MHDS Recovery Phase 2 PWS.pdf

PDF 486 KB Posted

Attached to
CS Communications Duct Space Reutilization
Solicitation number
FA462625Q0045
Issued by

About this file

This Statement of Objectives (SOO) details a telecommunications infrastructure repair project for Malmstrom Air Force Base (AFB) in Montana. The project involves engineering, furnishing, installing, and testing (EFI&T) the recovery of the MHDS-COP cable connecting the Control Tower and FMQ-19 Facility, which includes extracting approximately 14,000 feet of rigid HDPE innerduct from existing conduits. The contractor will be responsible for installing four new hand holes, potentially a NEMA enclosure, and completing all associated infrastructure work while adhering to strict safety, security, environmental, and technical standards.

Key requirements include comprehensive site coordination, safety protocols, security clearances, environmental compliance, and detailed documentation. The project has a one-year performance period post-contract award, with work primarily conducted during normal duty hours at Malmstrom AFB. The contractor must provide weekly status reports, comprehensive testing and acceptance plans, as-built drawings, geospatial data, and comply with numerous telecommunications industry standards including TIA, BICSI, and RUS bulletins. Specific technical requirements cover underground conduit systems, cable installation, maintenance hole specifications, and extensive quality assurance and testing procedures.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTROLLED UNCLASSIFIED INFORMATION

STATEMENT OF OBJECTIVES (SOO)

For

MHDS Recovery Phase 2 at

Malmstrom AFB MT

14 Mar 2025

Prepared By

38 ES/ENPG

4064 Hilltop Road

Tinker AFB OK 73145-2713

SOO – Repair MHDS-COP Cable Connecting Control Tower-FMQ-19 Facility

Page | 2

1. SCOPE.

This SOO defines the requirement for the Contractor to engineer, furnish, install and test (EFI&T) the recovery of the MHDS around the main campus of Malmstrom AFB MT.

The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOO. The Contractor shall comply with the current TIA telecommunication installation and testing commercial standard and base installation standards. All equipment, supplies, and materials provided shall be new and not refurbished

2.0 REQUIREMENTS.

2.1 GENERAL REQUIREMENTS.

2.1.1 Safety Requirements.

The contractor shall comply with all Federal, State, county, and base security and safety laws, regulations, policies, and requirements.

2.1.2 Site Coordination.

The Contractor shall meet with the base safety officer immediately upon arrival on site for review of the specific safety requirements prior to installation.

2.1.2.1 Confined Space.

The Contractors and Sub-contractors entering confined spaces on Malmstrom AFB MT are responsible for the safety of their personnel and for their own permit space program as outlined in AFMAN 91-203. All confined space operations must be coordinated with the Base Safety Office prior to start of work. The primary Contractor is responsible for all Sub-contractor confined space operations.

2.1.2.2 Accident/Incident Reporting and Investigation.

The Contractor shall record and report all facts relating to each instance of injury to either Contractor or Government personnel. Notification shall be provided to the 341 CS/SCXP Project Manager and the Base Safety Office unless otherwise stated in the SOO. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC. If the Government elects to conduct an investigation of the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.

2.1.2.3 Work Area(s).

At day’s end, the Contractor shall remove all debris and surplus materials from the workplace.

Safety barriers shall be in place to protect unfinished work site at the end of the day. All open holes or trenches shall be completely enclosed with flexible orange construction safety fencing, or other safety barriers, at the end of the workday. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard. The contractor shall co-ordinate with the 341 CS/SCXP to ensure that any locking manhole covers are put back in place at the end of each workday. For work performed in the flight line area, before the period of performance ends all extra dirt will be removed off base. The Contractor’s designated on-site project manager will maintain two-way radio contact with the Malmstrom AFB Air Traffic Control (ATC) Tower at all times during construction work within the CMA. Two-way radios/LMRs will be provided by the government.

Page | 3

2.1.2.4 Traffic Control.

In the event base vehicular traffic is disrupted by trenching or horizontal directional boring, the Contractor shall notify the 341 CS/SCXP PM NLT 10 work days in advance to inform base Security Forces and Emergency Services personnel of the planned disruptions.

2.1.2.5 Airfield Driving.

Any person operating a motor vehicle inside the airfield fence on Malmstrom AFB MT shall coordinate with airfield management to obtain the required training/certifications IAW local procedures.

2.1.3 Security Requirements.

The Contractor shall furnish a Contracting Entry Authority List (CEAL) of employees needing access on base to the Contracting Officer (CO). Employees without a badge and identification in their possession will be denied access to the base and work areas. This letter shall identify the names (as shown on the driver’s license), driver’s license numbers and state of issue, and birth date of the personnel who will be performing work under this SOO. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations.

2.1.3.1 Security Clearances.

Personnel must have base approved Contractor badges to enter onto Malmstrom Air Force Base.

Additional requirements are necessary if the designated facility is within a controlled/secure area of the base. Conform to all base regulations and directives pertaining to security, safety, fire, traffic, and personnel clearance while conducting business on Malmstrom AFB. Personnel must have the ability to be trained to properly operate a vehicle on the airfield if the designated facility is within the airfield environment. Personnel required to drive on the airfield must be knowledgeable of and comply with the procedures outlined in the installation airfield driving program. Ensure conformance of all personnel and subcontractors. The contractor shall comply with pertinent Air Force security regulations while working on the project. Contractor personnel are required to abide by all real-world Force Protection Condition (FPCON) measures, random anti-terrorism measures (RAMs), shelter-in-place orders, evacuations and lock-down notices as directed. Examples include mandatory badge or ID checks, facility single points-of-entry, and searches of hand carried items.

2.1.3.2 Operational Security (OPSEC).

Network infrastructure Drawings (MHDS, MH/HH locations, fiber paths, etc.) are on the 341 CS/SCXP Critical Information List and must be protected. The Contractor shall take appropriate measures to protect detailed information pertaining to the EFI&T effort, to include appropriate marking of documents as “Controlled Unclassified Information (CUI),” and ensuring limited distribution of documents and schematics/Drawings to only those individuals with a valid need to know. IAW AFI 10-701, OPSEC Considerations, the contractor shall follow the OPSEC guidance/plan (AFI10-701) to ensure the protection of CUI data either furnished by the government or produced by the contractor. In accordance with 18 United States Code § 795, it is expressly prohibited to capture any photograph, video, sketch, picture, drawing, map, or graphical representation of any DoD resources, facilities, or personnel conducting official business without obtaining explicit permission from the installation commander.

Page | 4

2.1.3.3 Anti-Terrorism (AT) Awareness Training.

In accordance with DoDI O-2000.16v1_AFI 10-245-O, Antiterrorism Program Implementation, ensure Level I - AT Awareness Training is completed by all contractors within 30 days of requiring access, and annually thereafter. The training will be provided by the government. The objective of the training is to provide personnel with requisite knowledge necessary to remain vigilant and enable employment of AT tactics, techniques, and procedures.

2.1.4 Environmental Compliance.

The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations, and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The Contractors are responsible to know and follow all applicable Federal, State, Local and Air Force regulations for environmental protection, including waste disposal, sewer discharge, air emissions, and storm water requirements. The contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Malmstrom AFB MT. The Prime Contractor shall ensure that their subcontractors (if any) comply with these specifications.

2.1.5 Permits.

The Contractor shall be responsible to coordinate, complete and process all permits required to complete the installation prior to any trenching, horizontal directional boring or modifications to a facility, maintenance hole (MH) or hand-hole (HH). For example:

• Digging permit, AF Form 103 shall be submitted through BCE 14 calendar days in advance of digging activities. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 remains current.

• Confine space entry permit, AF Form 1024 shall be coordinated through base safety office. The Contractor shall be prepared to provide proof of their Confined Space Training Program along with the AF Form 1024 to base safety.

• The Contractor shall trench, excavate, and mark and barricade open trenches IAW OSHA Standards.

All utility markings, flags, etc. shall be maintained by the contractor after the responsible work center/shop identifies/locates them and ensure that the AF Form 103 remains current. The contractor shall take precautions to protect existing infrastructure. If a utility is damaged attributed to the fault of the contractor, then the contractor shall repair and return the utility back to the condition prior to the damage.

2.1.6 Integrated Process Team (IPT).

The Contractor shall chair a weekly meeting or as needed (depending on the weekly report; see para 2.1.7) IPT meeting that includes Contractor representatives, the Government Contracting Officer (CO), the Government Project Manager, and other base personnel as required. The Contractor shall provide an agenda NLT 1 working day prior to the scheduled meetings. The Contractor shall provide worldwide Microsoft Teams/“Meet Me” teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, problems being encountered, and other information necessary/beneficial to ensure success and timely completion of contract requirements. The Contractor shall record meeting minutes and distribute to the attendees NLT 1 working day after each meeting.

Page | 5

2.1.7 Quality Assurance.

The Contractor shall provide Quality Assurance Support for the entire duration of the project.

The Contractor’s quality assurance evaluator shall assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the duration of the project. A weekly report (soft copy) shall be delivered/submitted to the POC by COB Monday, indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them.

2.1.8 Contractor Personnel.

2.1.8.1 Project Management.

The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project Manager’s or alternate's range of authority to act for the Contractor relating to daily contract operation.

2.1.8.2 Site Point of Contact (POC).

The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours for the duration of the project, up to and until final acceptance by the Government PM and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.

2.1.8.3 Personnel Requirements.

The Project Manager, Site POC, and respective alternate(s) shall be able to read, write, speak, and understand English and shall be on site to coordinate permits, clearances, and receive shipments/material related to the task order.

2.1.8.4 Minimum Contractor Qualifications.

All work shall be performed by an experienced Telecommunications Contractor. The Contractor shall have a minimum of 3 years of experience in Telecommunications Systems installations.

2.1.8.5 System for Award Management (SAM)

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for Installation via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address https://www.sam.gov SAM replaces the previous ECMRA application that was hosted on https://www.ecmra.mil. See https://www.dmdc.osd.mil/ecmra_splash/ Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the SAM help desk.

2.1.9 Warranty

The Contractor shall provide a one year warranty or manufacturer’s standard commercial warranty, whichever is longer. The warranty period shall start from the date of system and/or

SOO – Repair MHDS-COP Cable Connecting Control Tower-FMQ-19 Facility https://www.sam.gov/ https://www.ecmra.mil/ https://www.dmdc.osd.mil/ecmra_splash/

Page | 6 project acceptance. The Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.

2.1.10 Manuals and Practices.

The Contractor shall provide the latest version of operation, installation, and maintenance manuals and practices/users guide for each system installed as provided by the original manufacturer with all new equipment.

2.2 SPECIFIC REQUIREMENTS.

As indicated in this SOO and attached Project Picture, the Contractor shall EFI&T to will extract all rigid HDPE innerduct, up to three (3) innerducts per outer conduit (capable of being extracted, as determined by the 341 CS and the contractor), in approximately 14000 feet of designated conduits as depicted in the attached Project picture titled “Conduit Space Recovery” at Malmstrom AFB MT.

2.2.1 Outside Plant Requirements.

2.2.1.1 Existing Maintenance Holes.

The Contractor shall be responsible for pumping out maintenance holes/handholes. Water from maintenance holes/handholes shall be drain onto grass, when possible, to act as a natural filter;

then it may be pumped out onto the surrounding ground, as long as there is no impact to roads, driveways, or vehicle traffic. Mud and debris shall be disposed of IAW base requirements. If Contractor comes across a manhole with contaminated water, the Contractor shall coordinate with the environmental office in Base CE.

2.2.1.2 Measurements.

Any distances provided in this SOO are approximations and should NOT be used for ordering materials or determining duct lengths.

2.2.1.3 Underground Utilities Markings.

The Contractor shall coordinate with base agencies to ensure markings are placed over existing base infrastructure prior to digging or horizontal directional boring and shall take precautions to protect existing infrastructure. The Contractor is responsible for repair of any damage caused during installation when the infrastructure is clearly marked. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 (Dig Permit) remains current.

2.2.1.4 Outside Plant Multi-pair Cable.

Outside plant (OSP) multi-pair cable will be Rural Utility Service (RUS) Specification PE-89 as indicated on SOO Appendix A. The cable will comply with telecommunications industry standards with regard to manufacturers’ cable markings, jacket, rip cords, filling compound, color coding, jacketing materials, etc. All cable will be rated for the environment in which it is installed and will be in compliance with the current issue of the National Electric Code (NEC).

2.2.1.5 Closures for Cable Splicing in Maintenance Holes.

Only splice closures intended for underground applications will be used in the underground system. The splice closure will be suitable for pressure testing and will have a rigid end plate to provide a seal against the cable sheath for applications at locations where the possibility of immersion exists. The underground closure will be suitable for enclosing straight, butt splices, and branch splices in a protective housing. The Contractor will use standard re-enterable splice

Page | 7 closures. The closures will have adequate strength to protect the splice and maintain cable shield electrical continuity in the below ground environment. All underground closures will be stainless steel. All splices will be encapsulated upon completion. The Government quality inspector will have the opportunity to inspect the inside of the splice case before closure pressure testing and encapsulation is performed

2.2.1.6 Labeling.

The Contractor shall label all equipment and cables they install, and cables identified for re-use in accordance with TIA-606-D and as directed by the 341 CS/SCXP.

2.2.1.6.1 Cable Tags.

All tags will be permanently labeled, easily visible and corrosion resistant. Install cable tags in all manholes/hand-holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through manholes/handholes, put a tag on the cable, approximately 2 feet from each duct entrance. Information on the cable tag will identify cable by size, type, cable number and count. Tagging and labeling of new cables will be IAW the following:

• Example Copper Tags:

P1-24FF

CA02: 1-100

Line 1:

Line 2:

CA02: Cable Identifier; 1-100: Cable Count

2.2.1.6.2 New Ducts. N/A

New ducts shall be permanently labeled on the wall of each building/Maintenance hole (MH)/Handhole (HH) indicating the connecting building/Maintenance hole/Handhole at the other end of the duct (for example, “To MH-306H”). The same information shall appear on the Contractor’s completed as-built-Drawings

2.2.1.7 New Maintenance Holes/Hand holes. N/A

Maintenance holes installed under this Task Order shall have an American Association of State Highway and Transportation Officials (AASHTO) rating of H-20 (for oversea base/location, for

P – Plastic Sheath

# of cable pairs in cable. For 100 pair cable and up do not include “00”.

24 pairs and less, use “x”; 25 pairs and up, use “-“.

Gauge Size of each conductor.

PF – Plastic Insulated Filled Core Cable

FF – Foam Insulated Filled Core Cable

P 9 - 24 FF

P – Plastic Sheath; TA – Tape Armored Cable

# of cable pairs in cable. For 100 pair cable and up do not include “00”.

24 pairs and less, use “x”; 25 pairs and up, use “-“

Gauge Size of each conductor.

PF – Plastic Insulated Filled Core Cable FF – Foam Insulated Filled Core Cable

P 1 - 24 FF

Page | 8 faster lead time may want to add this statement: European equivalent or Japanese equivalent, etc.). Unless otherwise stated, MHs shall have minimum interior dimensions of 6’W x 8’L x 7’ H (Width, Length, Height); HHs shall have a minimum interior dimension of 3’W x 5’L x 4’H or 4’W x 4’L x 4’H (Width, Length, Height). New hand-holes shall have a self-latching torsion assisted full-opening diamond plate stainless steel 2-piece lid. Maintenance holes/Hand holes shall be furnished with cable rack hardware, pulling irons, a sump, water resistance gaskets, bonding ribbon and a grounding system; predrilled duct entry holes [sealed with knockouts configured for splayed entry in the end walls)] with duct terminators to accept 4-inch I.D.

schedule 40 conduit. It is understood that some Maintenance Holes are precast with bonding ribbons or some similar connection, to the manhole rebar and therefore do not require a ground rod. This method of grounding in lieu of a ground rod is satisfactory just as long as the achieved impedance to ground is twenty five (25) ohms or less. MHs/HHs shall be of concrete construction and meet the requirements of TIA -758B, paragraphs 5.2.1 and/or 5.2.2. Polymer concrete (i.e., Quazite) construction is NOT authorized.

Prefabricated MHs/HHs are preferred. MH/HH shall be installed so that they are reasonably level on a gravel bed of 6 inches to allow drainage of water from the walls. The gravel bed should extend 8 inches to 12 inches beyond the outer edges of the MH/HH. MH/HH covers shall be labeled with 1/8” raised letters stating “COMMUNICATIONS”.

2.2.1.8 Cable Racks and Cable Rack Supports. N/A

Cable racks shall be installed in maintenance holes and hand holes as required - this includes new and existing MHs/HHs. Splices shall not be supported by the cables that enter each end of the splice case. The splices shall be supported by cable hooks under the splice case.

Telecommunications industry standard cable hooks of the appropriate length shall be provided to support cables and splice cases. The cable hooks shall be secured using cable rack locking clips.

All cables shall be supported using racking clips, cable racks, and cable hooks.

2.2.1.9 Grounding. N/A

Grounding hardware such as corrosion resistant wire, bonding ribbon, clamps, ground rod, etc.

necessary to properly bond/ground the cable in MHs shall be provided by the Contractor.

Reference ANSI/TIA 607.

2.2.1.10 Underground Conduit System. N/A

The Contractor shall be responsible for any required trenching and/or boring necessary to lay the duct system. Contractor is also responsible for backfilling ditch lines and compaction of fill materials with appropriate compaction tools. Provide a minimum of 24" cover of clean fill above the conduit. Backfill material shall be clean and free from all organic material, clay, marl or unstable materials, debris, lumps, or broken paving. No rocks or stones larger than 3 inches in diameter shall be allowed in backfill. Material for backfill may be material resulting from excavation if it meets the above requirements. Directional drilling will be used for major road crossings. Otherwise, crossing of paved surfaces may be performed by pavement cuts and resurfacing with appropriate matching road material. This does not prevent the Contractor from using directional drilling if it is more cost effective. Ducts will be appropriately protected when placed under paved surfaces.

Page | 9

2.2.1.10.1 Composition. N/A

The ducts shall be corrosion resistant and 4-inch inside diameter (I.D.) round or metric equivalent. The ducts shall be made of EPC-40 Polyvinyl Chloride (PVC) (Schedule 40) IAW NEMA TC-2. For unique situations the ducts shall be EPC-80-PVC (Schedule 80) IAW NEMA TC-2, high density polyethylene (HDPE) SDR 11.5, Galvanized Iron Pipe (GIP) or “thickwall” stainless steel. Schedule 80 PVC shall be limited to risers. High density polyethylene (HDPE) SDR 11.5 shall be used when directional boring is used. GIP or stainless steel shall be used under taxiways and runways. The ducts shall be appropriately labeled indicating the composition material. Ducts shall have a sleeve or bell end type coupling and shall be watertight when assembled. In addition, the Contractor shall adhere to any additional Host Base/site specific requirements.

2.2.1.10.2 Installation.

Installation of underground the MaxCell shall be IAW RUS Bulletin 1751F-643 and RUS Bulletin 1753F-151.

2.2.1.10.3 Paved Surface Crossings. N/A

The Contractor shall cut and restore, and/or horizontal directional drilling (HDD) in order to cross paved surfaces. Paved surfaces may be asphalt, concrete, brick, or some type of paving stone. Paved surfaces include roads, driveways, sidewalks and parking lots. Paved surface crossings shall be IAW guidelines set forth by the base civil engineer (BCE). At a minimum, grade of PVC conduit at open trench paved surface crossings, or crossings which are planned for paving in the future, shall be Schedule 40 and shall be concrete encased. If horizontal directional drilling (HDD) is used, then it will be in compliance with commonly accepted telecommunications industry standards and practices relative to the installation, stabilization, and protection of conduits through a bore under a paved surface. The decision whether to trench (cut and patch) across or horizontal directionally drill under paved surfaces is at the discretion of the BCE and will be made on a case-by-case basis

2.2.1.10.4 Bends and Sealing. N/A

All bends between MHs/HHs shall be a minimum of ten times (10X) the diameter of the duct size (i.e., 4 inch duct = 40 inches) with the sum of bends in all directions not exceeding a total of 90 degrees where practical. Coordinate with 341 CS/SCX if runs have bends that total more than 90 degrees is required. Ducts shall have bell ends and enter a MH/HH perpendicular to the surface of the wall through which it is entering. All ducts/inner-ducts entering MH/HH shall be sealed. Universal duct plugs or removable putty sealants may be used. Upon completion of conduit sections, a rigid test mandrel ¼” (6.4mm) smaller than the inside diameter of the conduit shall be pulled through two diagonally opposite ducts to ensure proper alignment. In addition, all ducts shall be cleared of loose materials such as concrete, mud, dirt, stones, etc.

2.2.1.10.5 Utility Separation. N/A

When communications ducts cross either power duct or buried power cable, maintain a minimum separation of 3 inches of concrete or 12 inches of well-tamped earth between the two or 12 inches of well tamped earth when parallel; for pipes (e.g., gas, water, oil) maintain 6 inches when crossing or 12 inches when parallel.

Page | 10

2.2.1.10.6 Spacers and Tracer Wire.

Along the length of the duct run, if the ducts are installed by trenching, spacers shall be placed at five (5) foot intervals. At least one duct or roll pipe shall have tracer wire or be otherwise locatable from the surface. All new tracer wire installed for this project needs to have a wire nut and label installed at all wire ends, and those wire ends secured but not connected to grounds.

The tracer wire shall be exposed; free from the conduit and capped (insulated). The tracer shall be secured and routed to the maintenance hole or hand-hole neck to a point where maintenance personnel may access the wire without having to enter the maintenance hole/hand-hole and tagged with a label so indicating it as a “Duct Tracer Wire to xxx – Do Not Remove (where xxx is the other end of the wire).” Tracer wires shall not be connected to any grounding system.

Tracer wire shall be pulled back from building entrances until it is underground to prevent lightning damage.

2.2.1.10.7 Warning Tape.

Cable warning tape shall be buried one (1) foot below the surface and shall follow the duct route.

The tape shall be a minimum of three inches wide and orange in color with the appropriate warning message.

2.2.1.10.8 Entrance Conduits into Existing Maintenance Holes.

When new entrance conduits/ducts or sleeves are required, the Contractor shall bore and install the necessary holes and install the ducts or sleeves, if knockout doesn’t exist. Penetration shall not be in such a location through the wall as to block use of existing ducts in the maintenance hole. New ducts will be a minimum of 18 inches from either the floor or ceiling of the maintenance hole if practical. Ducts shall have bell ends and enter the maintenance hole perpendicular to the surface of the wall through which it is entering and shall be installed flush with the interior wall of the maintenance hole. Ducts and openings around ducts shall be sealed to prevent moisture from entering the maintenance holes.

2.2.1.10.9 Conduit Protection.

The Contactor shall install the appropriate physical protection required [(concrete encasement, steel tube (casing)] for buried PVC conduits or HDPE Roll pipe, consistent with commonly accepted telecommunications industry practices relative to the task and to the environment in which they are installed and the loads (H-5, H-10, H-20, railroads, flight line, etc.) to which they are expected to be exposed. Type of protection may be dependent upon the specific application and shall be IAW applicable federal, state or local (Malmstrom AFB Civil Engineering construction requirements) procedures. However, at a minimum, nonmetallic conduits shall be encased in concrete of minimum 3000 lb. /in2 compressive strength where vehicular traffic is above the pathway. The encasement shall be concrete of a wet type mix and shall be placed in such a manner as to ensure the concrete completely surrounds all conduits and no air voids are trapped in the mix a bend or sweep is placed in PVC nonmetallic duct bank between maintenance holes, the duct bank must be encased in concrete with a minimum compressive strength of 3000 pounds per square inch (psi).

2.2.1.10.10 Pull Tape

All newly installed ducts left vacant shall be provided with a pull tape with a waterproof, corrosion resistant, pre-lubricated flat woven polyester pull tape with sequential footage

Page | 11 markings, (1250 lb. pulling strength) for future cable installations. The pull tape shall extend into the maintenance holes/hand-holes and be secured to a cable rack or pulling iron, etc.

2.2.2 Requirement Installation.

This section describes the underground maintenance hole/conduit system, and copper cable installation requirements. The Contractor shall design and install Customer-Owned Outside Plant Telecommunications Infrastructure in according with TIA-758-B. Each cable installation shall be coordinated with the 341 CS/SCXP so that the impact on the building users is properly coordinated. The sequence of installation is at the Contractor’s discretion.

See Project Drawing below for reference and estimated distances of existing and proposed infrastructure and cables routes. This is only a proposed solution. The Contractor may make any recommendations pertaining to the accomplishment of this requirement in their proposal.

2.2.2.1 Infrastructure Installation.

The contractor shall install the following new infrastructure. All new locations and distances are approximations.

2.2.2.1.1 New NEMA Box Enclosure N/A

The Contractor shall install one NEMA enclosure at the FMQ-19-S. The Contractor shall coordinate with the 341 CS and 452 OSS to determine the size of the enclosure needed to satisfy the particular requirement at that location based on the quantity of conduits coming into the enclosure. The location of new NEMA enclosure shall be provided by 341 CS/SCXP.

2.2.2.1.2 New Maintenance Holes/Hand Holes. N/A

The Contractor shall install four 4’W x 4’L x 4’H (interior dimensions) hand holes (to be designated as HH 233B, HH 233C, HH 233 D & HH 233E). The approximate locations are shown on the Project Drawing. Coordinate with 341 CS/SCXP for final hand holes placement and numbering scheme.

2.2.2.1.3 Innerduct. N/A

2.2.3 Site Restoration.

The Contractor shall restore all disturbed grounds to the “as found” condition or better after installation. The Contractor shall comply with all base grounds restoration requirements.

Common use areas shall be restored with sod.

2.2.4 Service Outages.

The Contractor shall be responsible for preventing any unscheduled (i.e. cutting or disabling any in-service cables or equipment.), Contractor-caused, interruptions of communications capabilities that are properly identified. The Contractor shall coordinate planned outages with the site POC at least 10 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).

2.2.5 National Pollution Discharge Elimination System (NPDES).

If required by Base Civil Engineer (BCE), the Contractor shall not obtain approvals for NPDES at State and/or Federal level [in some locations this may be called the Storm Water Pollution Prevention Plan (SWPPP)]. The storm water/environmental plan is the sole responsibility of the

Page | 12

Contractor. Base Civil Engineering/CEV will review and advise to ensure minimum standards and storm water controls/BMPs are in place to ensure compliance; this is a compulsory item in the SOO and contract. The Contractor shall implement storm water controls/BMPs to ensure sediment, as a result of storm water runoff, does not enter storm drainage channels and/or inlets.

The Contractor shall conduct an initial meeting within 10 days of the Contractor site survey with the base environmental office to identify NPDES preparations and/or the storm water/environmental plan.

The Contractor shall review the NPDES requirements applicable to the base; develop a plan to comply with the NPDES; obtain approval of the NPDES plan from all appropriate government agencies; and comply with any other applicable state requirements for construction.

2.2.6 Identification/Marking.

The Contractor shall clearly mark all Contractor-Furnished Property and Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible, sign (minimum 8.5" x 11") on large containers, construction equipment, or un-manned rental vehicles while on the Government installation indicating the company name and both the Contractor and Site POC's names and local telephone numbers.

2.2.7 Installation Schedules.

The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub-projects associated with the installation of the components and system. All submissions shall be delivered electronically in MS Office-compatible format NLT 10 business days after contract award and as significant schedule changes occur to be determined by the IPT.

2.2.8 Weekly Status Reports.

The Contractor shall prepare a Weekly Status Report and distribute to the POC, the System Engineer(s), the Government Project Manager, and other base personnel as required. The purpose of the report is to inform IPT members of project progress, problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements.

2.2.9 Drawings.

2.2.9.1 As-Built Drawings.

The 341 CS/SCXP shall supply existing system Drawings, and the Contractor shall provide updated Drawings in Visio for building and rack elevation; Visio and .pdf for OSP. These Drawings shall depict the entire pathway and details of the installation, including but not limited to: labeling, cables, innerducts and maintenance holes/handholes, conduits, maintenance loops, distances, bores, trenches, building entrances. Detailed butterfly Drawings will also be required.

If the existing cable diagram or butterfly Drawings are not available; the contractor shall create the missing cable diagram/ butterfly Drawings to include all the components used in this project.

The Contractor shall record/deliver geospatial data of new outside plant distribution system.

2.2.9.2 Butterfly Drawings.

The Contractor shall record and submit butterfly, cable path and building penetration Drawings information for all new installations including butterfly Drawings for all maintenance holes and pull boxes that contain new or reused FOC. Drawings shall record the path and arrangement of

Page | 13 new and reused fiber optic cables, splices, and the arrangement duct banks, ducts, inner-duct and shall show maintenance hole orientation with respect to geodetic north. Drawings shall be submitted in an easily read electronic format such as pdf. Scanned data sheets or legible Drawings are acceptable.

2.2.9.3 Geospatial Deliverables.

The Contractor shall collect and record geospatial data and provide as-built documentation (shape files) of all new installed maintenance hole/duct system components and new cable components (including metadata) compatible with the Cyberspace Infrastructure Planning System (CIPS) Visualization Component (CVC) Drawings system. Data points shall be recorded at the center of each manhole/hand-hole lid and at intervals not to exceed 25 feet along cable routes. Sufficient data points shall be recorded to capture any change in direction along the route. All GPS coordinates shall have +/- 3 feet accuracy for all readings. The government will review the shape files and transcribe the information to the CVC system. Provide geospatial data via CD as Environmental Systems Research Institute (ESRI) Shape files. Shape files shall be delivered within 30 days of project completion.

2.2.10 Test and Acceptance/Installation Test Plan.

The Contractor shall provide a test plan as to how the system shall be pre-tested, in-progress-tested and post-tested. Draft Cut-over Test Plan shall be submitted NLT 10 calendar days after contract award. Government comments will be provided after review of the draft. A final plan will be submitted 30 calendar days before the actual cut-over date. The Contractor shall test the system to demonstrate to the Government quality assurance representative that the system is fully operational and meets or exceeds the specified requirements and that the system is fully ready to be placed into service. These tests shall be accomplished prior to the system being placed into service.

2.2.10.1 Testing.

The Contractor shall conduct on-site testing IAW OEM’s installation manuals, practices and the appropriate vendor’s test procedures. The Contractor shall furnish all test equipment and personnel required to conduct all required testing. During any testing phase, the Government reserves the right to perform any of the contractor performed inspections and tests to assure solutions conform to prescribed requirements. The Contractor shall provide on-site support during the acceptance testing. The Contractor shall participate with the Government in testing the complete communications system. When any system, subsystem, component or requirement test fails to meet the requirements of the test, Government acceptance and payment will be withheld until such time as the cause of the failure is corrected to the Government’s satisfaction.

After appropriate corrective action has been taken, all tests including those previously completed, related to the failed test and the corrective action shall be repeated and successfully completed prior to Government acceptance.

2.2.11 Acceptance/Installation Test Report.

The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan NLT 10 business days after Government Witness Testing is complete.

Page | 14

2.2.12 Final Acceptance.

The Contractor shall schedule a final project walk-through with the Base POC, including Quality Assurance Officer and Subject Matter Expert. The walk-through should be scheduled 5 calendar days prior to acceptance. The contractor shall route the AFTO 747 after the base has signed the test report and the walk-through has been completed.

2.2.13 Deliverable Summary.

All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in this Task Order. All deliverables shall be produced using recommended software tools/versions as accepted by the Government

3.0 GENERAL INFORMATION.

3.1 Period of Performance.

The period of performance for the project shall be one (1) year post contract award date.

3.2 Place of Performance.

The place of performance is Malmstrom AFB MT.

3.3 Hours of Operation.

The Contractor shall routinely work during normal duty hours of the site (0730-1630 PST).

However, mission requirements may necessitate work outside normal hours (nights and/or weekends), especially if existing service must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated with the 341 CS/SCXP and approved by the Contracting Officer at least 10 calendar days in advance.

3.4 Holidays/Down Days.

The Contractor shall not perform under this contract on federal holidays or site-unique down-days unless expressly authorized by the CO and coordinated with the base POC.

3.5 Base Support.

The Contractor shall identify any base support requirements (for example, laydown and storage areas) necessary to complete this project in their proposal. The contractor shall return all government furnished lay-down and storage areas to their original condition upon completion of the project.

Page | 15

4.0 APPENDICES.

4.1 Appendix A: APPLICABLE STANDARDS.

The following list is not all-exclusive. The Contractor shall comply with applicable commercial code and standards AFMAN 91-203 – Air Force Consolidated Occupational Safety Instruction OSHA CFR 29 Part 1910-268 – Telecommunications NEMA TC 2- Electrical Polyvinyl Chloride (PVC) Tubing and Conduit TIA-606-D Administration Standard for Telecommunications Infrastructure TIA-568-E Commercial Building Telecommunications (568C.1, 568C.2, 568C.3) Cabling Standard TIA-607-D Commercial Building Grounding (Earthing) and Bonding Requirements for Telecommunications TIA-526-7- Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant TIA-569-E - Commercial Building Standard for Telecommunications Pathways and Spaces TIA-570-D –Residential Telecommunications Infrastructure Standard TIA-758B Customer-owned Outside Plant Telecommunication Infrastructure Standard BICSI TDM Manual - Building Industries Consulting Services International Telecommunications Distribution Methods (TDM) Manual BICSI – Outside Plan Design Reference Manual RUS Bulletin 345-65 (PE-33) – Specification for Shield Bonding Connectors RUS Bulletin 1735F-401, Standards for Splicing Copper and Fiber Cable RUS Bulletin 1751F-643 - Underground Plant Design RUS Bulletin 1751F-644 - Underground Plant Construction Telecommunications Engineering Shield Continuity and Construction Manual (TE&CM) 451.2 RUS Bulletin 1751F-801 – Electrical Protection Fundamentals RUS Bulletin 1753F-151 (515b) - Specifications and Drawings for Underground Cable Installation RUS Bulletin 1753F-201 (PC-4) – RUS Standard for Acceptance Tests and Measurements of Telecommunications Plant RUS Bulletin 1753F-207 (PE-87) – REA Specification for Terminating Cables NFPA 70 - National Electric Code Unified Facilities Criteria 3-260-01 Unified Facilities Criteria 3-580 FGDC-STD-007.3-1998 - Geospatial Positioning Accuracy Standards Part 3: National Standard for Spatial Data Accuracy

5.0 Project Drawing

Page | 16

Page | 17

1. SCOPE.
2.0 REQUIREMENTS.
2.1 GENERAL REQUIREMENTS.
2.1.1 Safety Requirements.
2.1.2 Site Coordination.
2.1.2.1 Confined Space.
2.1.2.2 Accident/Incident Reporting and Investigation.
2.1.2.3 Work Area(s).
2.1.2.4 Traffic Control.
2.1.2.5 Airfield Driving.
2.1.3 Security Requirements.
2.1.3.1 Security Clearances.
2.1.3.2 Operational Security (OPSEC).
2.1.4 Environmental Compliance.
2.1.5 Permits.
2.1.6 Integrated Process Team (IPT).
2.1.7 Quality Assurance.
2.1.8 Contractor Personnel.
2.1.8.1 Project Management.
2.1.8.2 Site Point of Contact (POC).
2.1.8.3 Personnel Requirements.
2.1.8.4 Minimum Contractor Qualifications.
2.1.8.5 System for Award Management (SAM)
The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for Installation via a secure data collection site. The contractor is required to completel...
2.1.9 Warranty
2.1.10 Manuals and Practices.
2.2 SPECIFIC REQUIREMENTS.
2.2.1 Outside Plant Requirements.
2.2.1.1 Existing Maintenance Holes.
2.2.1.2 Measurements.
2.2.1.3 Underground Utilities Markings.
2.2.1.4 Outside Plant Multi-pair Cable.
2.2.1.5 Closures for Cable Splicing in Maintenance Holes.
2.2.1.6 Labeling.
2.2.1.6.1 Cable Tags.
Example Copper Tags:
2.2.1.6.2 New Ducts. N/A
2.2.1.7 New Maintenance Holes/Hand holes. N/A
2.2.1.8 Cable Racks and Cable Rack Supports. N/A
2.2.1.9 Grounding. N/A
2.2.1.10 Underground Conduit System. N/A
2.2.1.10.1 Composition. N/A
2.2.1.10.2 Installation.
2.2.1.10.3 Paved Surface Crossings. N/A
The Contractor shall cut and restore, and/or horizontal directional drilling (HDD) in order to cross paved surfaces. Paved surfaces may be asphalt, concrete, brick, or some type of paving stone. Paved surfaces include roads, driveways, sidewalks and...
2.2.1.10.4 Bends and Sealing. N/A
2.2.1.10.5 Utility Separation. N/A
2.2.1.10.6 Spacers and Tracer Wire.
2.2.1.10.7 Warning Tape.
2.2.1.10.8 Entrance Conduits into Existing Maintenance Holes.
2.2.1.10.9 Conduit Protection.
2.2.1.10.10 Pull Tape
2.2.2 Requirement Installation.
2.2.2.1 Infrastructure Installation.
2.2.2.1.1 New NEMA Box Enclosure N/A
2.2.2.1.2 New Maintenance Holes/Hand Holes. N/A
2.2.2.1.3 Innerduct. N/A
2.2.3 Site Restoration.
2.2.4 Service Outages.
2.2.5 National Pollution Discharge Elimination System (NPDES).
2.2.6 Identification/Marking.
2.2.7 Installation Schedules.
2.2.8 Weekly Status Reports.
2.2.9 Drawings.
2.2.9.1 As-Built Drawings.
2.2.9.2 Butterfly Drawings.
2.2.9.3 Geospatial Deliverables.
2.2.10 Test and Acceptance/Installation Test Plan.
2.2.10.1 Testing.
2.2.11 Acceptance/Installation Test Report.
2.2.12 Final Acceptance.
2.2.13 Deliverable Summary.
3.0 GENERAL INFORMATION.
3.1 Period of Performance.
3.2 Place of Performance.
3.3 Hours of Operation.
3.4 Holidays/Down Days.
3.5 Base Support.
4.1 Appendix A: APPLICABLE STANDARDS.

File details come from the government source that posted it. Updated .