This document is a submittal for library professional services from Metzger Willard in response to the City of Plant City, Florida's Request for Qualifications for Professional Consulting Services Continuing Contracts. The City seeks qualified firms to provide on-call professional consulting services in engineering and surveying disciplines for infrastructure and capital improvement projects with estimated construction costs not exceeding $7.5 million or study costs not exceeding $0.5 million. Seven discipline categories are available for competition: Site Development/General Civil, Transportation, Stormwater and Flood Mitigation, Mechanical/Electrical/Plumbing, Geotechnical & Materials Testing, Environmental Contamination, and Survey/Mapping & Subsurface Utility Engineering. Firms must submit separate responses for each discipline category, with submissions limited to 50 pages. The question submission deadline was May 11, 2026, at 5:00 p.m., with proposals due by May 21, 2026, at 2:00 p.m., via the City's e-Procurement Portal. Evaluation committee meetings were scheduled for May 27, 2026. The resulting contracts extend for three years from the effective date, with renewal options for two additional two-year periods at the City Manager's discretion.

Respondents must maintain professional liability insurance of $2 million for three years post-project completion, comprehensive liability insurance of $1 million, and workers' compensation coverage, while demonstrating compliance with all applicable federal, state, and local laws, including E-Verify employment verification requirements. Fees remain firm for the initial contract term, with renewal period adjustments limited to a maximum 4% increase supported by Consumer Price Index documentation and written justification. The City offers local preference points (1.5% of total score) to respondents maintaining a physical office within Plant City with at least two full-time employees, current Florida business tax certification, required professional licenses, and at least six months of establishment prior to submission. No set-asides for disadvantaged enterprises have been designated, no minimum work volume is guaranteed, and no specific budget has been identified. The City Manager may award contracts under $50,000, while the City Commission makes final decisions on contracts exceeding that threshold.

View the file

Other files

File Type Posted
Professional_Consulting_Services_Continuing_Contracts_(Addendum_#2_Revision).pdf PDF
Hyatt_RFQ_21-020EN-FC.pdf PDF
Inwood_RFQ21-020EN-FC.pdf PDF
JMTs_CoPC_Library_of_Eng_Services_21-020EN-FC.pdf PDF
Mead__26_Hunt.pdf PDF
OHC_Environmental_RFQ_21-020EN-FC_Plant_City.pdf PDF
PPM_Consultants_2C_Inc._RFQ_21-020-EN-FC_Library_of_Engineering_Services_for_Continuing_Contracts_(Cat_3).pdf PDF
PreproposalMeeting_042426.pdf PDF
RK_26K.pdf PDF
SGM_Submittal_RFQ_21-020EN-FC_Library_of_Engineering_Continuing_Contracts.pdf PDF
SinghofenAssociates_RFQ21-020EN-FC_PlantCity.pdf PDF
Southeastern_Surveying.pdf PDF
Hyatt_RFQ_21-020EN-FC.pdf PDF
Inwood_RFQ21-020EN-FC.pdf PDF
KCA_City_of_Plant_City_Library_of_Engineering_Svcs_for_Cont_Contracts_RFQ_21-020EN-FC.pdf PDF
Nova_-RFQ_21-020EN-FC_Library_of_Engineering_Services.pdf PDF
Reiss_-_Plant_City_RFQ_21_20_EN_FC_.pdf PDF
Hazen_and_Sawyer.pdf PDF
Nova_-RFQ_21-020EN-FC_Library_of_Engineering_Services.pdf PDF
PSI_RFQ_21-020EN-FC_submitted_by_Intertek.pdf PDF
Patel_2C_Greene_and_Associates.pdf PDF
ARMINIUS_CATEGORY_6.pdf PDF
Arehna_FQ_21-020EN-FC.pdf PDF
Atkins_RFQ-21-020EN-FC-Plant-City-FL-Gen-Eng-Svc.pdf PDF
Black_and_Veatch_RFQ21020ENFC.pdf PDF
Boggs_Enginering_RFQ_Response.pdf PDF
Carollo_Engineers.pdf PDF
CivilSurv.pdf PDF
DRMP_PlantCity_RFQ_21-020EN-FC.pdf PDF
DTC-RFQ_21-02EN-FC_Library_of_Engineering_Services_for_Continuing_Contract.pdf PDF
Wood_Bid_21-020EN-FC_Proposal_Final_12102020.pdf PDF
Applied_Sciences_Consulting.pdf PDF
Boggs_Enginering_RFQ_Response.pdf PDF
Carollo_Engineers.pdf PDF
Chastain_Skillman_SOQ-Plant_City_RFQ_2321-020EN-FC.pdf PDF
Curtoom_Libraries_of_Engineering_Services_RFQ_21_020EF_FC.pdf PDF
Florida_Transportation_Engineering.pdf PDF
Water_and_Wastewater_Engineering_Solutions.pdf PDF
Wood_Bid_21-020EN-FC_Proposal_Final_12102020.pdf PDF
Woodard__26_Curran.pdf PDF
Applied_Sciences_Consulting.pdf PDF
Ardaman__26_Associates.pdf PDF
Ardurra_RFQ_21-020EN-FC.pdf PDF
Cardno_2C_Inc.pdf PDF
Curtoom_Libraries_of_Engineering_Services_RFQ_21_020EF_FC.pdf PDF
Gallagher_Bassett_BSI_RFQ_21-020EN-FC_RESPONSE-121020.pdf PDF
Franks_Proposed_Eval_Memebers_(2).pdf PDF
2026-04-13_-_General_Engineering_Continuing_Agreement_-_Work_based_on_Work_order_(1).pdf PDF
2026-05-07_-_Surveying_and_mapping_-_by_Work_Order.pdf PDF
2026-04-13_-_General_Engineering_Continuing_Agreement_-_Work_based_on_Work_order_(1).pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LIBRARY OF ENGINEERING SERVICES

FOR CONTINUING CONTRACTS

CITY OF PLANT CITY | NO. 21-020EN-FC

10 December 2020

8600 Hidden River Parkway Suite 550 Tampa, Florida 33637-1033 Tel: 813-977-6005 Fax: 813-977-0593

December 10, 2020

City of Plant City City Hall 302 W. Reynolds Street Plant City, Florida 33563

SUBJECT: STATEMENT OF QUALIFICATIONS FOR LIBRARY OF ENGINEERING SERVICES

FOR CONTINUING CONTRACTS - RFQ # 21-020EN-FC

Metzger and Willard, Inc. (MWI) is pleased to provide our Statement of Qualifications for Library of Engineering Services for Continuing Contracts in the following Categories:

6. Water and Wastewater E

7. Subsurface Utility Engineering

10. Registered Surveying and Mapping

As a small company of skilled engineers, MWI is uniquely suited to provide City of Plant City with responsive consulting services at cost-effective rates. In addition, we have recent, relevant experience in the above disciplines. This will allow us to better, and more efficiently, perform tasks assigned under this contract. Our project team members have expertise in a broad range of skills including surveying, civil and environmental engineering, design, utilities planning, permitting and compliance, facilities rehabilitation, construction management and inspection, meter testing and calibration, flow testing, and forensic engineering. MWI is a certified Woman-Owned business with the State of Florida.

I will be the direct contact person for all work performed under this contract. A significant advantage of dealing with a small company is that you have direct access to the principal and owners of the firm. As President of MWI, I can commit all the company’s resources to you and directly control our work product and fees. The end result of this direct control is a superior project performed on time and within budget.

The Metzger + Willard, Inc. Project Team is well suited to successfully complete project tasks under the Library of Engineering Services for Continuing Contracts - RFQ # 21-020EN-FC. We look forward to discussing our Statement of Qualifications with you. Should you have any questions, please call me at (813) 977-6005.

Very truly yours, METZGER & WILLARD, INC.

Nancy O. Metzger, P.E.

President

CATEGORY LIST

December 10, 2020 Library of Engineering Services for Continuing Contracts

Category No. Category Descriptions Checkbox

1 General Engineering 2 Transportation Engineering 3 Environmental Engineering 4 Stormwater Engineering 5 Geotechnical Engineering 6 Water and Wastewater Engineering

7 Sub-Surface Utility Engineering

8 Instrumentation and Controls Engineering 9 Electrical Engineering

10 Registered Surveying and Mapping

CONTENTS

Executive Summary

1.1 – 1.24 Tab A | Ability of Professional Personnel & Staff Experience

2.1 – 2.20 Tab B | Relevant Experience

3.1 Tab C | Location / Accessibility

4.1 Tab D | Volume of Similar Contracts

5.1 – 5.2 Tab E | Current and Projected Workload

6.1

8.1 – 8.9

7.1 – 7.2 Tab G | Local Preference

Tab F | Certified Minority Business Enterprise

Tab H | Required Forms

Category List

TA

B

A

ABILITY of PROFESSIONAL PERSONNEL and STAFF EXPERIENCE

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.1

Metzger + Willard, Inc. (MWI) has provided engineering services to Tampa Bay area municipalities for more than 41 years. The majority of these projects have been conducted under continuing contracts. These services have included a broad array of projects from small studies to the design of large facilities requiring multi-discipline services. Because of this history, MWI staff are intimately familiar with utility operations, regulatory constraints and future needs. The focus of practice at MWI is strictly on utility infrastructure planning, design, construction and operation. As a result, our professionals have the in-depth backgrounds necessary to successfully perform services under a miscellaneous services contract where a diversity of projects may be assigned. The firm can also provide in-house survey and mapping, subsurface utility engineering, and construction management and inspection. This diversity makes the MWI project team uniquely qualified to meet the City’s needs under the proposed contract.

We believe this offers the City the best experience available in the area targeted to the City of Plant City’s needs.

To illustrate our comprehensive project team experience and capabilities as it relates to projects envisioned in this contract; we provide the following table, showing the key individuals that will be assigned, their particular areas of expertise (relative to the contract needs), and importantly, years of experience.

An organization chart, defining key personnel roles and hierarchy has been provided on Page 2. Resumes of the key Metzger + Willard, Inc. team members are included at the end of this section. Refer to Pages 3 through 24.

The following chart details the directly relevant experience of individual key project team member

KEY PROJECT

TEAM MEMBERS

Y ea rs

E xp er ie nc e

Fl oo d In ve st ig at io ns

Sm al l M ai nt en an ce

Pr oj ec ts

R ep or ts

D ra in ag e R ev ie w

Su rv ey

SC

at a / M ai nt en an ce

R ec or d

R ev ie w

H yd ra ul ic M od el in g

Su bs ur fa ce U til iti es

En gi ne er in g

V al ue E ng in ee rin g

N. Metzger, PE 38

X X X X X X X X X

D. Willard, PE 51 X X X X X X X X X

S. Martelli, PE 38 X X X X X X X X X

J. Martelli, PE 26 X X X X X X X X X

J. H. Scott, PSM 44 X X X X

J. Cruse 5 X X X

L. Murray 40 X X

A. Detloff 18 X X

W.D. Connor 41 X X X X X X

J. B. Scott 29 X X X X X X

G. Dillman 19

X X X X

F. Shepherd 19 X X X X X

J. Stilp 20 X X X X X X

ABILITY of PROFESSIONAL PERSONNEL and STAFF EXPERIENCE

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.2

ORGANIZATIONAL CHART DESIGN and CONSTRUCTION SERVICES and SURVEY and SUE

Contract Manager Technical Advisor Project Manager Alternate Project Manager Nancy O. Metzger, PE Daniel S. Willard, PE Susan G. Martelli, PE Joe Martelli, PE Metzger + Willard Metzger + Willard Metzger + Willard Metzger + Willard, Inc.

Storage and Pumping Utility Distribution and Collection Wastewater / Water Treatment Facilities Daniel S. Willard, PE Daniel S. Willard, PE Daniel S. Willard, PE Susan G. Martelli, PE Nancy O. Metzger, PE Joe Martelli, PE Nancy O. Metzger, PE Susan G. Martelli, PE Susan G. Martelli, PE Joe Martelli, PE Joe Martelli, PE Nancy O. Metzger, PE Jason Stilp Jay Scott Jason Stilp Jason Stilp

Technical Studies / Permitting / Environmental Construction Inspection Hydraulic Modeling Monitoring

Joe Martelli, PE Daniel S. Willard, PE Wm. Dale Connor Susan G. Martelli, PE Susan G. Martelli, PE Fred Shephard Nancy O. Metzger, PE Nancy O. Metzger, PE Jay Scott Daniel S. Willard, PE Joe Martelli, PE Glenn Dillman Jacob Cruse

Field Services I & I / Record Drawings / Construction Management / Testing Certifications Alt. Project Delivery

Larry Murray Jason Stilp Wm. Dale Connor Daniel S. Willard, PE Joe Martelli, PE Daniel S. Willard, PE Jay Scott Susan G. Martelli, PE Nancy O. Metzger, PE Glenn Dillman Nancy O. Metzger, E

Susan G. Martelli, PE Fred Shephard Joe Martelli, PE Joe Martelli, PE Jacob Cruse

Wm. Dale Connor

Survey SUE MOT

Jeffrey H. Scott, PSM Larry Murray Jeffrey H. Scott, PSM Al Detloff Jay Scott Larry Murray Larry Murray

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.3

RESUMES

NANCY O. METZGER, P.E. Senior Professional Engineer Ms. Metzger is a principal and owner of Metzger + Willard, Inc. She has over 38 years of civil and environmental engineering experience including the planning, design and construction of water, reclaimed water, and wastewater utilities; and environmental permitting and compliance. She has conducted numerous infrastructure planning and design projects for municipalities in Florida since 1983. Her experience includes feasibility studies, route studies, technical and forensic investigations, permitting and regulatory compliance, asset management, master planning, utility relocations, public outreach, preliminary and final design, cost estimating, and construction phase support.

RELEVANT EXPERIENCE

Falkenburg AWWTP Secondary Effluent Pump Replacement / Hillsborough County, FL. Principal-In-Charge and Project Manager responsible for design and construction of the replacement of three 150 HP secondary effluent pumps with smaller, more efficient pumps.

South Central Water Transmission Main / Hillsborough County, FL. Principal-In- Charge and Project Manager responsible for approximately 22,900 feet of 42- and 30-inch diameter transmission main, which delivers potable water from the Central Hillsborough Water Treatment Facility to the Hillsborough County water distribution system.

Large Diameter Force Main Valve Installations / Hillsborough County, FL. Principal- In-Charge responsible for design, permitting and construction phase services for the installation of six 24-inch diameter, three 20-inch diameter and one 16-inch diameter plug valves on two existing force mains for Hillsborough County. The valves required the contractor to perform line stops with bypass capabilities so that flow within the system would not be interrupted.

Madeira Beach Pump Station 189 Upgrade / Pinellas County, FL. Principal-In-Charge and Project Manager responsible for the rehabilitation and upgrade of the Madeira Beach Pump Station including new larger capacity pumps and emergency generator. Project elements included the design of a mixer system, access hatches, gas monitoring system with remote indication in control panel and on SCADA, protective coating for wet-well, and architectural finish improvements.

Carrollwood/Dale Mabry RWPS Replacement/ Hillsborough County, FL. Principal-In- Charge responsible for the design and construction of a reclaimed water pump station to meet a seasonal peak demand of 9,000 gpm. Improvements included six horizontal split case pumps, an electrical building, site improvements, SCADA equipment. Services included survey, preparation of contract documents, permitting, public outreach, geotechnical, bidding and construction phase services. Construction cost was $4.4 million.

Fire Protection Services / Hillsborough County, FL. Principal-In-Charge responsible for the Hillsborough County Fire Protection Improvement Program. This project involved the installation of fire hydrants and water mains in targeted areas through-out Hillsborough County. Tasks included planning and preliminary design, final design, permitting, bid phase assistance, construction phase support, and on-site inspection. Project cost was $2.6 million.

SCBWRF Large Reclaimed Valve Installation / Pinellas County. FL. Principal-In- Charge responsible for design of facilities to enable the control of reclaimed water flow from the South Cross Bayou Water Reclamation Facility. The improvements included new by-pass piping fitted with a 20-inch valve, and a 36-inch butterfly valve. The new valves were designed to be automatically operated. The design also included automatic operation for an existing 48-inch butterfly valve.

YEARS OF EXPERIENCE

EDUCATION

BS Civil Engineering (BSCE) University of Minnesota Institute of Technology 1982

REGISTRATIONS

Professional Engineer, Florida, Georgia

PUBLICATIONS

“Using a Design-Build Approach to Expand Water Service,” JOURNAL Florida Engineering Society 2017 Author, Nancy O. Metzger, PE, George Cassady, PE, Michael K.

Beukema, CGC

“Google Earth Goes Mobile,” The American Surveyor, 2013 Author, Nancy O. Metzger, Thomas G. Davis “Surveying with Google Earth in Google Earth,” The American Surveyor, 2011, Author, Nancy O.

Metzger, Thomas G. Davis

“Over the last 35 years, I have been involved in the design and construction of many exciting and challenging utilities projects. Each time my focus was to deliver the best project possible. That is still my commitment.”

Nancy O. Metzger, PE

MS. METZGER IS VERY FAMILIAR WITH MUNICIPAL UTILITY SYSTEMS

AND HAS PROVIDED ENGINEERING SERVICES UNDER MUNICIPAL

SERVICES CONTRACTS FOR MORE THAN 30 YEARS.

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.4

River Oaks AWWTP Methanol Storage Tank Assessment / Hillsborough County, FL. Principal-In-Charge and Project Manager responsible for the design and permitting of methanol tank replacement at the River Oaks Advanced Wastewater Treatment Plant. Elements of the project included removal of the existing containment system, existing methanol tanks, and fuel lines; installation of a new slab on grade, two (2) 10,000-gallon methanol fuel tanks, new fire hydrant, foam fire suppression system, dosing pumps, and leak detection.

Rehabilitation of Lift Station 28 and 29 / City of Clearwater, FL. Principal-In-Charge responsible for the rehabilitation of two City lift stations to bring the facilities up to the current City Standards. Work included design and permitting and included structural repairs and coatings for wet wells, replacement of pumping units, piping, fittings, valves, electrical and instrumentation, and other appurtenances. Bid phase services included attending the pre-bid conference, responding to RFIs, and developing addenda. Work also included the review of bids received and recommendation for award of the contract.

Symmes Road Parallel Force Main CPS/ Hillsborough County, FL. Principal-In-Charge and Project Manager responsible for permitting and construction services for 16,000 LF of 8-inch, 12-inch, and 16-inch PVC, and 12-inch and 16-inch ductile iron force main piping with valves and appurtenances. Project involved installation of an aerial crossing mounted to a bridge over Bull Frog Creek, and removal and re-installation of a forcemain under a railroad crossing. A portion of the project was constructed using directional drilling methods.

Lithia WTP Additional Pumping and Emergency Generator / Hillsborough County Public Works Department, FL.

Project Manager responsible for tasks relating to the expansion of the Lithia WTP including; an increase in pumping capacity to 92.2 MGD; expansion of emergency power, and construction of a 5.0 MGD ground storage reservoir. Tasks included survey, civil design, ground storage tank and yard piping design, permitting, construction phase services, and resident inspection.

Lithia RW Storage/Pumping / Hillsborough County, FL. Principal-in-Charge and Project Manager responsible for preliminary design, final design, permitting and construction phase services for a 2.0 MG reclaimed water pumping station and 5 MGD precast concrete storage tank. The project included 5 horizontal split-case pumps, pump enclosure with crane, electrical building, access road, stormwater improvements, and SCADA equipment for remote monitoring and operation.

Construction cost was $2.8 million.

Northlakes Reclaimed Water Pump Station Improvements / Hillsborough County, FL. Principal-in-Charge responsible for the preliminary design, final design, permitting and construction services for a 2.16 MGD reclaimed water pump station including four (4) horizontal split-case pumps, flow meter assembly, electrical building, SCADA equipment and site improvements. Construction completed in 2006 at a cost of $1.2 million.

Reclamation Facility Influent Pump Station Evaluation / City of Largo, FL. Principal in Charge responsible for an evaluation to address the South Influent Pump Station. This station receives 85% of the total flow to the City of Largo Wastewater Reclamation Facility and was scheduled for complete replacement. The evaluation involved assessment of the existing equipment including determination of condition and useful life, an alternative analysis to address options for improving safety, increasing efficiency, and facilitating maintenance operations.

Utilities Relocations US 19 from SR 52 to Pasco/Hernando County Line / Pasco County, FL. Principal-In-Charge responsible for preliminary and final design, permitting, bid phase support, and construction engineering and inspection services for the installation, adjustment, and relocation of potable water main and wastewater force main necessary to accommodate FDOT US 19 improvements from State Road 52 to US 19. The work included more than 21,200 LF of relocated 12-inch to 24-inch diameter water transmission main and force main, 3,880 LF of adjusted 12-inch to 24-inch diameter water transmission main and force main. More than 225 valve boxes were relocated and adjusted, existing water lines and force mains were removed, and fire hydrants were adjusted or relocated.

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.5

DANIEL S. WILLARD, P.E. Senior Professional Engineer Mr. Willard has 51 years engineering experience and has functioned as Principal-in-Charge, Project Manager and Project Engineer for a wide variety of water, reclaimed water and wastewater engineering projects; including water transmission and distribution mains, wastewater treatment and reuse facilities, pumping stations, sewage force mains and sewage collection systems, and reclaimed water recycling programs for various reuse applications.

Mr. Willard has worked for Florida municipalities for more than 40 years. During that time he has held several miscellaneous services contracts similar to the current proposed contract.

Where he has performed multiple projects which have included water system improvements, wastewater plant improvements, effluent disposal systems, wastewater collection systems, water main extensions and relocations, force main replacement and forensic studies, pump station improvements and expansions, storage tanks and tank repair, reclaimed pumping stations and storage facilities, meter facilities, SCADA improvements, and drainage improvements.

Madeira Beach Pump Station 189 Upgrade / Pinellas County, FL. Senior Project

Engineer responsible for the rehabilitation and upgrade of the Madeira Beach Pump Station including new larger capacity pumps and emergency generator. Project elements included the design of a mixer system, access hatches, gas monitoring system with remote indication in control panel and on SCADA, protective coating for wet-well, and architectural finish improvements.

Lithia Pinecrest RWTM / Hillsborough County, FL. Project Manager responsible for design/construction phase services for 11,300 lineal feet of 12-inch, 16-inch and 20-inch reclaimed water transmission main which included a 310’ bridge crossing of the Alafia River. The project involved construction along a heavily traveled road with numerous utilities.

Nature’s Way Pump Station Expansion / Hillsborough County, FL. Principal-in-Charge and Project Manager responsible for construction phase and start up services to upgrade and expand an existing master pump station including two wet wells, controls and variable frequency drive systems, generator with fuel system, odor control system, electrical modifications, and 1,500 feet of 16-, 18- and 24-inch sanitary force main.

South County Reclaimed Water Pump Station Replacement / Hillsborough County, FL. Project Manager responsible for design, permitting and construction phase services for reclaimed water pump station to accommodate 6300 gallons of reclaimed water per minute utilizing five horizontal split case pumps at a construction cost of $1.5 million.

2" Galvanized Pipe Replacement - Design & Construction / Pinellas County, FL.

Senior Project Engineer responsible for providing QA/QC for replacement of 92,000 LF of 2-inch, 3,000 LF of 4-inch and 14,000 LF of 6-inch water mains. Engineering services included preparation of a preliminary design report, hydraulic analysis and modeling, survey, utility coordination, cost estimating, and permitting. Work was completed by multiple contractors at a cost of $22.5 million.

Northlakes Reclaimed Water Pump Station Improvements / Hillsborough County, FL.

Project Manager responsible for the preliminary design, final design, permitting and construction services for a 2.16 MGD reclaimed water pump station including 4 horizontal split-case pumps, flow meter assembly, electrical building, SCADA equipment and site improvements. Construction was completed in 2006 at a cost of $1.2 million.

EDUCATION

Master of Engineering (Civil) Cornell University 1970 BS Civil Engineering (BSCE) University of Maryland 1962

REGISTRATIONS

Professional Engineer, Florida, North Carolina, New York Class “A” General Contractor, Florida

AFFILIATIONS

American Society of Civil Engineers Florida Engineering Society National Society of Professional Engineers American Consulting Engineers Council

“It is our belief that maintaining a partnership with our clients will assure the continuation of excellence in meeting the needs for public utilities for the citizens in Florida.”

Daniel S. Willard, PE

MR. WILLARD PREVIOUSLY SERVED AS DIRECTOR OF THE PINELLAS

COUNTY SEWER DEPARTMENT.

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.6

Dale Mabry Reclaimed Water System Improvements / Hillsborough County, FL. Project Manager responsible for PD&E Report, design, surveying and construction phase services for a reclaimed water pump station with four transfer pumps, electrical building, controls and metering facility located at the Dale Mabry AWWTP. To expedite the project MWI assisted the County in procuring major equipment items for installation by the Contractor.

Wimauma Water System- Phase II / Hillsborough County, FL. Project Manager responsible for the design of approximately 49,500 feet of 6- and 8-inch potable water distribution mains, fire hydrants, and appurtenances with connections to the County’s Wimauma Water System Phase. The project included two jack and bore crossings of a State Highway.

SR 54 - North Point to Sun Lake Water and Force Main / Pasco County, FL. Project Manager responsible for the design and permitting of approximately 9,500 linear feet of 12-inch force main and 9,500 linear feet of 12-inch water main, paralleling SR 54 from North Point Parkway to Sun Lake Blvd., including a jack and bore across SR 54 and crossing a triple barrel 48-inch diameter culvert at Sandy Branch.

North Blvd. Water System CPS / Hillsborough County, FL. Project Manager responsible for the installation of approximately 10,600 linear feet of 8, 6 and 4-inch PVC and DIP water main. The project was located in a residential neighborhood west of North Boulevard and south of Bearss Avenue. MWI provided construction management; submittal and schedule reviews; engineering site visits; review of schedule of values and applications for payment; record keeping for RFI’s and RFP’s; progress meetings; observation of all testing; substantial and final inspections; record drawings; and full-time resident inspection.

Boyette Road 16/20 FM Phase A / Hillsborough County, FL. Construction manager responsible for providing CEI services for the construction of 7,500 feet of 24-inch diameter force main within Fish Hawk Boulevard right-of-way. The project included an open-creek crossing of Fish Hawk Creek. Work tasks included meeting and schedule administration, construction observation and inspection, measurement and payment administration, and project close-out support.

Cemetery Road WWTP Improvements w/ Expansion to 3.0 mgd / Okeechobee Utility Authority, FL. Principal-In- Charge responsible for the Cemetery Road WWTP Expansion (from 1 to 3 MGD). Project included development of a preliminary engineering report, plans and specifications, permit applications and bidding documents. The project also included bid phase services, construction phase services and resident inspection for an expansion to the WWTP, including new headworks, biosolids management and deep well injection. Construction cost was $22 million.

Taylor Creek Isles Vacuum Sewer System/Okeechobee Utility Authority, FL. Principal-in-Charge and Project Manager responsible for a vacuum sewer collection system, including a pumping station and a transmission main for approximately 730 connections, with the potential for expansion to 1,000 connections; 52,300 feet of 6-, 8- and 10-inch vacuum collection system lines; 12,000 feet of 8-inch sewage force main and a vacuum pumping station. Services included design, permitting and construction phase services. Construction cost was approximately $3.4 million.

Water Delivery System Master Plan Update (FY 2003-2025) / City of Tampa, FL. QA/QC Task Leader responsible for the preparation of a Water Delivery Master Plan (FY 2003-2025) for the City of Tampa to identify future water system needs and provide an implementation plan for water system improvements. Work included evaluation of existing facility capacity, hydraulic modeling, and identification of improvements to meet future water supply needs. The project fee was $68,250.

WTP #5 / City of Groveland, FL. Project Manager responsible for the design and construction of a 1.7 MGD water treatment facility including 2-750 gpm potable water wells, 0.75 MG prestressed storage tank, water treatment process equipment for disinfection and stabilization, and emergency generator. Construction cost for Phase I of the facility was $1.4 million.

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.7

SUSAN G. MARTELLI, P.E. Senior Professional Engineer Ms. Martelli, Vice-President of Engineering, has over 38 years of civil and environmental engineering experience throughout the State of Florida. Her engineering experience includes planning, design of water, wastewater and stormwater management facilities, water supply and storage treatment and transmission system improvements, reclaimed water transmission and distribution facilities, wastewater collection systems, pumping stations, force mains and treatment facilities. She has conducted numerous projects for Hillsborough County, Pinellas County, Pasco County, the City of Tampa, Clearwater, Largo, and Tampa Bay Water.

Westchase Potable Water Interconnection Project / Hillsborough County, FL. Senior

Project Engineer responsible for the preliminary and final design, design survey, wetlands survey, permitting, bid phase support, construction phase services, inspection and asset management compliance. The project included the construction of approximately 2,600 linear feet of 12-inch water main with appurtenances, and required non-trenchless construction across sensitive wetland areas.

Reclamation Facility Influent Pump Station Evaluation / City of Largo, FL. Project Manager responsible for an evaluation to address the South Influent Pump Station. This station receives 85% of the total flow to the City of Largo Wastewater Reclamation Facility and was scheduled for complete replacement. The evaluation involved assessment of the existing equipment including determination of condition and useful life, an alternative analysis to address options for improving safety, increasing efficiency, and facilitating maintenance operations.

Golf and Sea Pump Station 1 and 2 - Conversion to Gravity / Hillsborough County, FL. Project Manager responsible for the Golf and Sea Sewer Improvements Project, which included the design, permitting, survey, construction management and resident project representation for converting two existing pump stations into manholes and the construction of gravity sewer systems to connect the new manholes to the Miller Mac Master Pump Station. The new gravity system includes approximately 1,000 LF of 8-inch PVC gravity main and 4 new manholes.

Rehabilitation of Lift Station 28 and 29 / City of Clearwater, FL. Project Manager responsible for the rehabilitation of two City lift stations to bring the facilities up to the current City Standards. Work included design and permitting and included structural repairs and coatings for wet wells, replacement of pumping units, piping, fittings, valves, electrical and instrumentation, and other appurtenances. Bid phase services included attending the pre-bid conference, responding to RFIs, and developing addenda. Work also included the review of bids received and recommendation for award of the contract.

Carrollwood/Dale Mabry RWPS Replacement / Hillsborough County, FL. Project Manager responsible for the design and construction of a new reclaimed water pump station to meet a seasonal peak demand of 9,000 gpm. Improvements included six horizontal split case pumps, an electrical building, site improvements, SCADA equipment. Services included survey, preparation of contract documents, permitting, public involvement, geotechnical, bidding and construction phase services.

Lithia Pinecrest RWTM / Hillsborough County, FL. Senior Project Engineer responsible for design/construction phase services for 11,300 lineal feet of 12-inch, 16-inch and 20-inch reclaimed water transmission main which included a 310’ bridge crossing of the Alafia River. The project involved construction along a heavily traveled road with numerous

EDUCATION

BS Environmental Engineering

(BSEE)

University of Florida 1982

REGISTRATIONS

Professional Engineer, Florida

TRAINING

Pump application for Wastewater Systems Training, Stormwater Management Training, 1987 Cross Country Control Training, Land Application of Wastewater Training, 1983 Associate of Arts Course, 1979 A Wetland Primer for Design Professionals, 2004 Project Managers Bootcamp I and II

“A successful project is guaranteed if each individual involved is committed to the group effort.”

Susan G. Martelli, PE

MS. MARTELLI PREVIOUSLY SERVED AS INTERIM UTILITIES DIRECTOR FOR THE CITY

OF OKEECHOBEE.

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.8 utilities.

Large Diameter Force Main Valve Installations / Hillsborough County, FL. Project Manager responsible for design, permitting and construction phase services for the installation of six 24-inch diameter, three 20-inch diameter and one 16-inch diameter plug valves on two existing major force mains for Hillsborough County. The valves required the use of a specialty contractor to perform line stops with bypass capabilities so that the flow within the system would not be interrupted.

William E. Dunn WRF Permit Renewal / Pinellas County County, FL. Project Manager responsible for preparation of an operating permit renewal for the William E. Dunn Water Reclamation Facility. The permit application required a capacity Analysis Report and operation and Maintenance Performance Report. At the request of FDEP some of the existing groundwater monitoring wells were abandoned, 4 new groundwater monitoring wells were installed, and a Groundwater Monitoring Plan was prepared.

Lithia RW Storage/Pumping / Hillsborough County, FL. Senior Project Engineer responsible for preliminary design, final design, permitting and construction phase services for a 2.0 MG reclaimed water pumping station and 5 MGD precast concrete storage tank. The project included 5 horizontal split-case pumps, pump enclosure with crane, electrical building, access road, stormwater improvements, and SCADA equipment for remote monitoring and operation. Construction cost was $2.8 million.

Miller Mac Pump Station Additions / Hillsborough County, FL. Project Manager responsible for providing design and construction phase services for a master pump station in Apollo Beach, including new wetwell, pumps, electrical, controls and emergency electrical services. The pump station which included three (3) pumps, was designed to handle a flow of 3,000 gpm and include a second wet well with splitter box. Work also included rehabilitation of the existing station.

Nature’s Way Pump Station Expansion / Hillsborough County, FL. Senior Project Engineer responsible for construction phase and start up services to upgrade and expand an existing master pump station including two wet wells, controls and variable frequency drive systems, generator with fuel system, odor control system, electrical modifications, and 1,500 feet of 16-, 18- and 24-inch sanitary force main.

Valrico AWTP Expansion w/UV Disinfection / Hillsborough County, FL. Senior Project Engineer responsible for tasks relating to the expansion of existing AWWTP from 6 to 12 MGD, including reclaimed water pumping and storage and UV disinfection. Tasks included survey, civil design, reclaimed water pump station design, environmental and construction phase services, resident inspection, and start-up. Project cost was approximately $52 million.

South County Reclaimed Water Pump Station Replacement / Hillsborough County, FL. Senior Project Engineer in charge of design, permitting and construction phase services. This project included engineering services for design, permitting and construction of reclaimed water pump station with a capacity sufficient to accommodate a total AADF (average annual daily flow) reclaimed water demand of 6300 gallons per minute (gpm). Construction cost was $1.5 million.

William E. Dunn WWTP Chlorine Building Project / Pinellas County, FL. Senior Project Manager responsible for the evaluation of chlorination system options, and preliminary and final design of the recommended alternative a gas chlorine system. Tasks included survey; civil, structural, mechanical, and electrical design; permitting, cost estimating, specifications, bid assistance, and construction phase services.

SR 54 - North Point to Sun Lake Water and Force Main / Pasco County, FL. Senior Project Engineer responsible for the design and permitting of new water and sewer facilities. The design included approximately 9,500 LF of 12-inch force main paralleling SR 54 from North Point Parkway to Sun Lake Blvd., including a jack and bore across SR 54 and crossing a triple barrel 48-inch diameter culvert at Sandy Branch. The project also included the extension of a 12-inch diameter water main on the north side of SR 54.

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.9

JOE MARTELLLI, P.E. Senior Professional Engineer Mr. Martelli is a Professional Engineer licensed in the State of Florida. He has over 26 years of experience including the planning and design of water, wastewater and reclaimed water projects, project management, forensics engineering, capital projects, asset management, infrastructure assessment and construction inspection.

Westchase Potable Water Interconnection Project / Hillsborough County, FL.

Project Manager responsible for the preliminary and final design, design survey, wetlands survey, permitting, bid phase support, construction phase services, inspection and asset management compliance. The project included the construction of approximately 2,600 linear feet of 12-inch water main with appurtenances, and required non- trenchless construction across sensitive wetland areas.

William E. Dunn WWTP Chlorine Building Project / Pinellas County, FL. Senior Project Engineer responsible for the evaluation of chlorination system options, and preliminary and final design of the recommended alternative a gas chlorine system.

Tasks included survey; civil, structural, mechanical, and electrical design; permitting, cost estimating, specifications, bid assistance, and construction phase services.

Golf and Sea Pump Station 1 and 2 - Conversion to Gravity / Hillsborough County, FL. Senior Project Engineer and Resident Project Representative responsible for the Golf and Sea Sewer Improvements Project, which included the converting two existing pump stations into manholes and the construction of gravity sewer systems to connect the new manholes to the Miller Mac Master Pump Station. The new gravity system included approximately 1,000 LF of 8-inch PVC gravity main and 4 new manholes.

Rehabilitation of Lift Station 28 and 29/ City of Clearwater FL. Senior Project Engineer responsible for the rehabilitation of two City lift stations to bring the facilities up to the current City Standards. Work included design and permitting and included structural repairs and coatings for wet wells, replacement of pumping units, piping, fittings, valves, electrical and instrumentation, and other appurtenances. Bid phase services included attending the pre-bid conference, responding to RFIs, and developing addenda. Work also included the review of bids received and recommendation for award of the contract.

Carrollwood/Dale Mabry RWPS Replacement / Hillsborough County, FL. Senior Inspector responsible for monitoring the construction of a new reclaimed water pump station to meet a seasonal peak demand of 9,000 gpm. Improvements included six horizontal split case pumps, an electrical building, site improvements, and SCADA equipment. Construction was $4.4 million.

Linsley Moon Avenue Water Main Replacement / Hillsborough County, FL.

Senior Project Engineer responsible for the design, permitting, bidding and construction phase support for 2,000 linear feet of water main in Brandon, Florida. The project involved replacing an asbestos cement line with a new water main in a very congested utility corridor, and also included design of new metering and connections in compliance with current code.

Lithia RW Storage/Pumping / Hillsborough County, FL. Senior Inspector responsible for construction observation of a 2.0 MG reclaimed water pumping station and 5 MGD precast concrete storage tank. The project included 5 horizontal split-case

EDUCATION

BS Mechanical Engineering (BSME) University of South Florida 1991 Associate of Specialized Technology, Pennco Technical Institute, 1987 Associate of Science, Cumberland County College, 1988

REGISTRATIONS

Professional Engineer, Florida

TRAINING

FDOT Certified Stormwater Management Inspector, 2012 Pumping Station Design, 2005 OSHA: The Complete Compliance Workshop, AMA, 1999 Project Management, Kepner Tregoe, Transferring Products & Processes, FEMA: Failure Mode, Effect & Criticality Analysis, 1995 Solving Indoor Air Quality Problems in Hot Humid Climates,1995 Shock & Vibration Analysis, 1994 Precision Machining Instruction, 1993 Install, Program & Maintain the SLC 5/01, 1992

“My background in maintenance and construction help me find practical, cost effective solutions to complex infrastructure challenges.”

Joe Martelli, PE

MR. MARTELLI HAS PROVIDED BOTH DESIGN AND CONSTRUCTION

INSPECTION SERVICES TO SEVERAL AREA MUNICIPALITIES UNDER

SIMILAR CONTINUING CONTRACTS.

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.10 pumps, pump enclosure with crane, electrical building, access road, stormwater improvements, and SCADA equipment for remote monitoring and operation. Construction cost was $2.8 million.

Miller Mac Pump Station Additions / Hillsborough County, FL. Senior Project Engineer responsible for the coordination of geotechnical engineering and design of the main pump station in Apollo Beach, including new wetwell, pumps, electrical, controls and emergency electrical service. Work also included rehabilitation of existing station.

Construction cost was $2.4 million.

Pump Station Replacements - Design for Rebuild / Hillsborough County, FL. Senior Project Engineer responsible for the upgrade/rehabilitation of four (4) wastewater pumping stations. Services included preparation of construction drawings, specifications, cost estimates, permit applications, and site improvements.

West Comanche Avenue Force Main Replacement Construction Phase Services / Hillsborough County, FL.

Resident Project Representative responsible for construction observation of the replacement of a failed 20-inch PVC force main in the area of Sweetwater Creek.

UV Disinfection Study at South Central WWTP / Hillsborough County, FL. Senior Project Engineer responsible for oversight and coordination of UV Study sampling and testing for disinfection alternatives at water reclamation facilities in Hillsborough County, including Falkenburg WRF, Valrico AWTP, South County AWTP and Northwest Regional WRF.

Reclamation Facility Influent Pump Station Evaluation / City of Largo, FL. Senior Project Engineer responsible for an evaluation to address operation of the South Influent Pump Station which received 85% of the total flow to the City of Largo Wastewater Reclamation Facility. The evaluation involved assessment of the existing equipment including determination of condition and useful life, an alternative analysis to address options for improving safety, increasing efficiency, and facilitating maintenance operations.

2” Galvanized Pipe Replacement - Design & Construction / Pinellas County, FL. Senior Inspector responsible for construction observation of 75,000 of 2-inch and 3,000 LF of 4-inch water main and 14,000 LF of 6-inch water mains using both open cut and directional drilling; and 20,000 LF of 2 and 4-inch water mains. Work was performed by multiple contractors. Total construction cost was $22.5 million.

Madeira Beach Pump Station 189 Upgrade / Pinellas County, FL. Senior Inspector responsible for monitoring the construction of the rehabilitation and upgrade of the Madeira Beach Pump Station including new larger capacity pumps and emergency generator. Project elements included the design of a mixer system, access hatches, gas monitoring system with remote indication in control panel and on SCADA, protective coating for wet-well, and architectural finish improvements.

Water Treatment Plant No. 5 / City of Groveland, FL. Senior Project Engineer responsible for water system modeling and design and permitting for the construction of a 1.7 MGD water treatment facility including 2-750 gpm potable water wells, 0.75 MG prestressed storage tank, water treatment process equipment for disinfection and stabilization, and emergency generator.

Sunshine WWTF Expansion / City of Groveland, FL. Senior Project Engineer responsible for design and construction phase services for a 1.0 MGD expansion to the WWTP. The design included an oxidation ditch wastewater treatment facility with reclaimed water storage and pumping. Construction cost was $9.0 million.

2" Galvanized Pipe Replacement - Design & Construction / Pinellas County, FL. Senior Inspector responsible for construction observation of 75,000 of 2-inch and 3,000 LF of 4-inch water main and 14,000 LF of 6-inch water mains using both open cut and directional drilling; and 20,000 LF of 2 and 4-inch water mains. Work was performed by multiple contractors. Total construction cost was $22.5 million.

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.11

Jacob Cruse Field Engineer Mr. Cruse is a degreed mechanical engineer with over 5 years of experience working in the technical field. Mr. Cruse is responsible for observing construction activities to verify compliance with construction drawings, specifications, and project design criteria. He will witness and report on field testing, prepare observation and progress reports, monitor quantities, review as-built drawings, and obtain GPS coordinates for installed facilities.

Bell Shoals Roadway Improvements / Metzger + Willard, Inc. Inspector responsible for utility coordination inspection throughout 2.75-mi stretch of Bell Shoals Road between Bloomingdale Avenue and Boyette Road. This includes water main and force main installations for the entire length of road between Bloomingdale and Boyette.

Senior Capstone / Villanova University. Responsible for the design of an apparatus to test how various thicknesses of a Phase Change material (PCM) can affect the heat retention of a solar water heater. Included designing apparatus, choosing PCM based on melting point, and ordering materials. Simulated in ANSYS. Received an American Society of Mechanical Engineers Grant to fund this Capstone Project. The results were shown to decrease the rate of heat dispersion of the Solar Water Heater.

Student Intern / Metzger + Willard, Inc. Responsible for compiling and analysis of data for permit renewal for the Marshall Street Water Reclamation Facility (City of Clearwater).

Determine trends in treatment processes for verification of permit limits. Perform facility inspection and condition assessment of treatment facility, equipment, chemical feed systems, and manpower commitments. Assist with the preparation of the Operation Maintenance and Performance Report.

Center for Advanced Medical Learning and Simulation / University of South Florida.

Assisted in the development of projects for simulated training activities for healthcare providers including surgeons, interventionists, and nurses to demonstrate skills proficiency for safe clinical practice and improved patient care.

Engineering Interdisciplinary Projects / Villanova University. Responsible for designing an inexpensive and effective water testing kit for rural communities.

Engineering Interdisciplinary Projects / Villanova University. Design of the programming for a robot with various sensors to run an obstacle course.

Design and Analysis / Villanova University. Responsible for the design and construction of a working three-pound robot.

BlackHagen Design. Developed and edited SolidWorks drawings and files.

EDUCATION

BS in Mechanical Engineering, Villanova University, Villanova PA

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.12

JASON M. STILP Senior Designer Trained as a CAD designer, Mr. Stilp has a broad range of computer drafting experience in civil, mechanical, electrical and architectural design. Mr. Stilp is also experienced with a wide variety of computer programs, hardware and networking. Mr. Stilp performs AutoCAD design for infrastructure improvement projects including roadways, stormwater facilities, water transmission/distribution, fire protection systems, reclaimed water, wastewater collection and treatment plant improvements, and site improvements. He has conducted the design for dozens of municipal utility projects since beginning his career in 2000 and is skilled in the use of Civil 3D.

Citrus Park Water Main Extension / Hillsborough County, FL. Senior Designer/CAD Technician responsible for survey base sheets, and design services in connection with the installation of 11,570 feet of 4- and 6-inch water main to serve a residential area in Citrus Park. The area was previously receiving potable water from private wells and lacked sufficient fire protection. The design included appropriately spaced and sized fire hydrants to provide fire protection.

North Palm River Water Expansion Project / Hillsborough County, FL. Senior Designer/CAD Technician responsible for preparing survey base sheets and utility design for more the five (5) miles of distribution pipeline, service lines, and 90 fire hydrants.

City of Tampa Water Main Design-Build / City of Tampa, FL. Senior Designer/CAD Technician responsible for preparing survey base sheets associated with topographic survey including over 104,000 LF of route. Survey drawings were provided in AutoCAD Civil 3D format. Additional responsibilities included the design of more than 50,000 LF of water main improvements and preparation of record drawings.

Cross Creek Blvd. Topographic Survey / City of Tampa, FL. Senior Designer/CAD Technician responsible for providing topographic surveying services to the City of Tampa in support of a city-wide pavement resurfacing program. The survey included two locations on Cross Creek Boulevard with cross sections at 25-ft intervals. Deliverables included an AutoCAD Civil 3D base map, AutoCAD Civil 3D surface model, and a signed and sealed topographic survey.

Suncoast Parkway Utilities Relocation Phase 1B / Hillsborough County, FL. Senior Designer/CAD Technician responsible for preparation of preliminary and final design plans for the installation, adjustment, and relocation of potable water main, reclaimed water main, and wastewater force main piping along the Suncoast Parkway corridor. The work included more than 8,650 feet of 8-inch to 24-inch water main, reclaimed water main, and wastewater force main.

Sun City - Fire Protection Improvement / Hillsborough County, FL. Senior Designer/CAD Technician responsible for providing design services for the installation of fire hydrants and water mains in Sun City. Responsibilities included the preparation of preliminary and final design plans, and preparation of record drawings. The total length of new pipe was approximately 23,800 feet.

Woodberry PS Fuel Storage System Replacement / Hillsborough County, FL. Senior Designer / CAD Technician responsible for the design of the Hillsborough County Woodberry Pump Station Fuel Tank Removal and Replacement Project. The project involved removal of the existing 2,200 gallon below-grade fuel storage tank and day tank (above-grade) that served the emergency generator, and replacing it with a new 3,000 gallon above-grade tank and associated monitoring controls equipment.

EDUCATION

Associate of Science, ITT Technical Institute, 2001

TRAINING

Civil 3D Certificate 2018

“Communication, Strategy and Execution are key ingredients to a successful project.”

Jason Stilp

MR. STILP HAS PROVIDED ENGINEERING DESIGN AND DRAFTING

SERVICES TO MWI SINCE THE BEGINNING OF HIS CAREER IN 2000.

December 10, 2020 Library of Engineering Services for Continuing Contracts Page 1.13

Citywide Survey Services - Palma Ceia I / City of Tampa, FL. Senior Designer / CAD Technician responsible for preparing a topographic survey for the City of Tampa Water Department for their use in design of improvements. The survey included 10,352 linear feet of route with cross sections at 50-ft intervals in the Palma Ceia area of Tampa.

Horizontal location on visible and above ground features in the survey area were provided, along with elevations for pipe inverts, ends of culverts, ground surface cross sections, railroad tracks and valve tops.

Utilities Relocations State Road 52 from Curley Rd to East of Morris Bridge Rd / Pasco County, FL. Senior Designer/CAD Technician responsible for preparation of preliminary and final design plans for the installation, adjustment, and relocation of potable water main, reclaimed water main, and wastewater force main piping along the State Road 52 corridor.