CUI_Novosel JA 2025_45_Redacted.pdf

PDF 201 KB Posted

Attached to
Justification and Approval (J&A) for Professional Support Services for A-CDID and AE-RDD
Solicitation number
MICC_2025-45
Issued by

About this file

This document is a Justification and Approval (J&A) for a sole-source bridge contract for professional support services for the Aviation-Capabilities Development and Integration Directorate (A-CDID) and the Aviation Enablers-Requirements Determination Directorate (AE-RDD) located at Fort Novosel, Alabama. The U.S. Army Mission and Installation Contracting Command (MICC) plans to award a 12-month firm fixed-price contract to Summit Technologies Inc. for $838,474.40, covering the period from April 1, 2025, to March 31, 2026.

The contract will provide specialized support for Army Aviation modernization efforts, focusing on integration and synchronization of Doctrine, Organization, Training, Materiel, Leader Development, Personnel, Facilities, and Policy (DOTMLPF-P) domains. The incumbent contractor will support critical work in areas such as Aircraft and Air Crews Survivability Systems, Navigation Systems, Aviation Logistics/Sustainment, and Mission Command and Networking. The justification emphasizes the urgency of maintaining continuity with the existing contractor, as the 11 contracted personnel represent one-third of the total organizational workforce and are crucial to accomplishing the mission of developing next-generation aviation combat capabilities.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Control No: MICC 2025-45

JUSTIFICATION REVIEW DOCUMENT

FAR 6 JUSTIFICATION AND APPROVAL FOR OTHER THAN

FULL AND OPEN COMPETITION

Program/Equipment: Support Services for the Aviation-Capabilities Development and Integration Directorate (A-CDID) and the Aviation Enablers-Requirements Determination Directorate (AE-RDD) located at Fort Novosel, AL.

Authority: 10 U.S.C. 3204(a)(2) as implemented by Federal Acquisition Regulation (FAR) Part 6.302-2 -- Unusual and Compelling Urgency.

Amount: $838,474.40 for a 12-month bridge period of performance.

Prepared by: Charles K. Joines DSN: 558-2226 Contracting Officer Representative Date: 23 JAN 2025 Email: charles.k.joines2.civ@army.mil

Contracting Officer: Anita L. McLain DSN: 558-2831 Chief, Installation Div. Date: 13 FEB 2025 Email: anita.l.mclain.civ@army.mil

Technical: Glen R. Woodard DSN: 558-1053 Deputy Director, AE-RDD Date: 19 FEB 2025

Email: glen.r.woodard.civ@army.mil

Requirements: Charles K. Joines DSN: 558-2226 Contracting Officer Representative Date: 19 FEB 2025 Email: charles.k.joines2.civ@army.mil

Reviews: I have reviewed this justification and find it adequate to support other than full and open competition.

Program Manager:

DSN:

_______ __ Date: See digital signature

Small Business Professional:

_ _____ _____ Date: See digital signature

Local Legal Counsel:

_ ______ Date: See digital signature

Director, MICC- Fort Novosel:

______ _ Date: See digital signature

Assistant Director, Small Business Program:

COM:

Date: See digital signature

MICC Office of Counsel:

_____ Date: See digital signature

FAR Part 6 Justification and Approval for Other than Full and Open Competition

1. Contracting Activity: U.S. Army Mission and Installation Contracting Command (MICC) - Fort Novosel), 453 Novosel Street, Bldg. 5700, Fort Novosel, Alabama, 36362.

2. Description of Action: The Aviation - Capability Development and Integration Directorate (A-CDID) and the Aviation Enablers - Requirements Determination Directorate (AE-RDD), subordinate elements of the Futures and Concepts Center and Army Futures Command, request a firm fixed-price contract with Summit Technologies Inc., 7449 Joyce Lane, Navarre, FL 32566-9759. The Government projects award for April 2025 and fiscal year (FY) 2025, and Operations and Maintenance, Army (OMA) funds will be used.

3. Description of Supplies/Services: This is a non-personal services bridge contract to provide professional support services for the A-CDID and AE-RDD located at the Aviation Center of Excellence (AVCOE), Fort Novosel, Alabama. This effort enables the A-CDID and AE-RDD to fulfill their mission to support integration and synchronization of Army Aviation modernization efforts for the enduring force, future force, and prepare the force to field emerging capabilities. This effort also assists A-CDID and AE-RDD in the conduct of their specific Doctrine, Organization, Training, Materiel, Leader Development, Personnel, Facilities and Policy (DOTMLPF-P) integration and synchronization efforts addressed in respective charters and directives from senior leadership of the Army for the enduring force modernization efforts and supporting the fielding of emerging capabilities from the Army Futures Command.

The contractor shall provide the necessary subject matter expertise and perform the integration and synchronization of the DOTMLPF-P domains for Army Aviation enabling capabilities in the areas of Aircraft and Air Crews Survivability Systems, Navigation Systems, Aviation Logistics/ Sustainment, and Mission Command and Networking. Army Aviation Survivability Equipment (ASE) includes Electromagnetic and Cyber Support across all Army Aviation platforms, utilizing the Department of Defense (DoD) Joint Capability Integration and Development System (JCIDS) requirements development processes and documentation, and Training and Doctrine Command (TRADOC) Regulation (TR) 71-20 dated 28 June 2013 and TR 71-12 dated 3 October 2012 and applicable emerging Army Futures Command regulations.

Period of Performance: 1 April 2025 to 31 March 2026

Total Value: $838,474.40

4. Authority Cited: 10 U.S.C. 3204(a)(2), as implemented by FAR 6.302-2, Unusual and compelling urgency.

5. Reason for Authority Cited: FAR 6.302-2, Unusual and compelling urgency. As described at FAR 6.302-2, if the agency’s need for supplies or services is so urgent that providing a fair opportunity would result in unacceptable delays.

FAR 52.217-8 Option to Extend Services, could not be utilized to extend this contract as we are over 12-months beyond the expiration date of the MATOC.

a. The lack of experienced government personnel authorizations necessitates reliance on contracted support for the operational and organizational Army Aviation system subject matter expertise. The eleven (11) personnel within this contracted workforce represents one third of the total organizational workforce and contribute significantly to the organization’s ability to accomplish its mission to provide the Army with the next generation of enabling aviation combat capabilities.

b. The existing contract period of performance ends 31 March 2025 for the current task order, W9124G22F0031, that supports A-CDID and AE-RDD. The incumbent contractor, Summit Technologies Inc., is best positioned to execute the bridge contract until the new contract is awarded. The Summit workforce has the requisite knowledge, and skill sets to perform the contracted functions. Introduction of another vendor for such a limited period of performance would be disruptive and increase risk to mission accomplishment.

c. Alternatives. One accomplishable alternative would be to descope or delay work on necessary programs required to equip our next generation Army to compete and prevail against our adversaries. This isn’t a viable alternative because our adversaries continue to acquire and employ new asymmetric capabilities. Another alternative examined was to add additional military and Army civilians to the workforce. This isn’t a viable alternative because of the Army end-strength cap.

d. This requirement is for a 12-month bridge contract with the incumbent of the current task order. Considering the short duration of the period of performance, it would be neither cost effective nor realistic to expect another contractor to fulfill the services required by A-CDID and AE-RDD during the interim period. While fair opportunity is desired, it isn’t efficient or practical for this requirement.

e. Impact if Justification not approved: If a 12-month bridge is not approved, significant degradation to A-CDID and AE-RDD mission would result as it would stop work on several requirements’ development processes and documentation for supported Army Aviation programs. These programs are on an aggressive acquisition timeline.

6. Efforts to Obtain Competition: In accordance with FAR 5.202(a)(11), this action will not be synopsized.

a. Effective Competition: Because this is a sole source action, effective competition is not applicable.

In accordance with FAR 5.202(a)(2), this action will

5. Reason for Authority Cited: FAR 6.302-2, Unusual and compelling urgency. As described at FAR 6.302-2, when the agency's need for the supplies or services is of such an unusual and compelling urgency that the Government would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits bids or proposals, full and open competition need not be provided for. Available options on W9124G22F0031 can no longer be exercised as the MATOC the order was issued against has expired.

d. This requirement is for a 12-month bridge contract with the incumbent of the current task order. Considering the short duration of the period of performance, it would be neither cost effective nor realistic to expect another contractor to fulfill the services required by A-CDID and AE-RDD during the interim period. While full and open competition is desired, it isn't efficient or practical for this requirement.

b. Subcontracting Competition: Subcontracting competition will be achieved by continuing to permit the incumbent to outsource subject matter expertise to subcontractors. The incumbent currently has a subcontract partnership with Navigator Development Group. Expect this partnership to continue through this limited bridge action. Pursuant to Title 48 CFR Part 19.705-2, as implemented by FAR 19.705-2, the Contracting Officer must determine whether a proposed contractual action requires a subcontracting plan. For this requirement, the Contracting Officer has determined that no subcontracting plan is required. This determination shall include a detailed rational and be placed in the contract file.

7. Actions to Increase Competition: The recompete packet for the follow-on contract for this requirement is currently being developed and is expected to provide fair opportunity. Contract language in the follow-on contract will discuss the prime contractor requirement for competition in its subcontracting.

8. Market Research: This is a recurring requirement. Similar Market Research has been conducted by Army Capability Managers (ACMs) and the Concepts, Experimentation, and Analysis Directorate (CEAD) located at the AVCOE, Fort Novosel, Alabama. Past acquisitions included a Multiple Award Schedule Task Order awarded by MICC-Fort Eustis. Multiple vendors have provided similar services in the past. Previous vendors who perform this type of work include ASRC (Broadleaf Inc.), Systems Studies and Simulations (S3 Inc), Science Application International Corporation (SAIC), Summitt Technologies Inc., and Navigator Development Group Inc. This bridge contract will perform the same functions as the previous (W9124G22F0031) task order.

9. Interested Sources: Summit Technologies, INC.

10. Other Facts:

a. Procurement History:

1) Contract number: W911S019D0002 / W9124G22F0031 Award date: 01 JUL 2022 Vendor: Summit Technologies, INC.

2) Competitive status: Full and open competition MATOC with Service-Disabled

Veteran-Owned Small Business (SDVOSB) reserves.

Fair Opportunity given.

11. Technical Certification: I certify that the supporting data under my cognizance which are included in the justification are accurate and complete to the best of my knowledge and belief.

___ Date: See digital signature

Deputy Director Aviation Enablers - Requirements Determination Directorate

12. Requirements Certification: I certify that the supporting data under my cognizance which are included in the justification are accurate and complete to the best of my knowledge and belief.

______ ___ Date: See digital signature

Contracting Officer Representative (COR)

13. Fair and Reasonable Cost Determination: I hereby determine that the anticipated cost or price to the Government for this contract action will be fair and reasonable.

This determination will be made using the IGE in comparison to historical data.

As a part of this basis, certified cost or pricing data will not be required and the following exception applies (FAR 15.403): The estimated cost of the contract action is less than the threshold for certified cost or pricing data.

_ _ Date: See digital signature

Contracting Officer

14. Contracting Officer Certification: I certify that this justification is accurate and complete to the best of my knowledge and belief.

__ __ Date: See digital signature

Contracting Officer

13. Fair and Reasonable Cost Determination: I hereby determine that the anticipated cost or price to the Government for this contract action will be fair and reasonable. This determination will be made using the IGE in comparison to historical data. As a part of this basis, certified cost or pricing data will not be required and the following exception applies (FAR 15.403): The estimated cost of the contract action is less than the threshold for certified cost or pricing data.

Approval

Based on the foregoing justification, I hereby approve the procurement of Professional Support Services for Aviation-Capabilities Development and Integration Directorate (A- CDID) and the Aviation Enablers-Requirements Determination Directorate (AE-RDD) located at Fort Novosel, Alabama on an other than full and open competition basis pursuant to the authority of Title United States Code Section 3204(a)(2) - Unusual and compelling urgency. The estimated value of the contract is $838,474.40 for a 1-year period of performance from 01 April 2025 through 31 March 2026. The approval is subject to availability of funds, and provided that the services or supplies herein described have otherwise been authorized for acquisition.

SCOTT D. KUKES

Alternate Advocate for Competition U.S. Army Mission and Installation Contracting Command, JBSA Fort Sam Houston, TX