This document is a Recommendation of Award from the Michigan Department of Technology, Management & Budget's State Facility Administration – Design & Construction Division for Request for Quote (RFQ) Number 250000000455, concerning the Torch Lake Superfund Site - Lake Linden Shoreline Restoration project. The RFQ was posted on SIGMA VSS on 6/3/2025, with proposals due by 7/9/2025. The evaluation was conducted by the professional services contractor AECOM, in collaboration with the Design and Construction Project Director, to select a responsive and responsible bidder offering the best value to the State of Michigan.
The award recommendation is made to Derek Bradway dba/ Bradway Enterprises for a total contract amount of $675,599.00, pending appropriate approval and contract execution. The project director for this solicitation is Sadi Rayyan, who can be contacted at RayyanS@michigan.gov or 517-719-2801 for any questions about the evaluation process. The recommendation was approved on 08/12/2025 by Adam P. Lach, Director of State Facilities Administration – Design & Construction Division, indicating the completion of the review and selection process for this shoreline restoration project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Tab 250709 20188.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF MICHIGAN
Department of Technology, Management & Budget State Facility Administration – Design & Construction Division 3111 W. St. Joseph Street, Lansing, MI 48917
Recommendation of Award
The Department of Technology, Management & Budget’s Design and Construction Division has completed the evaluation of Request for Quote, Number 250000000455, DTMB File Number 761/20188.SAR, Torch Lake Superfund Site - Lake Linden Shoreline Restoration and has made an award recommendation.
Any questions pertaining to the evaluation process need to be directed to the Project Director, whose contact information is listed below.
The Design and Construction Project Director is:
Sadi Rayyan Email: RayyanS@michigan.gov Phone: 517-719-2801
I. Evaluation Process The full evaluation process is stated in the Bidding and Contract Documents. The evaluation will be done primarily by the Professional Services Contractor, with assistance from the Design and Construction Project Director.
II. Evaluation Method Responses to this solicitation were reviewed by the professional, AECOM, with the DCD Project Director.
III. Bidders The RFQ was posted on SIGMA VSS, 6/3/2025. The following bidders submitted proposals, by the published due date of, 7/9/2025 Please see attached Bid Tabulation sheet.
IV. Award Recommendation:
Award recommendation is made to the responsive and responsible Bidder who offers the best value to the State of Michigan. Best value is based on price and qualitative components. Award Recommendation is made to Derek Bradway dba/ Bradway Enterprises, in the amount of $675,599.00, pending appropriate approval and contract execution.
Recommendation Approved
08/12/2025 Adam P. Lach, Director Date State Facilities Administration – Design & Construction Division