MDW Cab Duct Heater Replacement Spec Combined Revised.pdf

PDF 4 MB Posted

Attached to
Cab Duct Heater Replacement (MDW ATCT)
Solicitation number
697DCK24R00199
Issued by

About this file

This document appears to be a set of specifications for the replacement of two electric duct heaters serving the Airport Traffic Control Tower Cab at Chicago Midway International Airport. The work includes modifying the existing control system, installing two industrial workstation fans, and providing technical support for the building automation system. The contractor will be required to minimize disruptions to air traffic operations and follow certain work hour restrictions and operational risk management procedures. The solicitation number is 697DCK24R00199 and the work must be completed within 60 calendar days after the notice to proceed. The contractor will be expected to perform a site visit to verify existing conditions prior to submitting a proposal.

View the file

Other files

File Type Posted
697DCK-24-R-00199 P0001.pdf PDF
MDW Cab Duct Heater Sketches 12-5-23.pdf PDF
Wage Determination -IL20240009-2.pdf PDF
697DCK-24-R-00199.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Issued for Proposal FAA-GL-MDW-CDHR-1222SW2334

12/5/2023

CHICAGO MIDWAY

INTERNATIONAL AIRPORT

CHICAGO, IL

AIRPORT TRAFFIC CONTROL TOWER

CAB DUCT HEATER REPLACEMENT

SPECIFICATIONS

Federal Aviation Administration

Central Service Area by

Terminal Engineering Center, Chicago

6200 Laramie Ave, Chicago, IL 60638, Cook County

FEDERAL AVIATION ADMINISTRATION DEC 2023

MDW CAB DUCT HEATER REPLACEMENT

GENERAL PARAGRAPHS 01 00 00 - 1

SECTION 01 00 00- GENERAL PARAGRAPHS

PART 1 - GENERAL

1.1 PRE BID SITE VISIT

A. The offeror is highly recommended to examine the areas of the proposed work to verify existing

1.2 conditions, quantities and site characteristics inherent to the work involved. The submission of a proposal will be considered prima facie evidence that the offeror is knowledgeable of the site conditions and areas to be encountered in performing the work. Any claims of contract extras due to unforeseen conditions that would have been identified during a pre-bid site visit will be denied. For access to the ATCT site, contact the Contracting Officer indicated in the solicitation. Facility Address: 6200 Laramie Ave, Chicago, IL 60638, Cook County

TIME FOR COMPLETION

The work must be completed within 60 calendar days after Notice to Proceed (NTP) or as defined in the General Contract. Contractor must identify a schedule for work completion. Due to operational risk management (ORM) requirements the contractor may be required to perform work during minimal air traffic periods (Typically 11PM – 5AM). The contractor may also be required to work with minimal noise, odor, or dust disturbance in the cab environment or in areas that affect the cab environment. This requirement may require work to be paused or slowed as to not disrupt air traffic services. Contractor must see ORM section of specification under SECTION 01 14 00 - CONDITIONS AFFECTING WORK for further information.

1.3 PLANS, SPECIFICATIONS, AND OTHER CONTRACT DOCUMENTS

A. The requirements of AMS Clause 3.2.2.3-33, Order of precedence and AMS Clause 3.2.2.3-60, Specifications, Drawings, and Material Submittals must apply.

B. Plans showing general outlines and details necessary for a comprehensive understanding of the work form a part of the Contract Documents. All work under the Contract must be performed in all respects in compliance with the requirements of the Contract Documents.

C. The Contract Documents provide for a complete work package and may have been prepared in divisions of various crafts, trades and other categories of work. The Contractor is responsible for the performance of all work under the Contract regardless of any such divisions and must ensure that all of the work is performed and completed.

D. The FAA will provide the Contractor electronic .pdf versions of the construction plans and specifications, if requested, marked for the Contractor’s use during the execution of the

Contract. The Contractor may reproduce these documents for its use during the performance of

GENERAL PARAGRAPHS 01 00 00 - 2

the work under this Contract.

E. The Contractor must maintain at the Site at all times at least one (1) copy of Plans, Technical Specifications and all other Contract Documents, together with at least one (1) complete set of approved Shop Drawings and approved samples.

F. The Contractor must make available at the job site one copy of each referenced standards and/or specifications for the Contractor’s and the FAA’s use during the time that work covered by the standards and/or specifications is underway.

G. The Contract, Plans, Specifications, and all referenced standards cited are essential parts of the Contract requirements. A requirement occurring in one is as binding as though occurring in all.

They are intended to be complementary and to describe and provide for a complete work.

H. In the event of any conflicts ambiguities, or discrepancies among the Contract Documents, the precedence in resolving such conflicts, ambiguities, or discrepancies must be as follows:

1. The Schedule of Bid Items

2. Representations and other instructions

3. Contract Clauses (also referred to General Conditions)

4. Contract modifications

5. Addenda

6. General Conditions must govern over Division 1, Technical Specifications and Plans.

7. Division 1 must govern over Technical Specifications and Plans.

8. Technical Specifications must govern over Plans.

9. On the Plans, calculated or figured dimensions must govern over scaled dimensions.

10. Subject to the foregoing provisions of this paragraph, the more stringent requirements must apply in the event any conflicts cannot be resolved by applying the order of precedence.

I. The Contractor must not take advantage of any apparent error, omission, discrepancy, or ambiguity on the Plans or Specifications. If any error, omission, discrepancy, or ambiguity is found by the Contractor in the Plans or Technical Specifications, the Contractor must refer the same to the Contracting Officer (CO) for his interpretation and decision, and such decision must be final.

J. The CO must have the right to correct apparent errors or omissions in the Plans and Technical Specifications and to make such interpretations as he may deem necessary for the proper fulfillment of the Contract Documents. During the course of the work, should any conflicts, ambiguities, or discrepancies be found that are not addressed or any discrepancies between the Plans and the Technical Specifications to which the Contractor has failed to call attention before submitting the offer, then the CO will interpret the intent of the Plans and Technical Specifications and the Contractor hereby agrees to abide by the CO’s interpretation and agrees to carry out the work in accordance with the decision of the CO. In such event the Contractor will be held to have included in the offer the most expensive material and/or method of construction.

K. When a material, article, or equipment is designated by a brand name, and more than one brand

GENERAL PARAGRAPHS 01 00 00 - 3

name is listed, it will be understood that the design is based on one of the brand name listed products. The contractor will be responsible for all coordination necessary to accommodate the material, article, or equipment actually being provided without additional cost to the government.

L. The organization of the contract Documents into divisions, sections and articles, and the arrangement of Drawings does not restrict or limit the Contractor in dividing the Work among

Subcontractors or in establishing the extent of work to be performed by any trade.

M. Product and Reference Standards:

1. When descriptive catalog designations including manufacturer’s name, product brand name, or model number are referred to in the Contract Documents, such designations must be considered as being those found in industry publications of current issue on the date of the first advertisement for offers.

2. When standards of the Federal Government, State Department of Transportation, Standards Organization such as ASTM, AASHTO, AWS, or ANSI, trade societies, or trade associations are referred in the Contract Documents by specific date of issue, these must be considered a part of this Contract. When such references do not bear a date of issue, the current published edition on the date of the first advertisement for offers must be considered as part of the Contract.

3. Where in the Contract Documents an item is identified by a particular manufacturer’s name, model or other code it must be interpreted to include other manufacturers’ product of like and equal quality whether the words “or equal” are included or not.

4. Wherever a particular manufacturer’s product is required, to the exclusion of all others, appropriate language is included in the Contract Documents.

5. Wherever the terms, “as directed”, “ordered”, “permitted”, “designate”, “as approved”, “approved equal”, “or equal”, “acceptable” and other words of similar meaning which authorize an exercise of judgement are used in the Contract Documents, such judgment must be vested only in the Architect/Engineer and/or the FAA.

1.4 CONFORMITY WITH PLANS AND SPECIFICATIONS

A. No deviation from the Plans, Technical Specifications and other Contract Documents must be permitted without the prior written approval of the COR.

1.5 SUPERVISION AND CONSTRUCTION PROCEDURES

A. At all times during performance of this contract, and until the work is completed and accepted, the Contractor must directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the CO and has the authority to act for the

Contractor.

B. The Contractor must supervise and direct the Work, using the Contractor's best skill and attention. The Contractor must be solely responsible for and have control over construction means, methods, techniques, sequences, and procedures and for coordinating all portions of the

Work under the Contract including coordination of the duties of all trades, unless the Contract

GENERAL PARAGRAPHS 01 00 00 - 4

Documents give other specific instructions concerning these matters.

1.6

C. The Contractor must control its operations and those of its Subcontractors and Suppliers to assure the least inconvenience to the traveling public. Under all circumstances, safety must be the most important consideration.

D. Contractor must lay out all work well enough in advance to avoid conflicts or interferences with other work in progress so that in case of interference the layout may be altered to suit the conditions, prior to the installation of any work and without additional cost to the FAA. The contractor must be responsible to coordinate all work and take all action as required to avoid conflicts between trades.

CORRESPONDENCE

A. Contract correspondence must be directed to the CO with a copy to the COR. Submittals will be sent direct to the COR with a copy of the transmittal letter to the CO.

1.7 LIST OF SUBCONTRACTORS

A. The Contractor must, within 10 calendar days after award, furnish to the CO with a copy to the

COR, a list of subcontractors showing the type of work each will perform. If all subcontracts have not been awarded when the initial list is submitted, the Contractor must update the list.

1.8 PRECONSTRUCTION CONFERENCE

A. The CO will arrange a conference at a location, mutually agreeable to the CO and the

Contractor as soon as practicable after award of a contract. It will be mandatory that the

Contractor or his designated representative attends.

1.9 WORK NOT INCLUDED

A. Items noted on the drawings, details, or schedules as "NIC” (Not in Contract) are not included in this contract.

1.10 CHANGED CONDITIONS

A. Wherever changed conditions as defined in Contract Clause entitled, "Changes and Changed

Conditions" are encountered, and wherever conditions exposed during the course of the work necessitate a change from quantities indicated or specified as either estimated quantities or as a basis for offers, whether or not provision for a change in price for such variation is specified, the CO must be notified in writing and written directions to do so must be obtained before quantities stated in the contract documents are exceeded.

1.11 EXISTING WORK

GENERAL PARAGRAPHS 01 00 00 - 5

A. The disassembling, disconnecting, cutting, removal, or altering in any way of existing work must be carried on in such a manner as to prevent injury or damage to all portions of existing work, whether they are to remain in place, be re-used in the new work, or be salvaged and stored.

B. All portions of existing work which have been cut, damaged, or altered in any way during construction operations must be repaired or replaced in kind in an approved manner to match existing or adjoining work. All work of this nature must be performed by the Contractor at his expense and must be as directed. Existing work must, at the completion of all operations, be left in a condition as good as existed before the new work started.

1.12 MATERIALS AND EQUIPMENT TO BE SALVAGED

A. Except where specifically specified otherwise herein, or designated on the drawings, all existing

1.13 materials and equipment which are required to be removed or disconnected to perform the work but are not indicated or specified for use in the new work, must become the property of the

Contractor and must be disposed of properly. The Government may elect to salvage any or all materials removed by the Contractor by giving prior notice and pricing up materials at job site.

PARTIAL OCCUPANCY OR USE

A. The FAA may occupy or use any completed or partially completed portion of the Work at any

1.14 stage and, if the FAA chooses such partial occupancy, the Contractor and FAA must designate by an agreement the conditions of such partial occupancy. Such partial occupancy or use may commence whether or not the portion is substantially complete, provided the FAA and Contractor have accepted in writing the responsibilities assigned to each of them by the COR for payments, retainage if any, security, maintenance, heat, utilities, damage to the Work and insurance, and have agreed in writing concerning the period for correction of the Work and commencement of warranties required by the Contract Documents.

Consent of the Contractor to partial occupancy or use by the FAA must not be unreasonably withheld.

UNCOVERING AND CORRECTION OF WORK

A. Uncovering Work

1. If any portion of the Work is covered contrary to the COR 's request or to requirements specifically expressed in the Contract Documents, it must, if required in writing by the

COR be uncovered for his observation and be recovered (if corrections are not required) or be corrected, if applicable, at the Contractor's expense without change in the Contract

Time.

2. If a portion of the Work has been covered which the COR or any applicable governmental authority has not specifically requested to observe prior to its being covered, the COR may request to see such Work and it must be uncovered by the

Contractor. If such work is in accordance with the Contract Documents, costs of uncovering and restoration must, by appropriate Change Order, be charged to the FAA.

GENERAL PARAGRAPHS 01 00 00 - 6

If such Work is not in accordance with the Contract Documents, the Contractor must pay such costs unless the condition was caused by the FAA or a separate contractor in which event the FAA must be responsible for payment of such costs.

B. Correction Of Work

1. The Contractor must promptly correct Work rejected by the COR or any governmental authority that fails to conform to the requirements of the Contract Documents, whether observed before or after Substantial Completion and whether or not fabricated, installed or completed. The Contractor must bear all costs of correcting such rejected Work, including additional testing and inspections and compensation for the COR 's services and expenses incurred by the FAA.

2. If, within two years after the date of Substantial Completion of the Work or designated portion thereof, or after the date for commencement of warranties established above, or by terms of an applicable special warranty required by the Contract Documents, any of the work is found to be not in accordance with the requirements of the Contract Documents, the Contractor must correct it promptly after receipt of written notice from the FAA to do so unless the FAA has previously given the Contractor a written acceptance of that specific condition. This period of two years must be extended with respect to portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual performance of the Work. This obligation must survive acceptance of the Work under the Contract and termination of the Contract. The FAA must give such notice within a reasonable amount of time after discovery of the condition.

3. The Contractor must remove from the site portions of the Work that are not in accordance with the requirements of the Contract Documents and are neither corrected by the Contractor nor accepted by the FAA.

4. If the Contractor fails to correct nonconforming Work within a reasonable time, the FAA may correct it in accordance with General Provisions. If the Contractor does not proceed with correction of such nonconforming Work within a reasonable time fixed by written notice from the COTR, the FAA may correct or remove such nonconforming work and all costs for such corrections or removals must be assessed against the Contractor.

5. The Contractor must bear the cost of correcting destroyed or damaged Work, whether completed or partially completed, of the FAA or separate contractors caused by the Contractor's performing correction or removal of Work which is not in accordance with the requirements of the Contract Documents.

6. Nothing contained herein must be construed to establish a period of limitation with respect to other obligations that the Contractor might have under the Contract Documents. Establishment of the time period of two years as described above relates only to the specific obligation of the Contractor to correct the Work, and has no relationship to the time within which the obligation to comply with the Contract Documents may be sought to be enforced, nor to the time within which proceedings may be commenced to establish the Contractor's liability and damages with respect to the Contractor's obligations other than specifically to correct the Work.

C. Acceptance Of Nonconforming Work

1. If the FAA prefers to accept Work that is not in accordance with the requirements of the

GENERAL PARAGRAPHS 01 00 00 - 7

Contract Documents, the FAA may do so instead of requiring its removal or correction.

If the FAA accepts the Work under such circumstances, the Total Contract Price will be reduced in an equitable manner as determined by the Contracting Officer, whether or not final payment has been made.

D. Terms and Conditions” and “Contract Clauses”

1. Wherever a reference to a clause of the General Provisions or General Conditions occurs in the technical section of the specifications, it must be taken to mean the “Terms and Conditions” and “Contract Clauses” having the same title as the referenced General Provisions or General Conditions clause.

1.15 COOPERATE WITH AGENCIES

A. Cooperate with the FAA public or private utility service, or a utility service of another government agency that may be authorized by the FAA to construct, reconstruct, or maintain such utility services or facilities during the progress of the work. Control operations to prevent the unscheduled interruption of such utility services and facilities.

1.16 NOTICE TO FAA/OPERATORS

A. Prior to commencing the work in the general vicinity of an existing utility service or facility, 1.17

Contractor must notify each FAA/operator in writing of activities that might affect its interests.

If, in Contractor’s opinion, the FAA/operator’s assistance is needed to locate the utility service or facility or the presence of a representative of the FAA/operator is desirable to observe the work, such advice should be included in the notification. Furnish a copy of such written notices to COTR.

DAMAGE TO SERVICES

A. Should Contractor damage or interrupt the operation of a utility service or facility by accident or

1.18 otherwise, it must immediately notify in writing the FAA/operator, appropriate public safety authorities, and the COTR and must take all reasonable measures to prevent further damage or interruption of service. Cooperate with the utility service or facility FAA and the COTR continuously until such damage has been repaired and service restored.

FAILURE TO PROTECT PROPERTY

A. Contractor must not be entitled to any extension of time or compensation on account of

1.19

Contractor’s failure to protect all facilities, equipment, materials and other property as described herein. All costs in connection with any Improvements or restoration necessary or required by reason of unauthorized obstruction, damage, or use must be borne by Contractor.

UTILITY CONTRACTOR LICENSING REQUIREMENTS

A. Contractor must comply with all state and local requirements for construction of utilities.

GENERAL PARAGRAPHS 01 00 00 - 8

1.20 ASBESTOS AND LEAD FREE CERTIFICATION

A. FAA policy is to construct all new facilities without asbestos or lead containing products. The Contractor must provide a letter on his company’s standard letter head stating that to the best of his knowledge no product or material used on this project contains asbestos or lead. The statement must include the name of the project and the contract number and must be signed by an officer of the company. The statement must be furnished within 10 calendar days of the beneficial occupancy date. Submission of this statement is a calendar days of the beneficial occupancy date. Submission of this statement is a calendar days of the beneficial occupancy date. Submission of this statement is a condition for final payment under the contract.

B. Verification: If the FAA suspects the presence of asbestos or lead, tests must be performed on the material or product at the FAA’s expense. If it is determined that the product or material does contain asbestos or lead, then the contractor must remove the product or material and replace at his own expense including the expense of the testing and any retesting that may be necessary.

C. Non – Compliance: If the Contractor fails to provide the above statement, then the FAA must have a complete building survey performed by a qualified testing firm and the costs deducted from the contractor’s final payment.

PART 2 - PRODUCTS

NOT USED

PART 3 - EXECUTION

NOT USED

END OF SECTION 01 00 00

SUMMARY OF WORK 01 10 00 - 1

SECTION 01 10 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Type of the Contract.

3. Work phases.

4. Work under other contracts.

5. Products ordered in advance.

6. FAA-furnished products.

7. Use of premises.

8. FAA's occupancy requirements.

9. Work restrictions.

10. Specification formats and conventions.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Scope of Work.- Offeror is highly recommended to perform a site visit to verify existing conditions and quantities. Work consists of, but is not limited to, the following:

1. Replacement of two existing electric duct heaters serving the Airport Traffic Control Tower Cab including all remote panelboards and ancillary equipment.

2. Modification of existing control system for step control of duct heater application into existing facility sequence of operations. Control work must be through existing control company ABC Controls on existing Alerton BACtalk control system.

3. Installation of two industrial workstation fans in space above cab ceiling.

4. 80 hours of building automation system technical support from existing control system support supplier to correct problems with the existing operation of the cab and facility HVAC system.

5. A quote for additional add option of 40 hour increments of technical support for programming of Alerton BACtalk Building Automation System.

1.3 CONTRACT METHOD

A. Construct the Work under a single lump sum contract with additional option adds as identified.

1.4 WORK BY OTHERS

A. Work of the Project which will be executed by others is designated N.I.C.

SUMMARY OF WORK 01 10 00 - 2

1.5 WORK SEQUENCE

A. Construction Work stages must be defined by the General Contractor.

1.6 CONTRACTOR USE OF PREMISES

A. Assume full responsibility for protection and safekeeping of project materials under this

Contract.

B. Obtain and pay for use of additional storage or work areas needed for operations under this

Contract.

C. Parking is not allowed along existing roads or within portions of the site used for active FAA operations.

1.7 ACCESS TO SITE

A. The Contractor must submit for approval the material, equipment, storage and parking areas.

1.8

The Contractor must not permit any unauthorized construction personnel or traffic on the site.

The

Contractor must be responsible for traffic control to and from the various construction areas on the site. Directional signing at the access gate and along the delivery route to the storage area or work site must be as directed by the COTR. The Contractor will not be allowed to close any traffic lanes nor will the Contractor be allowed to impede the flow of airport traffic.

MATERIALS DELIVERY TO THE SITE

A. All material orders for delivery to the site must use as a delivery address the address of the airport traffic control tower. Delivery trucks must not pass in front of the terminal.

B. Contractor must prepare, and submit to the COR for approval, a delivery plan for all types of delivery. The plan must define the procedures that will be used to accommodate delivery traffic for all types of deliveries (e.g. concrete/asphalt, steel, precast, earth/aggregate, tractor trailer, city delivery truck) and any staging areas that will be used. Normal flow of traffic, into and out of the airport, must not be impeded. Deliveries must be suspended at the direction of the COR.

C. The Contractor is responsible for immediate clean-up of any debris deposited along the access road as a result of his/her construction traffic.

1.9 CONSTRUCTION AREA LIMITS

A. The limits of construction material storage areas, equipment storage areas, parking areas, and other areas as required by the Contractor must be as shown on the plans or as approved by the

COR. Should Contractor find it necessary or advantageous to use any additional offsite area for any purpose whatsoever, Contractor must, at its expense, provide and make its own arrangements for the use of such additional offsite areas.

B. Erect and maintain fencing, marking, and/or warning devices suitable for both day and night use to delineate the perimeter of all such areas.

SUMMARY OF WORK 01 10 00 - 3

C. When the Work requires Contractor to conduct operations within areas adjacent to active airport, the Work must be coordinated with the FAA through the COR.

D. Employee Parking. Parking will not be allowed along public right of way or the entrance/exit road. Parking is very tight at the facility; in the event adequate space is not available for parking on the project site the Contractor must arrange for off-site parking and provide bus transportation of employees to and from the site. No other areas will be made available for Contractor use for parking, staging, trailers, or storage.

1.10 PERMITS AND FEES

A. Contractor is responsible for paying all charges associated with the construction of the project.

PART 2 - PRODUCTS

NOT USED

PART 3 - EXECUTION

END OF SECTION 01 10 00

SUMMARY OF WORK 01 10 00 - 4

PAGE INTENTIONALLY LEFT BLANK

CONDITIONS AFFECTING WORK 01 14 00 - 1

SECTION 01 14 00 - CONDITIONS AFFECTING WORK

PART 1 – GENERAL

1.1 WORK SCHEDULE

A. The Chicago Midway International Airport Traffic Control Tower operates 24 hours a day, 7 days per week. It will be necessary to coordinate construction activity so as not to interfere with functions of the FAA or Airport. Loss of FAA equipment for any amount of time may jeopardize the safety of the flying public and may result in criminal charges against the Contractor. The Contractor will be required to follow certain limitations on their work hours for Operational Risk Management (ORM) purposes. Limitations are identified in ORM section (01 14 00 - 1.4) of this specification.

B. Normal working hours are 0700 to 1600, Monday through Friday (except U.S. holidays). The contractor may be required to work hours that minimize impact to air traffic; those hours are typically 0000 to 0500 but may vary depending on the facility and COR direction. See specification ORM section for guidance on guidance on how to consider this direction for bidding.

Contractor requests to work outside normal working hours require COR approval. However, the COR has full discretion to approve or disapprove, or withdraw approval of, requests. If the contractor desires to work outside normal hours (including Saturdays, Sundays, and holidays), he must submit his request to the COR at least 48 hours in advance. Some typical constraints on working outside normal working hours are:

1. The Contractor’s request must be made at least two days in advance (e.g., request received by close of business Wednesday for work on following Saturday). Prior to submitting the request, the Contractor must coordinate as needed (such as utility outages) and have all required people and materials for the work that will be performed.

2. A Contractor with quality or safety problems (as determined by the COR) will usually be restricted to normal working hours.

3. A Contractor who fails to correct deficiencies within a reasonable time (as determined by the COR) usually will be restricted to normal working hours or may be allowed to work outside normal working hours only to correct those deficiencies.

4. The Contractor must schedule his work to cause the least amount of interference to normal activities.

1.2 FAA OPERATIONS

A. Safety of the FAA National Airspace System (NAS) operations take precedence over any contractual work in this contract. The FAA has a safety program to help protect those operations titled Operational Risk Management or ORM. If anyone identifies personnel safety or NAS safety issues related to work under this contract, work must be stopped and the issues must be addressed immediately. If the contractor is notified of personnel or NAS safety issues associated with their

CONDITIONS AFFECTING WORK 01 14 00 - 2

work under this contract, they must immediately bring those issues to their FAA point of contact.

B. The FAA has established moratorium dates for construction activity at critical Air Traffic Control facilities. The intent is to minimize impact on the ability of FAA to perform its operational activities during peak air travel dates. Moratorium dates are typically scheduled over the

Thanksgiving Holiday and the Christmas/New Year Holiday. Exact dates will be provided at the preconstruction conference.

C. All construction activity during moratorium periods must be approved in advance by the FAA.

Submit items of work to be performed during moratorium dates no later than forty-five (45) days prior to the moratorium dates. Activities that have, in the sole opinion of the FAA, potential to negatively impact FAA operations will not be approved. A written waiver will be provided by

FAA to the Contractor outlining the allowable work items. No additional time or cost will be allowed for such denial.

1.3 AIRPORT OPERATIONS

A. RESTRICTIONS TO ACCESS - Access to work areas may be restricted from time to time by necessity of airport operations. Contractor acknowledges that it has taken into account and provided in its planning, scheduling and pricing for disruptions including but not limited to, restricted access to portions of the site that will not be immediately available, delivery time limitations, and moratorium dates.

B. OBSTRUCTION (OB) LIGHTS AND MARKINGS - Temporary obstruction lights and markings must be mounted on the highest point of any equipment used during the performance of work in accordance with Airport requirements

C. ILLUMINATION (EXTERIOR) – Ground level lights will be permitted to facilitate construction activity upon approval of the COR. Location and direction of illumination will be subject to acceptance by Air Traffic Control, which must have final authority concerning this matter.

Remove and/or reposition lights as required without additional cost to the FAA.

1.4 OPERATIONAL RISK MANAGEMENT (ORM)

A. ORM CONTRACTOR LIMITATIONS - The FAA has a safety program to help protect FAA operations titled Operational Risk Management or ORM. The program will require the contractor to follow guidelines and mitigations that are implemented to protect personnel and NAS Operations. The Contractor will be required to follow certain limitations on their work hours, performance criteria, sequencing of activities, and/or methods and means for Operational Risk Management (ORM) purposes.

B. CONTRACTOR ORM VIDEO – Each contractor or subcontractor performing work under this contract at any FAA facility must watch an approximately 6 minute video on ORM concepts and requirements at the FAA. Your work is important to the safety of the National Airspace System (NAS). This video will provide everyone with a basic understanding of the air traffic

CONDITIONS AFFECTING WORK 01 14 00 - 3

control environment where contractors will be working. The video will also include some do’s and don’ts, so your work won’t interfere with the safety critical work being done at FAA facilities. This video can be found at the following site:

https://www.youtube.com/watch?v=yyq9ESQ8vds

C. PROJECT RISK PLAN (PRP) – The FAA has performed a strategic operational risk analysis resulting in a Project Risk Plan (PRP). This plan identifies risks, operational consequences, and corresponding mitigations that must be implemented as a result of certain activities associated with this project. This information will be shared with the contractor at project kick off. The contractor will be expected to follow the PRP to the best of their ability during this project. In this specification the contractor is given information that should allow them to prepare their bid for the identified mitigations in the PRP. Those mitigations will be listed in the section titled

OPERATIONAL RISK MANAGEMENT (ORM), KNOWN RISK MITIGATIONS.

D. OPERATIONAL RISK MANAGEMENT PLAN (ORMP) – Some project related activities identified in the PRP will need specific coordination in regards to when and who will be performing those activities. For those activities the FAA will need to approve an Operational Risk Management Plan (ORMP) before those activities are accomplished. The contractor must be aware that they are not allowed to proceed with activities that need an ORMP until given specific direction from the COR.

E. TAKE 5 – The FAA has a safety concept under ORM known as “Take 5”. FAA employees have a responsibility to “Take 5” whenever they identify a safety related issue as part of the construction /installation contract. Employees are empowered to stop the work being performed until a “Take 5” evaluation is performed. If any contractor or subcontractor is notified of a “Take 5” situation, they should stop work immediately and contact their FAA point of contact. If a contractor or subcontractor identifies activities that they feel would jeopardize their safety, the safety of the FAA equipment, or the safety of personnel in the FAA facility, they should also “Take 5”. Once the FAA point of contact has been notified of a “Take 5” situation, they will coordinate with the contractor and any impacted personnel to evaluate the situation. They will ensure that work proceeds in a manner that protects the safety of personnel and the National Airspace System (NAS) Equipment.

If the Take 5 evaluation delays the project significantly enough for a contractor claim, that claim must be handled through the normal contracting processes.

F. KNOWN RISK MITIGATIONS – The following are known risks and the corresponding mitigations the contractor will be expected to implement in order to protect the National Airspace

System (NAS) equipment and services associated with this project:

Loss of HVAC systems in the Cab The contractor must work on one duct heater in each air handling system at a time for work associated with this project. The ductwork system must be isolated to minimize impact from the system being worked upon. Local facility representatives will be https://www.youtube.com/watch?v=yyq9ESQ8vds

CONDITIONS AFFECTING WORK 01 14 00 - 4

responsible for de-energizing or energizing of any equipment necessary to modify the systems. The contractor must provide the COR 8 hours’ notice when they are ready to work on a subsequent duct heater. When performing any direct work on the air handling system that could in the

FAA’s opinion cause an issue to the cab environment, the contractor can expect to work outside of normal business hours typically (11PM –

5AM) When working on any overall software control parameters, the contractor may be required to work outside normal working hours typically (11PM – 5AM) .

Contractor must bid with expectation for 40 hours of work outside of normal working hours for duct heater replacement modifications.

Fumes or odors or dust from project The contractor must provide the COR all sealants or lubricants required for the project for smell testing with local facility personnel. If dust from cutting, or smell from sealants are determined to be objectionable, the contractor may be required to do that work after normal working hours. Contractor must bid the work knowing that any smells or dust that impacts the safe control of air traffic will only be allowed after extensive odor or dust mitigations are implemented to a point of acceptable levels identified by the facility occupants. The contractor must bid with the expectation that some of the work may need to be done at a slower or less odor generating pace when replacing ductwork or unit heaters. Noise and Vibration Contractor will be required to demonstrate the noise and vibration levels caused from work associated with duct heater replacement. If noise or vibration impacts the operation of controllers in the facility, work will be

CONDITIONS AFFECTING WORK 01 14 00 - 5

required to be done after normal business hours. Contractor must bid the work knowing that excessive noise or vibration may not be allowed during normal business hours. Some of the work may need to be done at a slower or less noisy pace when replacing ductwork or unit heaters.

Control Outage In additional add bid for control modification work, the contractor must expect to work off line for control modifications. When modifications to operational system are needed, contractor must expect to perform this work after normal business hours. Cab Ceiling Work Work within the Airport Traffic

Control Cab can be distracting to controllers at Chicago Midway

International Airport. When work is to be done in the Control Cab, the contractor must expect to perform this work after normal business hours.

SECTION 2 - PRODUCTS

NOT USED

SECTION 3 - EXECUTION

END OF SECTION 01 14 00

CONDITIONS AFFECTING WORK 01 14 00 - 6

PROJECT MEETINGS 01 31 19 - 1

SECTION 01 31 19 - PROJECT MEETINGS

PART 1 - GENERAL

1.1 REQUIREMENTS INCLUDED

A. Contractor participation in pre-construction conferences.

B. Contractor administration of progress meetings and pre-installation conferences.

1.2 PRE-CONSTRUCTION CONFERENCES

A. The FAA will hold a pre-construction conference. The contractor is expected to participate in this meeting to go over contract requirements.

1.3 PROGRESS MEETINGS

A. The FAA will schedule and administer daily project activity meetings at approximately 7:45 AM.

The contractor must be expected to provide information to the COR by 6:30AM of any activities that will be performed at the FAA premises that day.

B. The FAA will schedule and administer Project meetings throughout progress of the work at weekly intervals as well as any called meeting. The contractor is expected to participate in these meetings.

C. Attendance: Job superintendents, Local Tech Ops and AT Representative; and COR as appropriate to agenda topics for each meeting.

D. General Contractor must prepare agenda and minutes of FAA weekly meetings.

E. Agenda will include review of Work progress, status of progress schedule and adjustments thereto, delivery schedules, submittals, maintenance of quality standards, pending changes and substitutions, RFI status, three (3) weeks ahead schedule and other items affecting progress or work.

PART 2 - PRODUCTS

NOT USED

PART 3 - EXECUTION

END OF SECTION 01 31 19

PROJECT MEETINGS 01 31 19 - 2

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 1

SECTION 01 32 00 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Preliminary Construction Schedule.

2. Contractor's Construction Schedule.

3. Submittals Schedule.

4. Daily construction reports.

5. Material location reports.

6. Field condition reports.

7. Special reports.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by COR.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Event: The starting or ending point of an activity.

F. Float: The measure of leeway in starting and completing an activity.

1. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 2

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

H. Major Area: A story of construction, a separate building, or a similar significant construction element.

I. Milestone: A key or critical point in time for reference or measurement.

J. Network Diagram: A graphic diagram of a network schedule, showing activities and activity relationships.

K. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

1.3 SUBMITTALS

A. Submittals Schedule: Submit three copies of schedule. Arrange the following information in a tabular format:

1. Scheduled date for first submittal.

2. Specification Section number and title.

3. Submittal category (action or informational).

4. Name of subcontractor.

5. Description of the Work covered.

6. Scheduled date for COR's final release or approval.

B. Preliminary Construction Schedule: Submit three opaque copies.

1. Approval of cost-loaded preliminary construction schedule will not constitute approval of

Schedule of Values for cost-loaded activities.

C. Contractor's Construction Schedule: Submit three opaque copies of initial schedule, large enough to show entire schedule for entire construction period.

1. Submit an electronic copy of schedule, using software indicated, on CD-R, and labeled to comply with requirements for submittals. Include type of schedule (Initial or Updated) and date on label.

D. Daily Construction Reports: Submit two copies at weekly intervals.

E. Material Location Reports: Submit two copies at weekly intervals.

F. Field Condition Reports: Submit two copies at time of discovery of differing conditions.

G. Special Reports: Submit two copies at time of unusual event.

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 3

1.4 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.

B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from parties involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

2.1 SUBMITTALS SCHEDULE

A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, manufacturing, fabrication, and delivery when establishing dates.

1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and

Contractor's Construction Schedule.

2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Substantial and Final Completion.

1. Contract completion date must not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

B. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:

1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by COR.

2. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

3. Submittal Review Time: Include review and resubmittal times indicated in Section 01 33 00 "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule.

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 4

4. Substantial Completion: Indicate completion in advance of date established for

Substantial Completion, and allow time for COR's administrative procedures necessary for certification of Substantial Completion.

C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.

1. Phasing: Arrange list of activities on schedule by phase.

2. Work under More Than One Contract: Include a separate activity for each contract.

3. Products Ordered in Advance: Include a separate activity for each product.

4. Work Restrictions: Show the effect of the following items on the schedule:

a. Coordination with existing construction.

b. Limitations of continued occupancies.

c. Uninterruptible services.

d. Partial occupancy before Substantial Completion.

e. Use of premises restrictions.

f. Provisions for future construction.

g. Seasonal variations.

5. Work Stages: Indicate important stages of construction for each major portion of the Work, including, but not limited to, the following:

a. Subcontract awards.

b. Submittals.

c. Purchases.

d. Mockups.

e. Fabrication.

f. Sample testing.

g. Deliveries.

h. Installation.

i. Tests and inspections.

j. Adjusting.

k. Curing.

l. Startup and placement into final use and operation.

6. Area Separations: Identify each major area of construction for each major portion of the Work.

CI. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion.

CII. Cost Correlation: At the head of schedule, provide a cost correlation line, indicating planned and actual costs. On the line, show dollar volume of the Work performed as of dates used for preparation of payment requests.

1. Contractor must assign cost to construction activities on the CPM schedule. Costs must not be assigned to submittal activities unless specified otherwise but may, with COR's approval, be assigned to fabrication and delivery activities. Costs must be under required principal subcontracts for testing and commissioning activities, operation and maintenance manuals, punch list activities, Project Record Documents, and

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 5

demonstration and training (if applicable), in the amount of 5 percent of the Contract

Sum.

2. Each activity cost must reflect an accurate value subject to approval by

COR.

3. Total cost assigned to activities must equal the total Contract Sum.

F. Contract Modifications: For each proposed field directive or contract modification and concurrent with its submission, prepare a time-impact analysis to demonstrate the effect of the proposed change on the overall project schedule.

G. Computer Software: Prepare schedules using a program that has been developed specifically to manage construction schedules.

2.3 PRELIMINARY CONSTRUCTION SCHEDULE

A. Bar-Chart Schedule: Submit preliminary horizontal bar-chart-type construction schedule within seven days of date established for the Notice to Proceed.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line. Outline significant construction activities for first 60 days of construction. Include skeleton diagram for the remainder of the Work and a cash requirement prediction based on indicated activities.

2.4 CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART)

A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal Gantt-chart-type, Contractor's Construction Schedule within 30 days of date established for the Notice to Proceed.

Base schedule on the Preliminary Construction Schedule and whatever updating and feedback was received since the start of Project.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.

1. For construction activities that require 3 months or longer to complete, indicate an estimated completion percentage in 10…

This is the start of the file's text. The full file is on GovTribe.