INDUSTRY DAY

Mud Mountain Dam Fish Passage Facility

Trucking Services

Enumclaw, WA

LOCATION:

USACE – Mud Mountain Dam Fish Passage Facility (MMD FPF)

25305 SE Mud Mountain RD

Enumclaw WA, 98022

DATE: May 21, 2021

TIME: 9:00 a.m. to 11:00 a.m. PST

The U.S. Army Corps of Engineers – Seattle District is hosting an Industry Day on May 21, 2021 at the Mud Mountain Dam (MMD) Fish Passage Facility (FPF), located in Enumclaw WA. The intent of the Industry Day is to provide more information on an upcoming requirement for trucking services at the newly constructed Fish Passage Facility. During Industry Day, Corps officials will provide an overview of the services needed to transport live fish that are collected at the FPF. Attending the Industry Day is “Not Mandatory” and is open to the entire vendor community. Please advise Vyacheslav (Slava) Govorushkin, Project Manager, at

Vyacheslav.V.Govorushkin@usace.army.mil or Casey Butcher at

Casey.J.Butcher@usace.army.mil of your plan to attend the Industry Day no later than 2:30 p.m., PST May 20th, 2021.

You must bring an official government picture identification to present in order to gain entry into the FPF. Registration and Citizenship Status: US Citizen (US Federal and/or State issued ID card required at check-in). In-processing for all vendors will begin near the Administrative Building that is located at the FPF. Please arrive a little early to allow enough time to check in. Parking will be available onsite near the Administrative Building.

Industry Day will take place from 9:00 a.m. to 11:00 a.m. at the MMD Fish Passage Facility, 25305 SE Mud Mountain RD, Enumclaw WA, 98022 near the Administrative Building. After touring the FPF, attendees will be allowed to view the Fish Release Site. The Fish Release Site is located approximately 12 miles upstream of the FPF. Vendors will be responsible for their own transportation from the FPF to the Fish Release Site.

***NOTE: Due to COVID requirements and social distancing, group size for in-person attendance is limited to twelve (12) people in total and we ask that only personnel essential to understanding the task attend in-person. Vendors will be required to wear the appropriate personal protective equipment (PPE), per CDC guidelines and Executive Order, the entire time they are on Federal property (even if outdoors). Additional information on the Executive Order on Protecting the Federal Workforce and Requiring Mask-wearing can be found here:

https://www.whitehouse.gov/briefing-room/presidential-actions/2021/01/20/executive-order-protecting-the-federal-workforce-and-requiring-mask-wearing/.

mailto:Vyacheslav.V.Govorushkin@usace.army.mil mailto:Casey.J.Butcher@usace.army.mil

INDUSTRY DAY

Enumclaw, WA

Participants will provide their own PPE, sanitize their hands when they get to the project, keep six-foot social distance, use a cloth face mask, and not attend if they feel sick or have a fever over 100.4 degrees. Required PPE for touring the FPF, per OSHA guidelines, includes the following: closed toed shoes, a hard hat, and a high visibility vest.

If you have any questions or concerns, please feel free to contact Tam Huynh via email at

Tam.C.Huynh@usace.army.mil.

A general scope overview is provided as an attachment.

Thank you for your interest and we look forward to your participation!

mailto:Tam.C.Huynh@usace.army.mil

General Scope for

Background Information:

The newly constructed Mud Mountain Dam (MMD) Fish Passage Facility (FPF) was put into service in 2021. The purpose of the FPF is to provide means of capturing live salmonids and transporting them to a release location upstream of the dam. The new FPF was constructed because the existing Fish Trap and trucking operation could not keep up with the increasing fish numbers mostly caused by population growth of pink salmon. The new FPF was supplied with five, 5200 gallon, fish transport trailers. During the peak of the fish run, typically starting in

August and concluding in October, the employees at the FPF do not have the staffing or the equipment necessary to haul all five trailers. A contract will be set up to supplement the government’s effort in transporting the fish transport trailers loaded with live fish.

Physical address of the MMD Fish Passage Facility is:

25305 SE Mud Mountain RD

Enumclaw WA, 98022

Services to be provided are:

Contractor shall provide up to 3 trucks with drivers for the performance of the work described below. Each truck must be capable of working up to 12 hours in a single day.

Trucking needs will vary day to day depending on factors such as fish run size, fish trap attraction success rate, equipment breakdowns, weather, etc. During peak operations, all 3 trucks may be utilized, working 12 hours a day 7 days a week. During slower periods, the number of trucks may vary between 0 and 3.

Government will determine the number of trucks required for each day. Contractor will be given

24-hour notice for truck mobilization(s). Contractor will be given 12-hour notice for truck demobilization(s).

Inability to meet the mobilization and demobilization requirements stated above will be grounds for termination of the contract.

Upon arrival to the Fish Passage Facility (FPF), the truck(s) will first hook up to the fish transport trailer(s). The daily activities will then include the cyclical repetition of the following procedures:

• At the FPF, fill the fish transport trailer with water

• Drive up to the fish trap and load trailer with live fish

• Drive to the Fish Release Site

• Hook up to the release chute

• Release fish

• Drive back to the FPF

Government employees will assist with filling fish transport trailers with water, loading of fish, and releasing of fish. Drivers may remain in their trucks during these tasks.

During the transportation of live fish, the drivers are required to monitor the dissolved oxygen levels within the fish transport trailer. When necessary, drivers shall make adjustments to maintain acceptable levels. This shall be performed via an electronic tablet device that is remotely synced to the trailer. The tablet will be handed to the driver upon coupling to the fish transport trailer. Need for adjustments is anticipated to be minimal.

Total distance for a round trip between the FPF and the Release Site is approximately 25 miles.

Requirements for the trucks are:

• Minimum 425 horsepower

• Minimum 12 speed transmission

• Capability to couple with fish transport trailer, to include all air and electrical connections. Trucks shall have two 7 pin trailer connectors

• Equipped with CB radios

• Capable of hauling 5,200-gallon fish transport trailer up 7% grade on state highway

• Must be in excellent working condition

• Insurance for truck and payload

Requirements for the drivers are:

• Class A CDL with tanker endorsement

• Able to pass background check

• Follow traffic laws

This contract is estimated for a total of 1,680 hours. Due to the unknown size of the fish run and other factors described earlier, use of all hours is not guaranteed.

1. MMD FPF Industry Day_Rev_4May21
2. General Scope for MMD FPF fish transport_Rev 4May21
3. MUD MOUNTAIN 5200 Gallon Fish Transport specs

File details come from the government source that posted it. Updated .