STATEMENT OF WORK

Project No. MDVL222104

Key Field Air National Guard Base, Meridian, Mississippi

RENOVATE SQUAD OPS RESTROOMS BLDG 308

24 MAY 2022

I. PURPOSE: This Statement of Work provides the requirements necessary to renovate the squadron operations restrooms in Bldg 308.

A. APPLICABLE REFERENCE DOCUMENTS:

1. Construction Plan Set

2. As-Built Facility Construction Plans available upon request.

II. REQUIREMENTS: The Contractor shall provide all, labor, supervision, parts, materials, equipment, tools, freight, rigging, temporary toilet facilities (if required) and transportation required at Key Field Air National Guard Base, as requested and described below.

A. DEMOLITION:

1. Generally, refer to D-1 of the Construction Plan Set for demolition requirements.

2. Demolish and dispose of all existing lay-in acoustical tile ceiling system in Rooms 111, 111A, and 115.

3. Safely disconnect and demolish existing lighting in Rooms 111, 111A, and 115.

4. Demolish existing wall tile, base, floor tile, showers and stalls, urinals, water closets, lavatories, waste receptacles, mirrors, accessories, and partitions in Room 111, 111A, and 115. In-fill at demolished waste receptacle locations with CMU or metal stud and cement board construction.

5. Protect existing HVAC ducts and grilles as well as floor drains throughout demolition and construction. Ensure dust, debris, trash, mortar, etc. does not enter drain or HVAC systems.

6. Remove and reinstall existing mass notification devices and speakers.

7. Remove and reinstall existing paper towel dispensers.

8. Modify lighting controls as shown on Sheets D-1 and E-1.

9. Disconnect and remove all power and wiring along with conduit not planned for reuse back to the nearest junction box.

10. Remove, demolish, and/or modify existing water supply and drain lines as necessary to accommodate proposed improvements. Existing supply or drain lines not proposed for re-use shall be removed or adapted for abandonment in accordance with industry standards.

11. All features of the facility not set to be demolished must be protected or restored to original condition at project completion.

B. IMPROVEMENTS:

1. Construct new 6” metal stud partition walls in Room 111A as shown on Sheets A-1 and A-2.

2. In-fill walls at three former built-in waste receptacles with CMU or metal stud and cement board for new wall construction and tile covering in Rooms 111 and 115.

3. Provide finishes as shown on Sheet A-1 and A-2 to include:

a. Replace ceiling system (tile ceiling in new showers), replace floor tile, construct wall tile with integral tile base, construct tile showers (quantity 5), and paint door frames (quantity 4, Rooms 111, 111A, 113, and 115).

4. Paint all door frames (quantity 4) with enamel “Kaffe, SW6104, gloss finish” (or approved equal).

5. Install new ceiling grid and ceiling tile (Certainteed BET-157 or approved equal) in 2’x2’ pattern throughout project area.

6. New ceramic floor tile shall be 18”x18” nominal Daltile Severino Aria Sand (or approved equal) with Laticrete Chestnut Brown grout (stain and crack resistant, or approved equal).

7. New wall tile shall be 12”x18” Daltile Severino Aria Sand (or approved equal) with Laticrete Chestnut Brown grout (stain and crack resistant, or approved equal).

Decorative wall band (as shown on Sheet A-2) shall be 2x2 mosaic.

8. New shower floor tile shall be 2x2 mosaic, Daltile Severino Aria Sand (or approved equal) with Laticrete Chestnut Brown grout (stain and crack resistant, or approved equal). Contractor shall provide mosaic around floor drains or adjust floor drain elevation as required.

9. Provide and install all necessary bullnose, corners, and other tile shapes as necessary for a clean, professional installation. Provide clear anodized aluminum corners for all tile areas.

10. Provide floor-mounted, overhead-braced HDPE partitions as shown on Sheets A-1 and A-2. Partitions shall be Scranton Products Hiny Hiders, color: Concrete (or approved equal) with all metallic hardware (clear anodized).

11. Provide and install new bathroom accessories in Rooms 111 and 115 as depicted in the construction plan package to include: 3-18”x30” stainless mirrors with integral shelf (Bobrick B-166 or approved equal), 4 grab bars (Bobrick B-6806 or approved equal), and 5 stainless toilet paper holders (Bobrick B-2730 or approved equal).

12. Install all new mechanical and plumbing fixtures as shown in the mechanical schedule on Sheet P-1 (or approved equals).

13. Install new 8” diameter circular HVAC supply duct from trunk line located in adjacent Rooms 109 and 123 and three new supply grills as shown on Sheet P-1.

14. Install three new exhaust fans as shown on Sheet P-1. Exhaust fans shall be wired to the lighting circuits in each space.

15. Install all new lighting in all areas of the project as shown and described on Sheet E-1 (Lithonia or approved equal).

16. Modify lighting circuitry as noted on Sheet E-1.

17. All new “homerun” circuitry, as required, should be installed in EMT. “MC” type cable may be installed to new fixtures and devices.

18. Replace all receptacles, switches, and cover plates (color: Ivory).

19. All features of the facility not set to be repaired or replaced must be protected or restored to original condition at project completion.

C. Contractor shall take care not to damage the facility any more than necessary to perform the work, and shall protect and restore the area throughout construction. The Contractor is responsible to repair any damage to bring the facility back to pre-construction conditions.

D. JOB SITE INSPECTION. The Contractor shall keep all work sites clear of trash and debris. The Government will inspect the work area around the work site at its discretion.

Any cleaning or trash problems not corrected by the Contractor in a timely manner will result in payment being withheld until the problem is corrected.

E. TOOLS. The Contractor shall supply all tools and equipment to provide services required in this SOW. The Contractor SHALL NOT, at any time, borrow or use any tools or equipment from Key Field shops or its employees (state, contract, or federal). This includes forklifts, motorized lifts, electric carts, hand tools, power tools, etc.

III. PERIOD OF PERFORMANCE: The project shall be accepted as substantially complete within 60 calendar days after issuance of the Notice to Proceed.

IV. ENVIRONMENTAL MANAGEMENT: Key Field ANGB is committed to AFPD 90-8 for all base personnel and operations to include construction and all contractors working on behalf of the Government. The primary tenets of AFPD 90-8 are: Environmental Compliance, Risk Management, and Continuous Improvement. As applicable, the Contractor is responsible for the following:

1. Provide copies of all Hazardous Material SDS’s (oil, paints, adhesives, refrigerant, etc) to the Contracting Officer for approval prior to use, and provide total usage of each item upon completion and prior to project closeout for required EPCRA 313 tracking. Additionally, any reclaimed or re-used refrigerant must be documented at project closeout by weight, type, and management method.

2. Provide secondary containment for all liquid Hazardous Materials in containers 55 gallons or larger.

3. Track and report amount of waste generated and method of disposal (recycled, reused, or landfilled). All waste must be managed or disposed in a legal manner.

Unless specifically noted, all waste belongs to the Contractor. Key Field ANGB’s existing solid waste program, to include green boxes and construction debris containers, SHALL NOT be used for Contractor’s waste unless explicitly authorized in writing.

4. Coordinate and secure MDEQ permits, as applicable, for emissions equipment and Storm Water Construction.

The afore-mentioned items highlight requirements for service and construction contracts but are not all inclusive. A more in-depth Environmental Contractor Packet is available upon request.

V. QUALITY ASSURANCE: The Government will provide visual inspections as needed to ensure that all work described in this SOW are complete.

VI. WORK SCHEDULE: All installation work associated with this contract shall be accomplished during daily work hours between 07:00 a.m. to 04:30 p.m. Monday through Friday except for Federal Holidays and compressed work days. The Government must approve any deviation from these hours.

VII. WARRANTY: The Contractor to finish all work in a professional manner, employing best construction practices, using all new materials as approved by the owner (unless otherwise noted). Labor, equipment and materials installed by the Contractor shall be guaranteed by the Contractor to be free from defect for a period of one year (unless noted otherwise by specification) from the date of final acceptance.

VIII. SAFETY AND FIRE PREVENTION: Contractor must comply with all appropriate Occupational Safety and Health Administration (OSHA) and National Fire Prevention Association (NFPA) regulations during construction. Contractor shall receive a burn permit from the Fire Department at Key Field ANG Base prior to any hot work, welding, or potential fire hazard operations. All personnel working in or around the facility shall be thoroughly briefed on any dangers in the area.

IX. BASE & FACILITY ACCESS: The Contractor shall coordinate with the 186th Security Forces Squadron and Contracting Officer to gain access to Key Field ANG Base and the operating area where work is to be performed. Contractor shall also coordinate with the BCE to avoid adverse impacts to Key Field flying mission or mission support functions. The Contractor will have access to any base infrastructure (power, water) presently available in or nearby the construction area.

Any modifications to base infrastructure to assist in construction must be requested in writing, approved by the Base Civil Engineer, and performed by the Contractor.

END OF STATEMENT OF WORK