISCUSSIONS
CONCLUDE AND
FINAL
SELECTION
Contracting Officer is assisted by numerous voting and non-voting members.
Pay Attention:
● Page limits
● Project limitations
● All factors are addressed in the technical proposal
● ANDs / ORs
● Review LEC Requirements & provide feedback EARLY
A Cautionary Note About Factors
QUESTIONS?