This is a Recommendation of Award memorandum issued by the Michigan Department of Technology, Management & Budget, State Facility Administration - Design & Construction Division for Request for Quote Number 260000000338, DTMB File Number 171/26076.GSA. The project involves upgrading the fire suppression system at the Flint Parking Ramp. The RFQ was posted on SIGMA VSS on June 9, 2026, with a submission deadline of July 8, 2026. The evaluation was conducted by the professional services contractor Matrix Consulting Engineers in collaboration with the Design and Construction Project Director. The award recommendation was approved on July 24, 2026.

The award recommendation has been made to Antler Construction Company, Inc., in the amount of $300,000.00, pending appropriate approval and contract execution. The selection was based on best value to the State of Michigan, which was determined through evaluation of both price and qualitative components. The award recommendation was approved by Adam P. Lach, Director of State Facilities Administration - Design & Construction Division. Questions regarding the evaluation process should be directed to Project Director George Ananich at AnanichG@michigan.gov or 517-328-9853.

View the file

Other files

File Type Posted
Bid Tab 260708 26076.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF MICHIGAN

Department of Technology, Management & Budget State Facility Administration – Design & Construction Division 3111 W. St. Joseph Street, Lansing, MI 48917

Recommendation of Award

The Department of Technology, Management & Budget’s Design and Construction Division has completed the evaluation of Request for Quote, Number 260000000338, DTMB File Number 171/26076.GSA, Flint Parking Ramp – Upgrade Fire Suppression System and has made an award recommendation.

Any questions pertaining to the evaluation process need to be directed to the Project Director, whose contact information is listed below.

The Design and Construction Project Director is:

George Ananich Email: AnanichG@michigan.gov Phone: 517-328-9853

I. Evaluation Process The full evaluation process is stated in the Bidding and Contract Documents. The evaluation will be done primarily by the Professional Services Contractor, with assistance from the Design and Construction Project Director.

II. Evaluation Method Responses to this solicitation were reviewed by the professional, Matrix Consulting Engineers, with the DCD Project Director.

III. Bidders The RFQ was posted on SIGMA VSS, 6/9/2026. The following bidders submitted proposals, by the published due date of, 7/8/2026 Please see attached Bid Tabulation sheet.

IV. Award Recommendation:

Award recommendation is made to the responsive and responsible Bidder who offers the best value to the State of Michigan. Best value is based on price and qualitative components. Award Recommendation is made to Antler Construction Company, Inc., in the amount of $300,000.00, pending appropriate approval and contract execution.

Recommendation Approved

07/24/2026 Adam P. Lach, Director Date State Facilities Administration – Design & Construction Division