MGM Basebuilding HVAC Replacement Project SOW 09.23.2024.pdf

PDF 11 MB Posted

Attached to
HVAC Replacement Project located at Montgomery Base Building, Montgomery Regional Airport, Montgomery, AL
Solicitation number
697DCK-25-R-00018
Issued by

About this file

This document is a Statement of Work (SOW) for the HVAC Replacement Project located at the Montgomery Base Building, Montgomery Regional Airport, Montgomery, AL. The Federal Aviation Administration is conducting a Market Survey/Request for Information to identify capable small and disadvantaged businesses that may be able to perform this project. The successful contractor will be responsible for furnishing all necessary supervision, labor, material, equipment, transportation, and services to complete the HVAC system replacement.

The FAA is seeking capability statements from interested vendors that address their ability to perform the required services, details on relevant past performance, and access to additional resources if needed. Respondents must provide company information, business size status, and SAM registration verification. The FAA will use the market survey responses to determine the appropriate procurement method, which may be a full and open competition or a set-aside for small businesses. Responses are due by October 15, 2024. The FAA anticipates issuing the formal Request for Proposals in October 2024, with proposals due approximately 30 days later.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FAA ATO

EASTERN SERVICE AREA (ESA)

SPECIFICATION

July 12, 2024

MGM Base building HVAC Replacement Project

Divisions 01 through 26

THIS PAGE LEFT INTENTIONALLY BLANK

FEDERAL AVIATION ADMINISTRATION JULY 2024

MGM BASE BUILDING HVAC REPLACEMENT PROJECT

TABLE OF CONTENTS 00 01 10 - 1 of 2

TABLE OF CONTENTS

DIVISION 01 - GENERAL CONDITIONS

01 00 00 GENERAL PARAGRAPHS

01 10 00 SUMMARY OF WORK

01 14 00 CONDITION AFFECTING WORK

01 33 00 SUBMITTAL PROCEDURES

01 74 13 CONSTRUCTION CLEANING

01 77 00 CLOSEOUT PROCEDURES

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 36 WARRANTIES AND GUARANTEES

01 78 39 PROJECT RECORD DOCUMENTS

DIVISION 02 - EXISTING CONDITIONS

02 03 00 GENERAL REQUIREMENTS FOR DEMOLITION AND RENOVATION

DIVISION 03 – DIVISION 06 NOT USED

07 72 00 ROOF ACCESSORIES

DIVISION 08 – DIVISION 22 NOT USED

DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING

23 05 00 COMMON WORK RESULTS FOR HVAC

23 05 13 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

23 05 53 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

23 07 00 HVAC INSULATION

23 09 23 CONTROLS FOR HVAC

23 81 19 SELF-CONTAINED AIR-CONDITIONERS

DIVISION 26 - ELECTRICAL

26 05 19 CONDUCTORS AND CABLES

26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

26 05 33 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS

26 05 48 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS

26 28 13 FUSES

26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

26 41 13 LIGHTNING PROTECTION

26 43 13 SPD FOR LOW VOLTAGE ELECTRIC POWER CIRCUITS

DIVISION 27 – DIVISION 33 NOT USED

APPENDICES:

TABLE OF CONTENTS 00 01 10 - 2 of 2

APPENDIX 1

US DOT/FAA Specification FAA-C-1217f Electrical Work, Interior

APPENDIX 2

US DOT/FAA Specification FAA-STD-019e Lightning Protection, Grounding, Bonding and Shielding

APPENDIX 3

Direct Expansion HVAC System Checklist

DRAWINGS

MGM-D-ATCT-19001249-G01

MGM-D-ATCT-19001249-G02

MGM-D-ATCT-19001249-M01

MGM-D-ATCT-19001249-M02

MGM-D-ATCT-19001249-M03

MGM-D-ATCT-19001249-M04

MGM-D-ATCT-19001249-M05

MGM-D-ATCT-19001249-M06

MGM-D-ATCT-19001249-M07

MGM-D-ATCT-19001249-M08

MGM-D-ATCT-19001249-M09

MGM-D-ATCT-19001249-E01

MGM-D-ATCT-19001249-E02

MGM-D-ATCT-19001249-E03

MGM-D-ATCT-19001249-E04

MGM ATCT HVAC REPLACEMENT PROJECT

GENERAL PARAGRAPHS 01 00 00 -1 of 8

SECTION 01 00 00- GENERAL PARAGRAPHS

PART 1 - GENERAL

1.1 DRAWINGS, SPECIFICATIONS, AND OTHER CONTRACT DOCUMENTS

A. Drawings showing general outlines and details necessary for a comprehensive understanding of the work form a part of the Contract Documents. The total number and the titles of the drawings constituting the Drawings are given in the index of the Drawings. All work under the Contract must be performed in all respects in compliance with the requirements of the Contract Documents.

B. The Contract Documents provide for a complete work, and may have been prepared in divisions of various crafts, trades and other categories of work. The Contractor is responsible for the performance of all work under the Contract regardless of any such divisions, and must ensure that all of the work is performed and completed.

C. The FAA will provide the Contractor with an electronic copy of the construction drawings and specifications for the Contractor’s use during the execution of the Contract. The Contractor may reproduce these documents for its use during the performance of the work under this Contract.

D. The Contractor must maintain at the Site at all times at least one (1) copy of Drawings, Specifications and all other Contract Documents, together with at least one (1) complete set of approved Shop Drawings and approved samples.

E. The Contract, Drawings, Specifications, and all referenced standards cited are essential parts of the Contract requirements. A requirement occurring in one is as binding as though occurring in all. They are intended to be complementary and to describe and provide for a complete work.

F. On the drawings, calculated or figured dimensions must govern over scaled dimensions.

G. In the event of a conflict between commercially available or industry standard documents and specific requirements in FAA Orders and Notices, the more stringent must apply.

H. The Contractor must not take advantage of any apparent error, omission, discrepancy, or ambiguity on the Drawings or Specifications. If any error, omission, discrepancy, or ambiguity is found by the Contractor in the Drawings or Specifications, the Contractor must refer the same to the Contracting Officer (CO) prior to beginning work on affected task(s), for interpretation and decision, and such decision must be final.

I. The CO has the right to correct apparent errors or omissions in the Drawings and Specifications and to make such interpretations as he may deem necessary for the proper fulfillment of the Contract Documents. During the course of the work, should any conflicts, ambiguities, or

GENERAL PARAGRAPHS 01 00 00 -2 of 8 discrepancies be found that are not addressed or any discrepancies between the Drawings and the Specifications to which the Contractor has failed to call attention before submitting the offer, then the CO will interpret the intent of the Drawings and Specifications and the Contractor hereby agrees to abide by the CO’s interpretation and agrees to carry out the work in accordance with the decision of the CO. In such event the Contractor will be held to have included in the offer the most proper material and/or method of construction in order to fulfill the intent of the Contract Documents.

J. When a material, article, or equipment is designated by a brand name, and more than one brand name is listed, it must be understood that the design is based on one of the brand name listed products. The contractor will be responsible for all coordination necessary to accommodate the material, article, or equipment being provided without additional cost to the government.

K. The organization of the specification into divisions, sections and articles, and the arrangement of Drawings does not restrict or limit the Contractor in dividing the Work among Subcontractors or in establishing the extent of work to be performed by any trade. It must be the responsibility of the Contractor to inform and coordinate all work specified in all Sections with all sub-contractors, regardless of which Section the work is specified.

L. Product and Reference Standards:

1. When descriptive catalog designations including manufacturer’s name, product brand name, or model number are referred to in the Contract Documents, such designations must be considered as being those found in industry publications of current issue on the date of the first advertisement for offers.

2. When standards of the Federal Government, State Department of Transportation, Standards Organization such as ASTM, AASHTO, AWS, or ANSI, trade societies, or trade associations are referred in the Contract Documents by specific date of issue, these must be considered a part of this Contract. When such references do not bear a date of issue, the current published edition on the date of the first advertisement for offers must be considered as part of the Contract.

3. Where in the Contract Documents an item is identified by a particular manufacturer’s name, model or other code it must be interpreted to include other manufacturers’ product of like and better or equivalent quality whether the words “or equal” are included or not.

4. Wherever a particular manufacturer’s product is required, to the exclusion of all others, appropriate language is included in the Contract Documents.

5. Wherever the terms, “as directed”, “ordered”, “permitted”, “designate”, “as approved”, “approved equal”, “or equal”, “acceptable” and or an approved substitution or other words of similar meaning which authorize an exercise of judgement are used in the Contract Documents, such judgment must be vested only in the CO and/or designated FAA representative.

GENERAL PARAGRAPHS 01 00 00 -3 of 8

1.2 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS

A. No deviation from the Drawings, Specifications and other Contract Documents will be permitted without the prior written approval of the CO.

1.3 SUPERVISION AND CONSTRUCTION PROCEDURES

A. At all times during performance of this contract, and until the work is completed and accepted, the Contractor must directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the CO and has the authority to act for the Contractor.

B. The Contractor must supervise and direct the Work, using the Contractor's best skill and attention. The Contractor must be solely responsible for and have control over construction means, methods, techniques, sequences, and procedures and for coordinating all portions of the Work under the Contract including coordination of the duties of all trades, unless the Contract Documents give other specific instructions concerning these matters.

C. The Contractor must control its operations and those of its Subcontractors and Suppliers to assure the least inconvenience to the traveling public. Under all circumstances, safety must be the most important consideration.

D. Contractor must lay out all work well enough in advance to avoid conflicts or interferences with other work in progress so that in case of interference the layout may be altered to suit the conditions, prior to the installation of any work and without additional cost to the FAA. The contractor must be responsible to coordinate all work and take all action as required to avoid conflicts between trades.

1.4 CORRESPONDENCE

A. Contract correspondence must be directed to the CO with a copy to the COR. Submittals will be sent direct to the COR with a copy of the transmittal letter to the CO.

1.5 LIST OF SUBCONTRACTORS

A. The Contractor must, within 10 calendar days after award, furnish to the CO with a copy to the COR, a list of subcontractors showing the type of work each will perform. If all subcontracts have not been awarded when the initial list is submitted, the Contractor must update the list.

1.6 WORK NOT INCLUDED

A. Items noted on the drawings, details, or schedules as "N.I.C.” (Not In Contract) are not included in this contract.

GENERAL PARAGRAPHS 01 00 00 -4 of 8

B. FAA Furnished Insurance

1. FAA is not maintaining any insurance on behalf of Contractor covering against loss or damage to the Work or to any other property of Contractor. In the event Contractor maintains insurance against physical loss or damage to Contractor’s construction equipment and tools, such insurance must include an insurer's waiver of rights of subrogation in favor of FAA.

1.7 SECURITY REQUIREMENTS

A. Personnel List: Contractor must provide the COR with a list of Contractor's personnel who will require access to the site. The list must be kept current during project work.

B. Right to Search: Current procedures at FAA facilities located within airport boundaries include the "right to search". If in the judgment of the authorized security guard a cause to search a vehicle or the person of personnel exists, such search will be made.

1.8 EXISTING WORK

A. The disassembling, disconnecting, cutting, removal, or altering in any way of existing work must be carried on in such a manner as to prevent injury or damage to all portions of existing work, whether they are to remain in place, be re-used in the new work, or be salvaged and stored.

B. All portions of existing work which have been cut, damaged, or altered in any way during construction operations must be repaired or replaced in kind in an approved manner to match existing or adjoining work. All work of this nature must be performed by the Contractor at his expense and must be as directed. Existing work must, at the completion of all operations, be left in a condition as good as existed before the new work started.

1.9 MATERIALS AND EQUIPMENT TO BE SALVAGED

A. Except where specifically specified otherwise herein, or designated on the drawings, all existing materials and equipment which are required to be removed or disconnected to perform the work but are not indicated or specified for use in the new work, must become the property of the Contractor and must be disposed of properly. The Government may elect to salvage any or all materials removed by the Contractor by giving prior notice and pricing up materials at job site.

1.10 UNCOVERING AND CORRECTION OF WORK

A. Uncovering Work

1. If any portion of the Work is covered contrary to the COR's request or to requirements specifically expressed in the Contract Documents, it must, if required in writing by the

GENERAL PARAGRAPHS 01 00 00 -5 of 8

COR be uncovered for his observation and be recovered (if corrections are not required) or be corrected, if applicable, at the Contractor's expense without change in the Contract Time or Amount.

B. Correction Of Work

1. The Contractor must promptly correct Work rejected by the COR or any governmental authority that fails to conform to the requirements of the Contract Documents, whether observed before or after Substantial Completion and whether or not fabricated, installed or completed. The Contractor must bear all costs of correcting such rejected Work, including additional testing and inspections and compensation for the COR's services and expenses incurred by the FAA.

2. Within two years after contractor’s acceptance inspection (CAI), any work or equipment found not in accordance with the requirements will be considered a latent defect, the Contractor must correct the latent defect promptly after receipt of written notice from the

FAA.

3. The Contractor must remove from the site portions of the Work that are not in accordance with the requirements of the Contract Documents and are neither corrected by the Contractor nor accepted by the FAA.

4. If the Contractor fails to correct nonconforming Work within a reasonable time, the FAA may correct it in accordance with General Provisions. If the Contractor does not proceed with correction of such nonconforming Work within a reasonable time fixed by written notice from the COR, the FAA may correct or remove such nonconforming work and all costs for such corrections or removals must be assessed against the Contractor.

5. The Contractor must bear the cost of correcting destroyed or damaged Work, whether completed or partially completed, of the FAA or separate contractors caused by the Contractor's performing correction or removal of Work which is not in accordance with the requirements of the Contract Documents.

6. Nothing contained herein must be construed to establish a period of limitation with respect to other obligations that the Contractor might have under the Contract Documents. Establishment of the time period of two years as described above relates only to the specific obligation of the Contractor to correct the Work, and has no relationship to the time within which the obligation to comply with the Contract Documents may be sought to be enforced, nor to the time within which proceedings may be commenced to establish the Contractor's liability and damages with respect to the Contractor's obligations other than specifically to correct the Work.

1.11 DAMAGE TO SERVICES

A. Should Contractor damage or interrupt the operation of a utility service or facility by accident or otherwise, it must immediately notify in writing the FAA/operator, appropriate public safety authorities, and the COR and must take all reasonable measures to prevent further damage or interruption of service. Cooperate with the utility service or facility FAA and the COR continuously until such damage has been repaired and service restored.

GENERAL PARAGRAPHS 01 00 00 -6 of 8

1.12 FAILURE TO PROTECT PROPERTY

A. Contractor must not be entitled to any extension of time or compensation on account of Contractor’s failure to protect all facilities, equipment, materials and other property as described herein. All costs in connection with any Improvements or restoration necessary or required by reason of unauthorized obstruction, damage, or use must be borne by Contractor.

1.13 ASBESTOS AND LEAD FREE CERTIFICATION

A. FAA policy is to construct all new facilities without asbestos or lead containing products. The Contractor must provide a letter on his company’s standard letter head stating that to the best of his knowledge no product or material used on this project contains asbestos or lead. The statement must include the name of the project and the contract number and must be signed by an officer of the company. Submission of this statement is a condition for final payment under the contract.

B. Verification: If the FAA suspects the presence of asbestos or lead, tests must be performed on the material or product at the FAA’s expense. If it is determined that the product or material does contain asbestos or lead, then the contractor must remove the product or material and replace at his own expense including the expense of the testing and any retesting that may be necessary.

C. Non – Compliance: If the Contractor fails to provide the above statement, then the FAA must have a complete building survey performed by a qualified testing firm and the costs deducted from the contractor’s final payment.

1.14 MATERIAL SAFETY DATA SHEETS (MSDS):

A. The Contractor must submit to the COR Material Safety Data Sheets (MSDS) for all materials and/or products utilized during the course of the project accomplishment. During the course of the project, both the Resident Engineer and the Contractor must routinely check products utilized on-site to ensure only products which have had MSDS submitted are utilized. Copies of all MSDS must be turned over to the local FAA office for their records.

1.15 PERFORMANCE TIME:

A. The Contractor must complete the installation of the HVAC units within thirty (30) calendar days after Notice-To-Proceed. The time required for the Government to review, comment and approve submittals, and the contractor to order and receive the equipment and materials will not be included in the Contractor’s performance time.

B. Notice-To-Proceed will not be granted until the Contractor certifies to the Contracting Officer that all required submittals, materials and equipment, as approved by the Government, are in his possession and ready for installation.

PART 2 - PRODUCTS

GENERAL PARAGRAPHS 01 00 00 -7 of 8

NOT USED

PART 3 - EXECUTION

END OF SECTION 01 00 00

GENERAL PARAGRAPHS 01 00 00 -8 of 8

SUMMARY OF WORK 01 10 00 - 1

SECTION 01 10 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.2 Provide all labor, materials, tools, equipment, and supervision required for the contractor to perform the work described in the specifications and drawings including:

1. Contractor must remove and replace Roof Top Units (RTU-1,2 and 3). New units must be fully functional and integrated with the existing multi-zone VAV HVAC systems and controls. RTU-1, 2, and 3 must be controlled from the existing FAA direct digital control system. (Submittal required)

2. Contractor must test, adjust and balance (TAB) RTU-1 and the 13 variable air volume terminal unit VAV-1 thru VAV-13 (deliverable required).

3. Contractor must test, adjust and balance (TAB) RTU-2, 3, Variable Air Volume FP-1 and communication equipment room 127 (deliverable required).

4. Contractor must provide a site-specific demolition / construction plan (Pre-award Submittal required)

5. Contractor must provide a site-specific safety plan. (Submittal required)

6. Contractor must have an approved crane lift plan. Due to a long lead time for FAA approval, the lift plan is an early submittal. (Early Submittal required)

7. System performance (Cooling Capacity, CFM, Electrical Data, etc.) must meet the requirements as scheduled or as referenced on drawing and in the specifications.

8. Contractor must furnish and install new roof curb adapter as needed for RTU-1,2,and 3.

Curb adapter must be fabricated of 18-8 stainless steel and duct connection must be constructed and sealed to SMACNA Class A Standard, 4”W.C Gauge. (Submittal required)

9. Contractor must replace the equipment tie-downs for RTU-1,2, and 3 replace on new unit. Existing anchor points to remain and be reused. New tie-down assembly must be rated for 150 MPH winds. (Submittal required)

10. Contractor must adhere to FAA Lock-Out / Tag-Out (LOTO) procedure. Contractor must not disable or enable any disconnect switch, circuit breaker or panel board.

Coordinate LOTO with COTR.

11. Contractor must furnish and install new connections, supply and return, between RTU and existing ductwork. Connections must be sized and coordinated for the largest cross-sectional area available. Connections must be fully fabricated off site, including insulation.

12. Contractor must furnish and install all direct digital control (DDC) devices, points list data is provided by either interior to controller to the RTU(s) or as separate devices.

SUMMARY OF WORK 01 10 00 - 2

Control devices must be fully compatible with the existing I-net DDC system. Contractor must provide all programing to fully integrate new unit, points list and devices to the existing DDC system, including but not limited to, sequence of operation, data graphic user interface. (Submittal required)

13. Contractor must furnish and install duct-mounted supply smoke detectors. Upon activation of the smoke detector the alarm system must be notified and unit must deactivate. Contractor can mount units to existing ductwork but wiring, programing, integration and testing must be performed by a fire alarm specialist certified to work on the existing fire alarm system. (Submittal required)

14. The contractor must remove and replace, with new, lightning protection system components associated with unit. (Submittal required)

15. Units must be grounded and bonded as per FAA-C-1217H and FAA-STD-19F.

16. The contractor must replace all conductors as per electrical drawings and specifications.

17. The contractor must remove existing disconnect switch and furnish and install new heavy duty, NEMA 4X Stainless Steel, 100 amps rated, three-pole disconnect switch fused at 90A for RTU-3 (Submittal required).

18. The contractor must furnish and install a Type 2 Surge Protective Device mounted adjacent with its own disconnect switch. Wiring connections must be made at the load side of the switch. (Submittal required)

19. Liquide-tight flexible conduit, sized to match rigid conduit, must be limited to the final points of connection to the equipment and a length no greater than 6 feet. Liquid-tight flexible conduit must be U/L listed (Submittal required).

20. All flexible conduits must be provided with an external bonding jumper in addition to the internal equipment grounding conductor. The bonding jumper must be a 6 AWG green-insulated stranded copper conductor. The bonding jumper must terminate on fittings listed for grounding at each end of the flexible conduit.

21. Contactor must furnish and install new electrical circuit breaker for RTU-3 as per electrical drawings. (Submittal required)

22. Electrical work must comply with FAA electrical standard, FAA-STD-019f, Lightning and Surge Protection, Grounding, Bonding, and Shielding Requirements for Facilities and Electronic Equipment, FAA-C-1217H, Electrical Work, Premises Wiring, and the

NEC.

23. Provide a factory 3-year whole unit and a 5-year compressor unit parts, labor, and refrigerant warranty for RTU-1,2 ,3. Warranty includes, but not limited to, compressors, evaporator coil, condensing coils, refrigerant piping and refrigerant pipe accessories (filter drier, sight glass, solenoid valves, etc.). (Deliverable item required). The warranty must be a separately priced bid item for FAA consideration.

24. Provide 1-year parts and labor warranty on all other materials furnished. (Deliverable item required)

SUMMARY OF WORK 01 10 00 - 3

25. Provide factory certified training to a minimum audience of five (5) FAA staff members for the proper operation, maintenance and troubleshooting of the HVAC systems.

Training must cover the following items:

System Overview

• Introduction to the rooftop HVAC system

• Key components and their functions (e.g., compressors, heat exchangers, fans, controls)

• Review of system specifications and design features

Installation Review

• Inspection of installed components

• Verification of compliance with design specifications and safety standards

Controls and User Interface Training

• Introduction to the control systems (e.g., thermostats, on-board control panels, building management system integration (I-net)

• Demonstration of control interface and system programming

• Explanation of different operating modes (cooling, heating, etc.)

• Hands-on practice with control settings and troubleshooting

Maintenance and Service Procedures

• Review of preventive maintenance tasks (filters, coils, belts, etc.)

• Instruction on scheduling and conducting routine maintenance.

• Explanation of common problems and troubleshooting techniques

• Discussion of warranty and establishment of an account with the factory service representative

System Operation and Performance Testing

• Overview of system commissioning and testing procedures

• Performance testing demonstration (temperature control, airflow, energy efficiency)

• Discussion of system performance benchmarks and acceptance criteria

Safety Protocols

SUMMARY OF WORK 01 10 00 - 4

• Review of system safety features (e.g., refrigerant management, electrical safety, airflow control)

• Emergency shutdown procedures

• Safety inspection and documentation requirements

Acceptance Walkthrough and Documentation Review

• Final walkthrough of the installed rooftop HVAC system

• Review of system documentation (manuals, warranties, maintenance logs)

• Addressing any final questions or concerns

26. Startup system with a factory certified technician and a manufacture’s approved procedure and checklist. An office report must be submitted for each system, see Direct Expansion HVAC System Checklist within the specifications for further Requirements (Submittal Required)..

1.3 WORK SEQUENCE (Schedule)

1. Contractor must provide a project schedule covering, as a minimum, for each definable feature of work; order of events, durations and the critical path. The schedule must include Contract award, Submittals, Equipment and Materials Acquisition Notice to Proceed / Pre-construction meeting and Construction phases. (Submittal required with contractor’s pre-award proposal).

B. Additional phasing may be necessary due to site availability restrictions.

1.4 CONTRACTOR USE OF PREMISES

A. The FAA must have the right of unlimited access to the premises.

B. Assume full responsibility for protection and safekeeping of project materials under this

Contract.

1.5 MATERIALS DELIVERY TO THE SITE

A. All material orders for delivery to the site must use as a delivery address the address of the tower.

1.6 CONSTRUCTION AREA LIMITS

SUMMARY OF WORK 01 10 00 - 5

A. The limits of construction material storage areas, equipment storage areas, parking areas, and other areas as required by the Contractor must be as shown on the plans or as approved by the COTR. Should Contractor find it necessary or advantageous to use any additional offsite area for any purpose whatsoever, Contractor must, at its expense, provide and make its own arrangements for the use of such additional offsite areas.

END OF SECTION 01 10 00

CONDITIONS AFFECTING WORK 01 14 00 - 1

SECTION 01 14 00 - CONDITIONS AFFECTING WORK

PART 1 – GENERAL

1.1 WORK SCHEDULE

A. Normal working hours are 0700 to 1600, Monday through Friday (except U.S. Federal holidays). Contractor requests to work outside normal working hours require COTR approval.

However, the COTR has full discretion to approve or disapprove, or withdraw approval of requests. If the contractor desires to work outside normal hours (including Saturdays, Sundays, and holidays), he must submit his written request to the COTR at least 48 hours in advance.

Some typical constraints on working outside normal working hours are:

1. The Contractor’s request must be made at least two days in advance (e.g., request received by close of business Wednesday for work on following Saturday). Prior to submitting the request, the Contractor must coordinate as needed (such as utility outages) and have all required people and materials for the work that will be performed.

2. A Contractor with quality or safety problems (as determined by the COTR) will be restricted to normal working hours.

3. A Contractor who fails to correct deficiencies within a reasonable time (as determined by the COTR) will be restricted to normal working hours or may be allowed to work outside normal working hours only to correct those deficiencies.

4. The Contractor must schedule his work to cause the least amount of interference to normal activities.

5. CDC and FAA Covid-19 health screening and guidelines must be enforced.

1.2 FAA OPERATIONS

A. The FAA has established moratorium dates (dates in which no construction activities may occur) for construction activity at critical Air Traffic Control facilities. The intent is to minimize impact on the ability of FAA to perform its operational activities during peak air travel dates. Moratorium dates are typically scheduled over the Thanksgiving Holiday and the Christmas/New Year Holiday. Exact dates will be provided at the preconstruction conference.

1.3 AIRPORT OPERATIONS

A. RESTRICTIONS TO ACCESS - Access to work areas may be restricted from time to time by necessity of airport operations. Contractor acknowledges that it has taken into account and provided in its planning, scheduling and pricing for disruptions including but not limited to, restricted access to portions of the site that will not be immediately available, delivery time limitations, and moratorium dates.

CONDITIONS AFFECTING WORK 01 14 00 - 2

1.4 UTILITY SERVICE

GENERAL - Permission to interrupt any utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption. No utility service must be interrupted without written approval of the COTR.

END OF SECTION 01 14 00

SUBMITTAL PROCEDURES 01 33 00 - 1 of 6

SECTION 01 33 00 - SUBMITTAL PROCEDURES

1.1 SUMMARY

A. Submittals listed or specified in this Contract must conform to the provisions of this section, unless explicitly stated otherwise.

1.2 REFERENCES

1.3 DEFINITIONS

A. Submittal Definition: Shop drawings, product data, samples, administrative and closeout submittals, and additional data presented for review and approval. Contract clauses referring to material, workmanship specifications and drawings for construction must apply to all submittals.

B. Types of Submittals

1. Shop Drawings. As used in this Section, drawings, schedules, diagrams, and other data prepared specifically for this contract, by the Contractor or through the Contractor by way of a subcontractor, manufacturer, supplier, distributor, or other lower tier contractor, to illustrate a portion of the work.

2. Product Data. Preprinted material such as illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer's descriptive literature, catalog data, and other data to illustrate a portion of the work, but not prepared exclusively for this Contract. Information such as mix design, material characteristics, and similar data is included herein.

3. Administrative and Closeout Submittals. Submittals of data for which reviews and approval will be to ensure that the administrative requirements of the project are adequately met but not to ensure directly that the work is in accordance with the design concept and in compliance with the contract documents.

C. Approving Authority: Contracting Officer's Technical Representative (COTR).

D. Work: As used in this Section, the construction required by the contract documents, including labor necessary to produce the construction and materials, products, equipment, and systems incorporated or to be incorporated in such construction and including materials, products, equipment, and systems produced both on-and off-site.

1.4 SUBMITTALS

A. Submit the following in accordance with the requirements of this section.

SUBMITTAL PROCEDURES 01 33 00 - 2 of 6

1. Submittal status log: List each submittal. Include for each submittal the specification section number; description of item for which the submittal is required; and the Contractor's scheduled date for the submittal. Submit the log within 15 business days after contract award. Indicate required approval date to maintain project schedule.

1.5 PROCEDURES FOR SUBMITTALS

A. Limits and Constraints Regarding Submittals

1. Submittals must be complete for each portion of the work; components of the work interrelated as a system must be submitted at the same time.

2. When submittal acceptability is dependent on conditions, items, or materials included in separate subsequent submittals, the submittal will be returned without review.

3. Submittals of information not required as a submittal, or covering work for which the submittals have been returned as “No Exceptions Taken” will be returned without review.

4. Approval of a separate material, product, or component does not imply approval of assembly in which the item functions.

5. The work must conform to approved submittals, except contractor must conform to the contract requirements and resubmit the submittal if a previously approved submittal has an error or omission.

6. When submitting for approval material which is other than that cited in the contract, submit the necessary scale drawings, wiring and control diagrams, cuts or entire catalogs, pamphlets, descriptive literature, and performance and test data of both the material specified and the material he wishes to substitute in the number of copies of each as required under the contract.

B. Scheduling of Submittals

1. Coordinate preparation and processing of submittals with performance of the work so that work will not be delayed by submittal processing. Coordinate and sequence different categories of submittals for same work, and for interfacing units of work, so that one will not be delayed for coordination with another.

2. Except as specified otherwise, allow a review period, beginning with receipt by the approval authority, that includes at least 15 working days.

C. Substitutions: Substitutions from contract requirements require Government approval and will be considered where advantageous to the Government. Where substitutions are proposed for consideration, submit a written request, with documentation of the nature and features of the substitution and why the substitution is desirable and beneficial to the Government. The proposed substitution must be identified separately and included along with the required submittal for the item. When a substitution is submitted for approval, the Contractor warrants the following:

1. Substitution Is Compatible: The Contract has been reviewed to establish that the substitution, when incorporated, will be compatible with other elements of the work.

2. Contractor is Responsible: The Contractor must take action and bear the additional cost, including review costs by the Government, necessary because of the proposed

SUBMITTAL PROCEDURES 01 33 00 - 3 of 6 substitution.

D. Contractor's Responsibilities:

1. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and Contract documents.

2. Ensure that material is clearly legible. Ensure required specialty stamps are affixed and signed.

3. Sign the Contractor's certification. The person signing the certification must be one designated in writing by the Contractor as having that authority. The signature must be in original ink. Stamped signatures are not acceptable.

4. Transmit submittals to the approving authority in orderly sequence, in accordance with the Submittal Status Log, and to prevent project delays and delays in work by the Government or separate contractors.

5. Advise the approving authority of substitution, as required by the paragraph entitled " Substitutions."

6. Correct and resubmit submittal as directed by the approving authority. Direct specific attention, in writing or on resubmitted submittal, to revisions not requested by the approving authority on previous submissions.

7. Retain a copy of approved submittals at the project site, including the Contractor's copy of approved samples.

8. Furnish additional copies of submittals if requested by the COTR.

9. Ensure no work is begun until the submittals for that work have been returned with a review comment other than “Revise and Resubmit” or “Rejected”.

E. Approving Authority's Responsibilities:

1. Submittals will be reviewed for approval with reasonable promptness and only for conformance with project design concepts and compliance with the contract documents.

If a substitution is not identified as required by the paragraph entitled " Substitution ", then the approval of the submittal MUST NOT be an approval of the substitution.

2. The checking, marking or approval of the shop drawings and/or product data by the COTR must not be construed as a complete check, but will indicate only that the general method of construction and detailing is satisfactory. Approval will not relieve the contractor of the responsibility for any error which may exist. The contractor must be responsible for the dimensions and design of adequate connections, details, and satisfactory construction of all work.

3. Submittals will be returned with one of the following notations:

a. Submittals marked ”As Submitted” indicate the work may proceed as presented in the submittal.

b. Submittals marked “Not Approved” indicate the submittal has failed to meet the specification requirements and work may not proceed.

c. Submittals marked “As Noted” indicate there are markings in the submittal that must be included to result in an acceptable submittal. Contractor may proceed with the work by accepting and incorporating the markings in the finished work unless the “Revise and Resubmit” box is checked.

SUBMITTAL PROCEDURES 01 33 00 - 4 of 6

d. Submittals marked “Revise and Resubmit” must be modified and resubmitted.

The revised submittal number must indicate that it is a resubmittal of a rejected submittal.

1.6 FORMAT AND QUANTITY OF SUBMITTALS

A. Transmittal Form: Transmit each submittal, except sample installations and sample panels, to the office of the approving authority. Transmit submittals with a transmittal form approved by the COTR and standard for the project. The transmittal form must identify the Contractor, indicate the date of the submittal, and include information prescribed by the transmitted form and required in the paragraph entitled "Identifying Submittals." Process transmittal forms to record actions regarding sample panels and sample installations.

B. Identifying Submittals: Identify submittals, except sample panel and sample installation, with the following information permanently adhered to or noted on each separate component of each submittal and noted on the transmittal form. Mark each copy of each submittal identically, with the following:

1. Project title and location.

2. Construction contract number.

3. The Section number and paragraph number of the Section by which the submittal is required and the paragraph to which it conforms.

4. The name, address, and telephone number of the subcontractor, supplier, manufacturer and any other second tier contractor associated with the submittal.

5. Product identification and location in project.

C. Format and Quantity for Shop Drawings

1. For shop drawings presented on sheets larger than 11-inches by 17 inches, submit two printed copies and one Portable Document Format (PDF) file.

2. For shop drawings presented on sheets 11-inches by 17 inches or less, submit two printed copies with each bound in a separate volume and a PDF.

3. Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to the information required in the paragraph entitled "Identifying Submittals."

4. Dimension drawings, except diagrams and schematic drawings; prepare dimensioned drawings to scale. Identify materials and products for work shown.

5. Shop drawings must be not less than 8 1/2 by 11 inches or more than 36 by 42 inches.

6. After review, the approving authority will return a PDF file and a marked original.

D. Format and Quantity for Product Data

1. Submit two printed copies with each, bound in a separate volume and a PDF file.

2. Present submittals for each Section as a complete, bound volume. Include a table of contents listing page and catalog item numbers for product data.

3. Indicate, by prominent notation, each product that is being submitted; indicate the Section and paragraph numbers to which it pertains.

4. Supplement product data with material prepared for the project to satisfy submittal

SUBMITTAL PROCEDURES 01 33 00 - 5 of 6 requirements for which product data does not exist. Note that the material is developed specifically for the project.

E. Format and Quantity of Administrative and Closeout Submittals

1. Unless otherwise specified, submit administrative and closeout submittals in the format and quantities required for shop drawings.

2. Comply with section entitled “Contract Closeout Procedures”.

END OF SECTION 01 33 00

SUBMITTAL PROCEDURES 01 33 00 - 6 of 6

CONSTRUCTION CLEANING 01 74 13 - 1

SECTION 01 74 13 - CONSTRUCTION CLEANING

1.1 REQUIREMENT INCLUDED

A. Cleaning and disposal of waste materials, debris and rubbish during construction.

2.1 EQUIPMENT

A. Provide covered containers for deposit of waste materials, debris and rubbish.

3.1 CLEANING

A. Maintain areas under Contractor's control free of waste materials, scraps, surplus material, debris and rubbish. Maintain site in a clean and orderly condition.

B. Remove debris and rubbish from pipe chases, plenums attics, crawl spaces and other closed or remote spaces, prior to closing the space.

C. Clean interior areas daily to provide suitable conditions for work and to prevent fire or accidents.

D. All combustible waste materials must be removed from buildings at the end of each working day.

E. Control cleaning operations so that dust and other particulates will not become airborne in the equipment room.

F. Responsibility for construction cleaning must not be delegated to subcontractors performing construction work under this Contract.

3.2 DISPOSAL

A. Remove waste materials, debris and rubbish from site bi-weekly and legally dispose of off-site in an authorized disposal area.

END OF SECTION 01 74 13

CONSTRUCTION CLEANING 01 74 13 - 2

CLOSEOUT PROCEDURES 01 77 00 - 1

SECTION 01 77 00 - CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Compliance with Specification 01 78 23-Operation and Maintenance Data

2. Compliance with Specification 01 78 36-Warranties and Guarantees

3. Compliance with Specification 01 78 39-Project Record Documents

4. Completion of Lock Out/Tag Out (LOTO) Procedures as per Division 26

5. Final Punch List

1.2 FINAL COMPLETION

A. Preliminary Procedures: Contractor should request final inspection prior to contract completion date. Before requesting final inspection for determining date of Final Completion, complete the following:

1. Submit a Final Application for Payment.

2. Submit certified copy of COTR's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by COTR. The certified copy of the list must state that each item has been completed or otherwise resolved for acceptance.

3. Submit specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.

B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, COTR will either proceed with inspection or notify Contractor of unfulfilled requirements.

COTR will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1.3 WARRANTIES

A. Submit warranties in accordance with Section 01 78 36 “WARRANTIES AND GUARANTEES”. Warranty period must begin on date of Substantial Completion as listed in Certificate of Substantial Completion.

B. Provide additional copies of each warranty to include in operation and maintenance manuals.

CLOSEOUT PROCEDURES 01 77 00 - 2

PART 2 - NOT USED

PART 3 - NOT USED

END OF SECTION 01 77 00

OPERATION AND MAINTENANCE DATA 01 78 23 - 1 of 8

SECTION 01 78 23 - OPERATION AND MAINTENANCE DATA

1.1 REQUIREMENTS INCLUDED

A. Preparation and submittal of operation and maintenance data.

B. All submittals must be bound in commercial quality 8.5 x 11 three ring binders.

1.2 REFERENCES

A. The current issues of the publication listed below forms a part of this specification to the extent referenced. The publication is referred to in the text by the basic designation only.

1.3 SUBMISSION OF OPERATION AND MAINTENANCE DATA

A. Submit operation and maintenance (O&M) data which is specifically applicable to this contract and a complete and concise depiction of the provided equipment or product. All data must be site specific. Data containing extraneous information to be sorted through to find applicable instructions will not be accepted. Present information in sufficient detail to clearly explain user O&M requirements at the system, equipment, component, and subassembly level. Include an index preceding each submittal. Submit in accordance with Section 01 33 00, "SUBMITTAL

PROCEDURES."

B. Quantity: Submit two copies of the manufacturers' information specified herein for the components, assemblies, subassemblies, attachments, and accessories. The items for which O&M data is required are listed in the technical sections which specify that particular item.

C. Package Content and Format: For each product, system, or piece of equipment requiring submission of O&M data, submit the package required in the individual technical section.

D. Package content must be as required in the paragraph entitled "Schedule of Operations and Maintenance Data Packages," with the following general requirements:

1. First page must be a Cover Page, identifying:

FEDERAL AVIATION ADMINISTRATION

MONGOMERY (MGM) ATCT BASE BUILDING

RTU – 1, 2, 3, T1, AND T2

(Manual Title) (Date)

2. Second page must be a Table of Contents indicating the contents of the binder(s).

3. The third page must list the Names, Addresses, Contracts, and Phone Numbers for the following:

OPERATION AND MAINTENANCE DATA 01 78 23 - 2 of 8

a. FAA Project Engineer

b. Designer(s)

c. General Contractor

d. Subcontractors

e. Suppliers

4. The remaining portions of the manual must be separated by each major division of work as identified by the Contract Documents.

a. PROJECT INFORMATION

b. Within each major division of work, each section must be individually identified by a typed index/tab. For each specification requirement, submit the following information in the order outlined below:

1) Test Reports

2) Operating and Maintenance Instructions, including but not limited to:

a) Manufacturer’s Recommended Care and Cleaning

b) Installation Instructions

c) Parts Lists

d) Lubrication Checklists

e) Equipment Supplier Lists

f) Special Instructions

g) Preventive Maintenance Instructions.

5. Copies of electrical panel schedules and directories.

1.4 TYPES OF INFORMATION REQUIRED IN O&M DATA PACKAGES

A. Operating Instructions: Include specific instructions, procedures, and illustrations for the following phases of operation:

1. Safety Precautions: List personnel hazards and equipment or product safety precautions for all operating conditions.

2. Operator Prestart: Include requirements to set up and prepare each system for use.

3. Startup, Shutdown, and Post shutdown Procedures: Include a control sequence for each of these operations.

4. Normal Operations: Include control diagrams with data to explain operation and control of systems and specific equipment.

5. Emergency Operations: Include emergency procedures for equipment malfunctions to permit a short period of continued operation or to shut down the equipment to prevent further damage to systems and equipment.

6. Operator Service Requirements: Include instructions for services to be performed by the operator such as lubrication, adjustments, and inspection.

B. Preventive Maintenance: Include the following information for preventive and scheduled maintenance to minimize corrective maintenance and repair.

OPERATION AND MAINTENANCE DATA 01 78 23 - 3 of 8

1. Preventive Maintenance Plan and Schedule: Include manufacturer's schedule for routine preventive maintenance, inspections, tests and adjustments required to ensure proper and economical operation and to minimize corrective maintenance and repair. Provide manufacturer's projection of preventive maintenance man-hours on a daily, weekly, monthly, and annual basis including craft requirements by type of craft.

C. Appendices: Provide information required below and information not specified in the preceding paragraphs but pertinent to the maintenance or operation of the product or equipment. Include the following:

1. Parts Identification: Provide identification and coverage for all parts of each component, assembly, subassembly, and accessory of the end items subject to replacement.

2. Warranty Information: List and explain the various warranties and include the servicing and technical precautions prescribed by the manufacturers or contract documents to keep warranties in force.

3. Personnel Training Requirements: Provide information available from the manufacturers to use in training designated personnel to operate and maintain the equipment and systems properly.

4. Testing Equipment and Special Tool Information: Include information on test equipment required to perform specified tests and on special tools needed for the operation, maintenance, and repair of components.

5. Contractor Information: Provide a list that includes the name, address, and telephone number of the General Contractor and each…