Memo 261117 Award T.S. Contract Management, Inc. Y27032.pdf

PDF 244 KB Posted

Attached to
Notice of Intent to Award 260000000460; 472/25139. ABG
Solicitation number
NIA1 171 270000000111 1
Issued by
Chippewa County, Michigan

About this file

This is a Recommendation of Award memo issued by the State of Michigan Department of Technology, Management & Budget's Design and Construction Division for Request for Quote Number 260000000460 (DTMB File Number 472/25139.MDL) regarding Kinross Correctional Facility PA Upgrades. The RFQ was posted on SIGMA VSS on September 2, 2026, with a submission deadline of September 30, 2026. The solicitation was evaluated by professional services contractor Tower Pinkster in coordination with Design and Construction Project Director Mike Lusk. The award recommendation, approved on November 17, 2026, is based on best value to the State of Michigan, considering both price and qualitative components.

T.S. Contract Management, Inc. has been selected as the responsive and responsible bidder and is recommended for award in the amount of $827,086.00, pending appropriate approval and contract execution. The evaluation process and detailed bidder information are documented in the accompanying Bid Tabulation sheet and Bidding and Contract Documents. Project inquiries should be directed to Project Director Mike Lusk at LuskM@michigan.gov or 906-322-9002.

View the file

Other files

File Type Posted
Bid Tab 260930 25139.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF MICHIGAN

Department of Technology, Management & Budget State Facility Administration – Design & Construction Division 3111 W. St. Joseph Street, Lansing, MI 48917

Recommendation of Award

The Department of Technology, Management & Budget’s Design and Construction Division has completed the evaluation of Request for Quote, Number 260000000460, DTMB File Number 472/25139.MDL, Kinross Correctional Facility - PA Upgrades and has made an award recommendation.

Any questions pertaining to the evaluation process need to be directed to the Project Director, whose contact information is listed below.

The Design and Construction Project Director is:

Mike Lusk Email: LuskM@michigan.gov Phone: 906-322-9002

I. Evaluation Process The full evaluation process is stated in the Bidding and Contract Documents. The evaluation will be done primarily by the Professional Services Contractor, with assistance from the Design and Construction Project Director.

II. Evaluation Method Responses to this solicitation were reviewed by the professional, Tower Pinkster, with the DCD Project Director.

III. Bidders The RFQ was posted on SIGMA VSS, 9/2/2026. The following bidders submitted proposals, by the published due date of, 9/30/2026 Please see attached Bid Tabulation sheet.

IV. Award Recommendation:

Award recommendation is made to the responsive and responsible Bidder who offers the best value to the State of Michigan. Best value is based on price and qualitative components. Award Recommendation is made to T.S. Contract Management, Inc., in the amount of $827,086.00, pending appropriate approval and contract execution.

Recommendation Approved

11/17/2026 Adam P. Lach, Director Date State Facilities Administration – Design & Construction Division

File details come from the government source that posted it. Updated .