This is a Recommendation of Award memorandum from the Michigan Department of Technology, Management & Budget's State Facility Administration - Design & Construction Division for Request for Quote Number 260000000443 (DTMB File Number 472/26319.SMD). The project involves the Handlon Correctional Facility Unit B Conversion. The RFQ was posted on SIGMA VSS on August 19, 2026, with a submission deadline of September 16, 2026. The evaluation process was conducted by the professional services contractor Abonmarche in conjunction with the Design and Construction Project Director. An award recommendation was approved on October 13, 2026, by Adam P. Lach, Director of State Facilities Administration - Design & Construction Division.

The award recommendation was made to Shreck, Inc., as the responsive and responsible bidder offering the best value to the State of Michigan in the amount of $1,221,820.00. The award determination was based on both price and qualitative components. The recommendation is pending appropriate approval and contract execution. Project Director Scott DeKorte may be contacted at DeKorteS@michigan.gov or 616-490-6169 for questions pertaining to the evaluation process.

View the file

Other files

File Type Posted
Bid Tab 260916 26319.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF MICHIGAN

Department of Technology, Management & Budget State Facility Administration – Design & Construction Division 3111 W. St. Joseph Street, Lansing, MI 48917

Recommendation of Award

The Department of Technology, Management & Budget’s Design and Construction Division has completed the evaluation of Request for Quote, Number 260000000443, DTMB File Number 472/26319.SMD, Handlon C.F. – Unit B Conversion and has made an award recommendation.

Any questions pertaining to the evaluation process need to be directed to the Project Director, whose contact information is listed below.

The Design and Construction Project Director is:

Scott DeKorte Email: DeKorteS@michigan.gov Phone: 616-490-6169

I. Evaluation Process The full evaluation process is stated in the Bidding and Contract Documents. The evaluation will be done primarily by the Professional Services Contractor, with assistance from the Design and Construction Project Director.

II. Evaluation Method Responses to this solicitation were reviewed by the professional, Abonmarche, with the DCD Project Director.

III. Bidders The RFQ was posted on SIGMA VSS, 8/19/2026. The following bidders submitted proposals, by the published due date of, 9/16/2026 Please see attached Bid Tabulation sheet.

IV. Award Recommendation:

Award recommendation is made to the responsive and responsible Bidder who offers the best value to the State of Michigan. Best value is based on price and qualitative components. Award Recommendation is made to Shreck, Inc., in the amount of $1,221,820.00, pending appropriate approval and contract execution.

Recommendation Approved

10/13/2026 Adam P. Lach, Director Date State Facilities Administration – Design & Construction Division