This is a bid set and specifications document from the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration for the Traverse City State Office Building Bathroom & Piping Upgrade Project (File No. 171/23058.RLO). The project includes facility bathroom renovations, plumbing sanitary and water piping replacement, and associated plumbing, mechanical, and electrical improvements at 701 S. Elmwood, Traverse City, Michigan. The work encompasses multiple divisions including selective demolition, concrete, masonry, metals, carpentry, thermal protection, doors and windows, finishes, specialties, fire protection, plumbing, mechanical, and electrical systems across all building levels. A mandatory pre-bid conference is scheduled for July 20, 2026 at 11:00 a.m. ET at the project site, with an optional facility tour immediately following. Bids are due electronically through the SIGMA VSS system by 2:00 p.m. ET on August 5, 2026. The bid hold period is 60 calendar days after bid opening. The Apparent Low Bidder must submit qualification submittals including a pre-award schedule, list of subcontractors, and other documentation within specified timeframes following the professional's request.

Bid security of five percent (5%) of the bidder's base bid is required, submitted as a certified or cashier's check or money order to the State Facilities Administration Design & Construction Division in Lansing, Michigan, or through SIGMA as per standard bidding procedures. All bids must include sales and use taxes, tariffs, and the cost of all required permits, approvals, licenses, and fees. The contract documents include performance bonds, payment bonds, and compliance with prevailing wage requirements as specified in the appendices. Bidders are responsible for examining the bidding documents, visiting the site, understanding all site conditions, complying with applicable Michigan and federal laws including soil erosion and sedimentation control requirements, and accounting for all costs associated with performing the work. The owner reserves the right to reject any or all bids, waive irregularities, issue post-bid addenda for rebidding without re-advertising, or take any other appropriate action in its sole discretion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF MICHIGAN

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

STATE FACILITIES ADMINISTRATION

File No. 171/23058.RLO

DTMB

State of Michigan Office Building Bathroom & Piping Upgrade Project

701 S. Elmwood Traverse City, MI

BID SET:

June 26, 2026

STATE OF MICHIGAN TABLE OF CONTENTS

Project Name: TC State Office Bldg File No. 171/23058.RLO

KTA-216007C 00010 − 1

Copyright 6/26/2026

SECTION 00010 TABLE OF CONTENTS

SECTION/PAGE NO.

SUBJECT INDEX

SECTION 00020 GLOSSARY ............................................................................................................................................. 00020 - 1 SECTION 00030 ADVERTISEMENT .................................................................................................................................. 00030 - 1 SECTION 00100 INSTRUCTIONS TO BIDDERS ............................................................................................................... 00100 - 1 ARTICLE 1 BIDDING DOCUMENT INTERPRETATIONS .................................................................................................. 00100 - 2 ARTICLE 2 QUALIFICATIONS OF BIDDERS ..................................................................................................................... 00100 - 2 ARTICLE 3 BIDDING DOCUMENTS; SITE CONDITIONS; SAFETY REQUIREMENTS; LAWS ....................................... 00100 - 2 ARTICLE 4 INTERPRETATIONS; ADDENDA .................................................................................................................... 00100 - 4 ARTICLE 5 BID SECURITY ................................................................................................................................................ 00100 - 4 ARTICLE 6 CONTRACT TIME; LIQUIDATED DAMAGES .................................................................................................. 00100 - 5 ARTICLE 7 MATERIALS AND EQUIPMENT ...................................................................................................................... 00100 - 5 ARTICLE 8 SUBCONTRACTORS ...................................................................................................................................... 00100 - 6 ARTICLE 9 BID FORM AND BID FORM ATTACHMENTS ................................................................................................. 00100 - 7 ARTICLE 10 PREPARATION AND SUBMISSION OF BIDS.................................................................................................. 00100 - 7 ARTICLE 11 BID WITHDRAWAL; BID MODIFICATION ........................................................................................................ 00100 - 8 ARTICLE 12 BID OPENING; OBJECTION TO THE AWARD ................................................................................................ 00100 - 9 ARTICLE 13 BIDS TO REMAIN OPEN .................................................................................................................................. 00100 - 9 ARTICLE 14 AWARD OF THE CONTRACT .......................................................................................................................... 00100 - 9 ARTICLE 15 EXECUTION OF THE AGREEMENT ............................................................................................................. 00100 - 12 ARTICLE 16 MOBILIZATION PAY ITEM ............................................................................................................................. 00100 -12 ARTICLE 17 SOIL EROSION AND SEDIMENTATION CONTROL–FINE FOR NON-COMPLIANCE-NOT APPLICABLE .. 00100 -13 ATTACHMENT A TO SECTION 00100: BIDDER'S CHECK LIST........................................................................................ 00110 - 1 SECTION 00120 SUPPLEMENTARY INSTRUCTIONS ..................................................................................................... 00120 - 1 MILESTONE PROJECT SCHEDULE ..................................................................................................................................... 00120 - 1 SECTION 00210 INFORMATION FOR BIDDERS .............................................................................................................. 00210 - 1 SECTION 00300 BID SUMMARY ....................................................................................................................................... 00300 - 1 SECTION 00300 BID FORM ............................................................................................................................................... 00300 - 2 ARTICLE 1 THIS BID IS SUBMITTED TO THE STATE OF MICHIGAN ("THE OWNER"). ................................................. 00300 - 2 ARTICLE 2 THE BIDDER'S REPRESENTATIONS ............................................................................................................... 00300 - 2 ARTICLE 3 TIME OF COMPLETION ..................................................................................................................................... 00300 - 3 ARTICLE 4 ATTACHMENTS INCLUDED WITH THIS BID .................................................................................................... 00300 - 3 ARTICLE 5 DEFINED TERMS ............................................................................................................................................... 00300 - 3 ARTICLE 6 BID SCHEDULE .................................................................................................................................................. 00300 - 4 ARTICLE 7 SCHEDULE OF CHANGE ORDER PRICES ...................................................................................................... 00300 - 6 ARTICLE 8 BID SUBMITTED ON ......................................................................................................................................... 00300 - 7 SECTION 00310 BID BOND ............................................................................................................................................... 00310 - 1 SECTION 00320 NONCOLLUSION AFFIDAVIT ............................................................................................................... 00320 – 1 SECTION 00330 ASBESTOS ABATEMENT ATTESTATION........................................................................................... 00330 – 1 SECTION 00410 BID BREAKDOWN ................................................................................................................................. 00410 - 1 SECTION 00420 QUESTIONNAIRE ................................................................................................................................... 00420 - 1 ARTICLE 1 ORGANIZATION ............................................................................................................................................... 00420 - 1 ARTICLE 2 SPECIALTY CONTRACTOR LICENSES .......................................................................................................... 00420 - 1 ARTICLE 3 EXPERIENCE ................................................................................................................................................... 00420 - 1 ARTICLE 4 ADDITIONAL QUALIFICATIONS ...................................................................................................................... 00420 - 2 ARTICLE 5 REFERENCES .................................................................................................................................................. 00420 - 2 REFERENCES ATTACHMENT ......................................................................................................................... 00420 - 3 SECTION 00430 LIST OF SUBCONTRACTORS ............................................................................................................... 00430 - 1 SECTION 00440 SCHEDULE OF MATERIALS AND EQUIPMENT .................................................................................. 00440 - 1 ARTICLE 1 BID MATERIALS AND EQUIPMENT −LISTED (NAMED OR SPECIFIED) ITEMS ........................................... 00440 - 1 ARTICLE 2 BID MATERIALS AND EQUIPMENT − OPEN SPECIFICATIONS .................................................................... 00440 - 2 SECTION 00500 AGREEMENT .......................................................................................................................................... 00500 - 1 ARTICLE 1 THE CONTRACT; THE PROJECT; THE WORK .............................................................................................. 00500 - 1

KTA-216007C 00010 − 2

ARTICLE 2 CONTRACT DOCUMENTS .............................................................................................................................. 00500 - 1 ARTICLE 3 CONTRACT PRICE ........................................................................................................................................... 00500 - 2 ARTICLE 4 CONTRACT TIME; LIQUIDATED DAMAGES ................................................................................................... 00500 - 2 ARTICLE 5 PAYMENTS TO CONTRACTOR ...................................................................................................................... 00500 - 3 ARTICLE 6 THE PROFESSIONAL SERVICES CONTRACTOR ......................................................................................... 00500 - 4 ARTICLE 7 CONTRACTOR'S REPRESENTATIONS .......................................................................................................... 00500 - 4 ARTICLE 8 MISCELLANEOUS ............................................................................................................................................ 00500 - 4 ARTICLE 9 NOTICE AND SERVICE .................................................................................................................................... 00500 - 5 SECTION 00520 ATTACHMENT “A” TO AGREEMENT – NOT APPLICABLE ................................................................. 00520 - 1 SECTION 00610 PERFORMANCE BOND ........................................................................................................................ 00610 - 1 SECTION 00620 PAYMENT BOND ................................................................................................................................... 00620 - 1 SECTION 00700 GENERAL CONDITIONS ........................................................................................................................ 00700 - 1 ARTICLE 1 INTERPRETATIONS ........................................................................................................................................... 00700 - 1

1.1 Section 00020 Glossary:............................................................................................................................................... 00700 - 1

1.2 Intent of the Contract Documents: ................................................................................................................................ 00700 - 1

1.3 Priority of the Contract Documents: ....... 00700 - 2

1.4 Interpretation of Indemnification Provisions: ................................................................................................................. 00700 - 3

1.5 Additional Interpretations: ............................................................................................................................................. 00700 - 3

1.6 Ownership and Use of the Contract Documents: .......................................................................................................... 00700 - 3

1.7 Copies of the Contract Documents: .............................................................................................................................. 00700 - 4

ARTICLE 2 THE OWNER−GENERAL PROVISIONS .......................................................................................................... 00700 - 4

2.1 Availability of Lands, Areas, Properties and Facilities: ................................................................................................. 00700 - 4

2.2 Reference Points; Base Lines and Benchmarks: .......................................................................................................... 00700 - 4

2.3 Stop Work Order: .......................................................................................................................................................... 00700 - 4

2.4 Limitations on the Owner’s Responsibilities: ................................................................................................................ 00700 - 4

2.5 Additional General Provisions: ...................................................................................................................................... 00700 - 5

2.6 Partnering Charter: ....................................................................................................................................................... 00700 - 5

ARTICLE 3 THE PROFESSIONAL − GENERAL PROVISIONS .......................................................................................... 00700 - 5

3.1 Owner’s Representative: ............................................................................................................................................. 00700 - 5

3.2 Clarifications and Interpretations: ................................................................................................................................. 00700 - 5

3.3 Minor Variations and No-Cost Changes; Minor Delays:................................................................................................ 00700 - 6

3.4 Determinations by the Professional: ........................................................................................................................... 00700 - 6

3.5 Limitations on the Professional’s Responsibilities: ....................................................................................................... 00700 - 6

ARTICLE 4 CONTROL OF WORK − GENERAL PROVISIONS ........................................................................................... 00700 - 6

4.1 Review of the Contract Documents: ............................................................................................................................. 00700 - 6

4.2 Management, Supervision, and Personnel: .................................................................................................................. 00700 - 6

4.3 Materials and Equipment: ............................................................................................................................................. 00700 - 7

4.4 Concerning Control of Work: ........................................................................................................................................ 00700 - 7

4.5 Patent Fees and Royalties: ........................................................................................................................................... 00700 - 8

4.6 Use of Premises: .......................................................................................................................................................... 00700 - 8

4.7 Record Documents: ...................................................................................................................................................... 00700 - 9

4.8 Emergencies: ................................................................................................................................................................ 00700 - 9

4.9 Indemnification: ............................................................................................................................................................ 00700 - 9

ARTICLE 5 SUBCONTRACTORS AND SUPPLIERS ........................................................................................................ 00700 - 10

5.1 Employment of Subcontractors: .................................................................................................................................. 00700 - 10

5.2 "Or Equal" and Substitute Materials and Equipment:.................................................................................................. 00700 - 10

5.3 The Contractor’s Continuing Responsibilities: .......................................................................................................... 00700 - 11

ARTICLE 6 SUBMITTALS .................................................................................................................................................. 00700 - 11

6.1 Shop Drawing, Sample and Other Technical Submittals: ........................................................................................... 00700 - 11

6.2 Review and Return of Technical Submittals: .............................................................................................................. 00700 - 12

6.3 Progress Schedule Submittals: ................................................................................................................................... 00700 - 12

6.4 Review and Return of Progress Schedule Submittals: ............................................................................................... 00700 - 13

6.5 Additional Provisions Concerning Submittals: ............................................................................................................ 00700 - 13

ARTICLE 7 LEGAL REQUIREMENTS; INSURANCE ........................................................................................................ 00700 - 13

7.1 Laws; Permits (Which Include Approvals and Licenses): ........................................................................................... 00700 - 13

7.2 Sales and Use Tax and Other Similar Taxes, including Tariffs: .................................................................................. 00700 - 14

7.3 Safety and Protection: ................................................................................................................................................ 00700 - 14

KTA-216007C 00010 − 3

7.4 Bonds and Insurance - General Requirements: .......................................................................................................... 00700 - 15

7.5 The Contractor’s Liability Insurance:......................................................................................................................... 00700 - 15

7.6 Pollution Liability Insurance: ....................................................................................................................................... 00700 - 16

7.7 Property Insurance (Builder's All Risk Insurance): ...................................................................................................... 00700 - 16

7.8 Waiver of Rights: ........................................................................................................................................................ 00700 - 16

7.9 Receipt and Application of Proceeds: ......................................................................................................................... 00700 - 16

7.10 Unfair Labor Practice: ................................................................................................................................................. 00700 - 17

7.11 Michigan Right-To-Know Law: .................................................................................................................................... 00700 - 17

7.12 Nondiscrimination: ...................................................................................................................................................... 00700 - 17

7.13 Michigan Residency for Employees: ........................................................................................................................... 00700 - 18

7.14 Prevailing Wages: ....................................................................................................................................................... 00700 - 18

7.15 Asbestos Abatement:.................................................................................................................................................. 00700 - 19

ARTICLE 8 PROSECUTION; SUBSTANTIAL COMPLETION ........................................................................................... 00700 - 20

8.1 Starting the Work: ....................................................................................................................................................... 00700 - 20

8.2 Revision 0 (Rev. 0) Schedule and Cost Submittals: ................................................................................................... 00700 - 20

8.3 Compliance with Contract Time Requirements: .......................................................................................................... 00700 - 20

8.4 Substantial Completion: .............................................................................................................................................. 00700 - 20

8.5 Partial Use: ................................................................................................................................................................. 00700 - 21

8.6 Division of Responsibilities: ........................................................................................................................................ 00700 - 21

8.7 Suspension of Work: .................................................................................................................................................. 00700 - 21

8.8 Sharing of Total Float on Non-Critical Paths: .............................................................................................................. 00700 - 22

ARTICLE 9 WARRANTY; TESTS, INSPECTIONS, AND

APPROVALS; CORRECTION OF WORK ....................................................................................................... 00700 - 22

9.1 Warranty: ................................................................................................................................................................... 00700 - 22

9.2 Tests, Inspections and Approvals: ............................................................................................................................. 00700 - 22

9.3 Uncovering Work: ...................................................................................................................................................... 00700 - 23

9.4 Correction of Work: .................................................................................................................................................... 00700 - 23

9.5 Special Correction Period Requirements: .................................................................................................................. 00700 - 24

9.6 Special Maintenance Requirements: ......................................................................................................................... 00700 - 24

ARTICLE 10 CHANGES ..................................................................................................................................................... 00700 - 24

10.1 Changes in the Work: ................................................................................................................................................ 00700 - 24

10.2 Differing Subsurface or Physical Site Conditions: ...................................................................................................... 00700 - 25

10.3 Responsibilities for Underground Utilities: ................................................................................................................. 00700 - 26

10.4 Hazardous Material Conditions: ................................................................................................................................. 00700 - 26

10.5 Incidents with Archaeological Features: .................................................................................................................... 00700 - 26

10.6 Unit Price Work: ......................................................................................................................................................... 00700 - 27

10.7 Cash Allowances; Provisionary Allowances: ............................................................................................................. 00700 - 27

10.8 Change Orders; Change Authorizations: ................................................................................................................... 00700 - 27

ARTICLE 11 CHANGES IN CONTRACT PRICE; CHANGES IN

CONTRACT TIME ......................................................................................................................................... 00700 - 28

11.1 General Provisions: ................................................................................................................................................... 00700 - 28

11.2 Changes in Contract Time: ........................................................................................................................................ 00700 - 28

11.3 Methods for Making Adjustments in Contract Price: .................................................................................................. 00700 - 29

11.4 Labor, Subcontract and Material/Equipment Costs: .................................................................................................. 00700 - 29

11.5 Construction Equipment Costs: ................................................................................................................................. 00700 - 30

11.6 Rented or Leased Construction Equipment: .............................................................................................................. 00700 - 30

11.7 Owned Construction Equipment: ............................................................................................................................... 00700 - 30

11.8 General Conditions Costs: ......................................................................................................................................... 00700 - 30

11.9 Limitations on Allowable Costs: ................................................................................................................................. 00700 - 31

11.10 Costs Covered by the Fee for the Work Involved (and not Allowable as Cost of the Work Involved): ....................... 00700 - 31

11.11 Limits on the Fee for the Work Involved: ................................................................................................................... 00700 - 32

11.12 Fee for Unabsorbed Home Office Overhead: ............................................................................................................ 00700 - 32

11.13 Changes in Contract Time for Early Completion: ....................................................................................................... 00700 - 33

11.14 Access to Records: .................................................................................................................................................... 00700 - 33

11.15 Price Reduction for Defective Cost and Pricing Data: ............................................................................................... 00700 - 33

ARTICLE 12 PROGRESS PAYMENTS; FINAL PAYMENT ............................................................................................... 00700 - 34

12.1. Schedule of Values: ................................................................................................................................................... 00700 - 34

12.2 Requests for Payment: .............................................................................................................................................. 00700 - 34

12.3 Review of Request for Payment; Intent of Review: .................................................................................................... 00700 - 35

12.4 Refusal to Make or to Recommend Payment: ........................................................................................................... 00700 - 35

KTA-216007C 00010 − 4

12.5 Final Request for Payment: ....................................................................................................................................... 00700 - 35

12.6 Final Payment and Acceptance: ................................................................................................................................ 00700 - 36

12.7 Contractor’s Continuing Obligation: ......................................................................................................................... 00700 - 36

12.8 Waiver of Claims: ...................................................................................................................................................... 00700 - 36

ARTICLE 13 OTHER WORK .............................................................................................................................................. 00700 - 36

13.1 Related Work at Site: ................................................................................................................................................. 00700 - 36

13.2 Coordination Requirements: ...................................................................................................................................... 00700 - 37

13.3 Claims Between the Contractor and Other Parties: ................................................................................................. 00700 - 37

ARTICLE 14 TERMINATION .............................................................................................................................................. 00700 - 38

14.1 Notice Requiring Assurance of Due Performance: .................................................................................................... 00700 - 38

14.2 Contractor Default and Termination for Cause: ........................................................................................................ 00700 - 38

14.3 Surety Default: ........................................................................................................................................................... 00700 - 39

14.4 Termination for Convenience of the Owner: .............................................................................................................. 00700 - 39

14.5 The Contractor May Suspend Work: ........................................................................................................................ 00700 - 40

ARTICLE 15 DISPUTES .................................................................................................................................................... 00700 - 40

15.1 Claims Under This Article: ......................................................................................................................................... 00700 - 40

15.2 Requirement for Certification of Contractor Claims: ................................................................................................. 00700 - 41

15.3 Recommendations or Decisions from the Professional:........................................................................................... 00700 - 41

15.4 Determinations by the Director-DCD: ....................................................................................................................... 00700 - 41

15.5 Supplements to AAA Arbitration: ............................................................................................................................... 00700 - 42

15.6 Interest on a Judgment; Payment of Judgment: ........................................................................................................ 00700 - 42

15.7 Venue; Flow-Through Provision: ............................................................................................................................... 00700 - 42

SECTION 00800 SUPPLEMENTARY CONDITIONS ......................................................................................................... 00800 - 1

1.1 Construction Testing and Inspections .......................................................................................................................... 00800 – 1

SECTION 01310 PROGRESS SCHEDULE ........................................................................................................................ 01310 - 1

GENERAL SPECIFICATIONS – BOUND WITHIN

DIVISION 1 -- GENERAL REQUIREMENTS ....................................................................................................................... 010000 - 1

011000.01 - CONTRACTOR CERTIFICATION OF ASBESTOS-FREE PRODUCT INSTALLATION FORM

011000.02 – REQUEST FOR INFORMATION FORM (RFI)

011001 - SUBSTITUTION REQUEST FORM

011004 – ELECTRONIC FILE TRANSFER POLICY

013301 – STATEMENT OF SPECIAL INSPECTIONS

DIVISION 2 -- SITE CONSTRUCTION ................................................................................................................................ 020000 - 1

020101 – ASBESTOS SURVEY REPORT

020101 – ASBESTOS SURVEY: PRE-RENOVATION

024100 – SELECTIVE DEMOLITION

DIVISION 3 -- CONCRETE .................................................................................................................................................. 030000 - 1

033000 - CAST-IN-PLACE CONCRETE

DIVISION 4 – MASONRY .................................................................................................................................................... 040000 - 1

042000 – UNIT MASONRY

DIVISION 5 -- METALS ........................................................................................................................................................ 050000 - 1

055000 - METAL FABRICATIONS

DIVISION 6 -- WOOD AND PLASTICS ............................................................................................................................... 060000 - 1

061000 - ROUGH CARPENTRY

062000 - FINISH CARPENTRY

064100 – ARCHITECTURAL WOOD CASEWORK

DIVISION 7 -- THERMAL AND MOISTURE PROTECTION ................................................................................................ 070000 - 1

072100 – THERMAL INSULATION

078443 – JOINT FIRESTOPPING

079005 - JOINT SEALERS

DIVISION 8 -- DOORS AND WINDOWS ............................................................................................................................. 080000 - 1

081416 – FLUSH WOOD DOORS

083113 - ACCESS DOORS AND FRAMES

087100 - DOOR HARDWARE

088300 - MIRRORS

KTA-216007C 00010 − 5

DIVISION 9 -- FINISHES ...................................................................................................................................................... 090000 - 1

092116 - GYPSUM BOARD ASSEMBLIES

093000 – TILING

095100 – ACOUSTIC CEILINGS

096813 – CARPET TILE

099000 - PAINTS AND COATINGS

DIVISION 10 -- SPECIALTIES ............................................................................................................................................. 100000 - 1

101423 – BUILDING SIGNAGE

102800 – TOILET ACCESSORIES

DIVISION 11 – EQUIPMENT – NOT USED

DIVISION 12 – FURNISHINGS ............................................................................................................................................ 120000 - 1

123600 – SOLID SURFACING SILLS

DIVISION 13 – SPECIALTIES ............................................................................................................................................. 130000 - 1

134802 – SOUND CONTROL COMPONENTS

DIVISION 21 – FIRE PROTECTION .................................................................................................................................... 210000 - 1

21 05 00 – COMMON WORK RESULTS FOR FIRE SUPPRESSION

21 13 00 - FIRE-SUPPRESSION SPRINKLER SYSTEMS

DIVISION 22 – PLUMBING .................................................................................................................................................. 220000 - 1

220000 – PLUMBING GENERAL PROVISIONS

220010 – PLUMBING EQUIPMENT AND MATERIALS

220517 - PLUMBING SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING

220553 – IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

220719 – PLUMBING PIPING INSULATION

221005 – PLUMBING PIPING

221006 – PLUMBING PIPING SPECIALTIES

223000 – PLUMBING EQUIPMENT

224000 – PLUMBING FIXTURES

DIVISION 23 – MECHANICAL ............................................................................................................................................. 230000 - 1

230000 - MECHANICAL GENERAL PROVISIONS

230010 - MECHANICAL EQUIPMENT AND MATERIALS

230510 – PENETRATION FIRESTOPPING FOR HVAC

230548 – VIBRATION CONTROLS FOR MECHANICAL PIPING AND EQUIPMENT

230553 – MECHANICAL IDENTIFICATION FOR PIPING AND EQUIPMENT

230593 – TESTING, ADJUSTING BALANCING FOR HVAC

230713 – DUCT INSULATION

230719 – PIPING INSULATION

231123 – FACILITY NATURAL GAS PIPING

232113 – HYDRONIC PIPING

233100 – HVAC DUCTS AND CASINGS

233300 – AIR DUCT ACCESSORIES

233423 – HVAC POWER VENTILATORS

233700 – AIR OUTLETS AND INLETS

238200 – CONVECTION HEATING AND COOLING UNITS

DIVISION 26 – ELECTRICAL .............................................................................................................................................. 260000 - 1

260000 – ELECTRICAL GENERAL PROVISIONS

260010 – ELECTRICAL EQUIPMENT AND MATERIALS

260050 - BASIC MATERIALS AND METHODS

260505 – ELECTRICAL DEMOLITION

260526 – GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260924 – LIGHTING CONTROL DEVICES – VACANCY/OCCUPANCY SENSORS

262726 – WIRING DEVICES

265100 – INTERIOR LIGHTING

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY ................................................................................................... 280000 - 1

283100 – ADDRESSABLE LIFE SAFETY SYSTEM REVISIONS

APPENDIX I – SPECIAL WORKING CONDITIONS ........................................................................................ APPENDIX I-00800 - 1 DTMB State Facilities ....................................................................................................................................... APPENDIX I-00800 - 2 Department of Health and Human Services ..................................................................................................... APPENDIX I-00800 - 4

KTA-216007C 00010 − 6

APPENDIX II – SPECIAL PROJECT PROCEDURES .................................................................................... APPENDIX II-00800 - 1 Demolition/Remodeling Project Procedures .................................................................................................... APPENDIX II-00800 - 2 Hazardous Materials Project Procedures ........................................................................................................ APPENDIX II-00800 - 3 Asbestos Abatement Project Procedures ........................................................................................................ APPENDIX II-00800 - 4 Lead Abatement Materials Project Procedures ............................................................................................... APPENDIX II-00800 - 5

APPENDIX III – PREVAILING WAGE RATE SCHEDULE ............................................................................ APPENDIX III-00800 - 1

DRAWINGS - BOUND SEPARATELY

SHEET TITLE

T100 COVER SHEET AND PROJECT TEAM

A100 GENERAL INFO, WALL TYPES, ABBREVIATIONS AND SYMBOLS

A101 ROOM FINISH SCHEDULE, DOOR SCHEDULE AND DOOR DETAILS

A200 OVERALL TUNNEL AND GROUND LEVEL

A201 OVERALL LEVELS 1 AND 2

A202 OVERALL LEVELS 3 AND 4

A203 GROUND LEVEL – NORTH WING

A204 GROUND LEVEL – SOUTH WING

A205 LEVEL 1 – NORTH WING

A206 LEVEL 1 – SOUTH WING

A207 LEVEL 1 – EAST WING

A208 LEVEL 2 – NORTH WING

A209 LEVEL 2 – SOUTH WING

A210 LEVEL 2 – EAST WING

A211 LEVEL 3 – NORTH WING

A212 LEVEL 3 – SOUTH WING

A213 LEVEL 3 – EAST WING

A214 LEVEL 4 – NORTH WING

A215 LEVEL 4 – SOUTH WING

A216 LEVEL 4 – EAST WING

FP200 FIRE PROTECTION OVERALL TUNNEL AND GROUND LEVEL

FP201 FIRE PROTECTION OVERALL LEVELS 1 AND 2

FP202 FIRE PROTECTION OVERALL LEVELS 3 AND 4

P100 PLUMBING SYMBOL LEGEND AND ABBREVIATIONS

PD200 PLUMBING DEMOLITION OVERALL TUNNEL AND GROUND LEVEL

PD201 PLUMBING DEMOLITION OVERALL LEVELS 1 AND 2

PD202 PLUMBING DEMOLITION OVERALL LEVELS 3 AND 4

P200 PLUMBING OVERALL TUNNEL AND GROUND LEVEL

P201 PLUMBING OVERALL LEVELS 1 AND 2

P202 PLUMBING OVERALL LEVELS 3 AND 4

P203 PLUMBING GROUND LEVEL – NORTH AND SOUTH WINGS

P204 PLUMBING LEVEL 1 – NORTH, SOUTH AND EAST WINGS

P205 PLUMBING LEVEL 2 – NORTH, SOUTH AND EAST WINGS

P206 PLUMBING LEVEL 3 – NORTH, SOUTH AND EAST WINGS

P207 PLUMBING LEVEL 4 – NORTH, SOUTH AND EAST WINGS

P300 PLUMBING SANITARY AND WATER RISERS

P301 PLUMBING SCHEDULES AND DETAILS

P302 PLUMBING SCHEDULES AND DETAILS

M100 MECHANICAL SYMBOL LEGEND AND ABBREVIATIONS

MD200 MECHANICAL DEMOLITION OVERALL GROUND LEVEL

MD201 MECHANICAL DEMOLITION OVERALL LEVELS 1 AND 2

MD202 MECHANICAL DEMOLITION OVERALL LEVELS 3 AND 4

M200 MECHANICAL OVERALL GROUND LEVEL

M201 MECHANICAL OVERALL LEVELS 1 AND 2

M202 MECHANICAL OVERALL LEVELS 3 AND 4

M203 MECHANICAL GROUND LEVEL – NORTH AND SOUTH WINGS

KTA-216007C 00010 − 7

M204 MECHANICAL LEVEL 1 – NORTH, SOUTH AND EAST WINGS

M205 MECHANICAL LEVEL 2 – NORTH, SOUTH AND EAST WINGS

M206 MECHANICAL LEVEL 3 – NORTH, SOUTH AND EAST WINGS

M207 MECHANICAL LEVEL 4 – NORTH, SOUTH AND EAST WINGS

M300 MECHANICAL VENTILATION RISER PLAN

M301 MECHANICAL SCHEDULES AND DETAILS

M302 MECHANICAL SCHEDULES AND DETAILS

E000 ELECTRICAL LEGEND AND DETAILS

E200 ELECTRICAL OVERALL TUNNEL AND GROUND LEVEL

E201 ELECTRICAL OVERALL LEVELS 1 AND 2

E202 ELECTRICAL OVERALL LEVELS 3 AND 4

E203 ELECTRICAL GROUND LEVEL – NORTH AND SOUTH WINGS

E204 ELECTRICAL LEVEL 1 – NORTH, SOUTH AND EAST WINGS

E205 ELECTRICAL LEVEL 2 – NORTH, SOUTH AND EAST WINGS

E206 ELECTRICAL LEVEL 3 – NORTH, SOUTH AND EAST WINGS

E207 ELECTRICAL LEVEL 4 – NORTH, SOUTH AND EAST WINGS

E300 ELECTRICAL PANEL SCHEDULES

E301 ELECTRICAL PANEL SCHEDULES

E302 ELECTRICAL PANEL SCHEDULES

E303 ELECTRICAL PANEL SCHEDULES

E304 ELECTRICAL PANEL SCHEDULES

E305 ELECTRICAL EXISTING RISER DIAGRAM

STATE OF MICHIGAN GLOSSARY

KTA-216007C 00020 - 1

SECTION 00020 GLOSSARY

1.1 Defined Terms:

1.1.1. The following terms or relative pronouns used in Division 0 of the Specifications have these intent and meanings:

Activity− An element in the Progress Schedule establishing a requisite step, or the time and resources required, for completing the part of the Work associated with that Activity.

Addenda− Written instruments that are used by the Owner and/or Professional to incorporate interpretations or clarifications, modifications, and other information into the Bidding Documents. An Addendum issued after Bid opening to those Bidders who submitted a Bid, for the purpose of rebidding the Work without readvertising, is referred to as a post-Bid Addendum.

Agreement− The written agreement between the Owner and Contractor covering the Work to be furnished and performed.

Alternate− Refers to Work specified in the Bidding Documents for which the Bidder shall bid a Bid Price in the space provided in the Schedule of Alternates in Section 00300 Bid Form.

Apparent Low Bidder:- Those Bidders whose Base Bid, when added to those specific Alternates the Owner intends to accept, yields the three lowest sums of Base Bid and Alternates. Additional Bidders may be considered Apparent Low Bidders if their Base Bid, when added to those specific Alternates the Owner intends to accept, yields a sum within 10% of the lowest of the Apparent Low Bidder’s sum. If a qualified disabled veteran meets the requirements of the contract solicitation and with the veteran’s preference is the lowest Bidder is considered the Apparent Low Bidder.

Archaeological Feature− Any prehistoric or historic deposit of archaeological value, as determined by a representative of a State agency that is duly authorized to evaluate such findings and render such judgments. An Archaeological Feature deposit may include, but is not limited to Indian habitations, ceremonial sites, abandoned settlements, treasure trove, artifacts, or other objects with intrinsic archaeological value and that relate to the history and culture of the State of Michigan.

As-Planned Schedule− The Contractor’s Revision 0 Progress Schedule returned to the Contractor as "Resubmittal Not Required," with or without comments or objections noted.

Authorized Technical Data− Information and data contained in a report of exploration and tests of subsurface conditions that are expressly designated in paragraph 2.0 of Section 00210 Information for Bidders. Also, any physical data (dimension, location, conditions, etc.) contained in those drawings of physical conditions of existing surface and subsurface facilities identified in paragraph

3.0 of Section 00210 Information for Bidders.

Bar Chart Schedule− Activity schedule, in a bar chart format, that accounts for the entire Work at a level of detail commensurate with the Progress Schedule requirements of the Contract Documents.

Bid− Written offer by a Bidder for the Work, as specified, which designates the Bidder’s Base Bid and Bid Prices for all Alternates.

The term Bid includes a Rebid.

Bidder− The Person acting directly, or through an authorized representative, who submits a Bid directly to the Owner.

Bidding Documents− The proposed Contract Documents as advertised, and all Addenda issued before Bid opening, and after Bid opening, if the Work is rebid without readvertising.

Bid Price− The Bidder's price for a lump sum item of Work, or the product of the Bidder's unit price for an item of Unit Price Work times the quantity given on the Bid Form for that item.

Bid Security− A security serving as a guarantee that the Bidder will conform to all conditions requisite for its return or as liquidated damages in the event of failure or refusal to conform.

Bidding Requirements− The Advertisement, Instructions to Bidders (including Attachment A), Supplementary Instructions, Information for Bidders, Bid Form, Bid Form Attachments and Qualification Submittals, as advertised and as modified by Addenda, and any other Section included within Division 0 of the Bidding Documents for the purpose of governing bidding and award of the Contract.

*AD Board− The Administrative Board of the State of Michigan.

KTA-216007C 00020 - 2

Bonds− Section 00310 Bid Bond, Section 00610 Performance Bond and Section 00620 Payment Bond are security furnished by the Contractor, as required by the Contract Documents.

Business Day− Any Day except Saturdays, Sundays and holidays observed by the Owner.

Bulletin− A standard DTMB or other PSC form used by the PSC & Owner to describe a change in the Work under consideration by the Owner and to request the Contractor to submit a proposal for the corresponding adjustment in Contract Price and/or Contract Time, if any.

Calendar Day− Every day shown on the calendar, Saturdays, Sundays, and holidays included.

Cash Allowance− An Owner-specified sum included within the Contract Price to reimburse the Contractor for the actual purchase/furnished cost of materials and/or equipment or other designated items, as specifically provided in the Contract Documents.

Although the scope (e.g., the required quantity) of any Work covered by a Cash Allowance is sufficiently detailed in the Contract Documents for the purposes of bidding the required labor costs, Subcontract costs, construction equipment costs and general conditions costs and Fee, it is understood that the required materials, equipment or other designated items are of uncertain purchase cost at the time of Bid or are yet to be specified in more detail by the Professional as to quality, appearance, durability, finish and such other necessary features affecting purchase price.

Change Authorization− A written order issued and signed by the Professional, which directs changes in the Work that require no adjustment in Contract Price or Contract Time, or which allows for variations in the quantities of Unit Price Work.

Change Order− A written order issued and signed by the Owner, which amends the Contract Documents for changes in the Work or an adjustment in Contract Price and/or Contract Time, or both.

Construction Mechanic− A skilled or unskilled mechanic, laborer, worker, helper, assistant, or apprentice working on a state project but shall not include executive, administrative, professional, office, or custodial employees

Contact Person− Individual in the employ of the Professional or the Owner who is designated as the sole point of contact for prospective Bidders for requests or inquiries concerning the Work and/or the Bidding Documents.

Contract− Refer to the definition in paragraph 1.1 of Section 00500 Agreement. The term “Contract” encompasses the legal obligations of the Owner and Contractor, as defined by the Contract Documents.

Contract Award− The official action of the Board, the Director-SFA or the Director-DCD awarding the Contract to the Contractor.

Contract Documents− Those documents itemized or designated in paragraphs 2.2 through 2.4 of Section 00500 Agreement.

Contract Float− Calendar Days between the Contractor's anticipated date for early completion of the Work, or of a specified portion of the Work, if any, and the corresponding Contract Time.

Contract Price− The Contract price for the Work, or a designated portion of the Work, as designated in Section 00500 Agreement or elsewhere in the Contract Documents, is the total compensation, including authorized adjustments, payable by the Owner to the Contractor (subject to provisions for Unit Price Work).

Contract Times− The Contract Times for the entire Work are the periods allowed, including authorized adjustments, for Substantial Completion and final completion of the Work. The Contract Times for a designated portion of the Work are the periods allowed for Substantial Completion and final completion of any such portion of the Work, as specified in the Contract Documents.