STATEMENT OF WORK

Project No. MDVL212111

Key Field Air National Guard Base, Meridian, Mississippi

RENOVATE OFFICE AND CLASSROOM AT COMMUNICATIONS

BLDG 603

7 JULY 2021

I. PURPOSE: This Statement of Work provides the requirements necessary to renovate existing areas in Bldg 603.

A. APPLICABLE REFERENCE DOCUMENTS:

1. Millwork Technical Specifications (attached)

2. Construction Plan Set

3. As-Built Facility Construction Plans (available upon request)

II. REQUIREMENTS: The Contractor shall provide all, labor, supervision, parts, materials, equipment, tools, freight, rigging, temporary toilet facilities (if required) and transportation required at Key Field Air National Guard Base, as requested and described below.

A. DEMOLITION:

1. Generally, refer to D1.0 of the Construction Plan Set for demolition requirements. This project affects existing room numbers 129, 130, 131, 133, 134, 135, 143, and 144.

Work may also be required in Rooms 132 and 142 for electrical and mechanical improvements.

2. Demolish and dispose of all existing lay-in acoustical tile ceiling systems, flooring, and lighting in Rooms 129, 130, 131, 133, 134, 135, 143, and 144. Contractor is responsible for safely relocating mass notification (MNS), fire alarm, and speaker devices in the ceiling. Government (Base Communications) will assist in disconnecting and reinstalling MNS.

3. Demolish and/or modify existing HVAC features within the project area, including exhaust fans, return duct, and cassettes, as noted on Sheet D1.0.

4. Demolish existing walls as shown on Sheet D1.0.

5. Demolish existing cabinetry in Rooms 133 and 135.

6. Disconnect and remove all power and wiring along with conduit not planned for reuse back to the nearest junction box.

7. Demolish, remove, and/or modify existing features as required for construction as noted in the plan set.

8. All features of the facility not set to be demolished must be protected or restored to original condition at project completion.

B. IMPROVEMENTS:

1. Provide and install new doors and frames as noted on Sheet A1.0. Wood door shall be clear finish, flush solid wood with birch veneer. Storefront door shall be clear anodized framing (Kawneer 451UT or approved equal) with clear glass (fully tempered ¼” thickness). Hardware packages shall be as noted in the door schedule on Sheet A1.0.

2. Provide finishes as shown on Sheet A1.0 and A1.1 to include: replace/install flooring, paint door frames and walls, and replace ceiling system. Refer to the finish schedule on Sheet A1.0 for limits of finish improvements and for room-specific information.

3. Paint all interior door frames throughout the project area (quantity 4 doors, including new frames) with enamel, color TBD by Government.

4. Install new ceiling grid and ceiling tile (Certainteed BET-157) in 2’x2’ pattern in identified areas throughout project area.

5. New ceramic floor tile shall be 18”x18” nominal Daltile Severino Aria Sand (or approved equal) with Laticrete Chestnut Brown grout (stain and crack resistant, or approved equal).

6. New wall tile in Room 130 shall be 12”x12” Daltile Severino Aria Sand (or approved equal) with Laticrete Chestnut Brown grout (stain and crack resistant, or approved equal) with similar 2”x2” decorative mosaic.

7. Provide and install all necessary bullnose, corners, and other tile shapes as necessary for a clean, professional installation.

8. Provide and install new bathroom accessories in Room 130 as depicted in the construction plan package to include: 18”x30” stainless mirror with integral shelf (Bobrick B-166 or approved equal), 2 grab bars (Bobrick B-6806 or approved equal), and 1 stainless toilet paper holder (Bobrick B-2730 or approved equal).

9. Install new millwork in Room 129 as shown on Sheets A1.0 and A1.1 according to the technical specifications.

10. Install all new mechanical and plumbing fixtures as shown in the mechanical schedule on Sheet MP1.0 (or approved equals).

11. Relocate two HVAC devices (1 cassette and 1 return) and modify remaining as necessary for new ceiling installation.

12. Install “T” valve under new sink in Room 129for future connection to Government-furnished refrigerator icemaker.

13. Provide new duplex receptacles, data infrastructure, and lighting controls as shown on Sheet E1.0.

14. BID OPTION #1 – Modify existing floor receptacle in Room 134 to provide 2 new circuits for installation of 5 new floor data/receptacle boxes as shown on Sheet E1.0.

Provide floor box equal to WireMold Evolution Series EFB45S. Each floor box shall be installed with 2 duplex receptacles and a spare 1-1/2” conduit for future data installation.

15. IF BID OPTION #1 IS NOT AWARDED – Replace the receptacles in the two existing floor boxes, repair as necessary for proper function, and install new flush covers.

16. Install all new lighting throughout the project area as noted on Sheet E1.0.

17. Furnish new receptacles, switches, and covers in all existing fixtures to remain throughout the project area.

18. All new distribution circuitry (homeruns) above the ceiling and all circuitry in or on walls should be installed in EMT. “MC” type cable may be installed to new fixtures and devices above the ceiling.

19. All features of the facility not set to be repaired or replaced must be protected or restored to original condition at project completion.

C. Contractor shall take care not to damage the facility any more than necessary to perform the work, and shall protect and restore the area throughout construction. The Contractor is responsible to repair any damage to bring the facility back to pre-construction conditions.

D. JOB SITE INSPECTION. The Contractor shall keep all work sites clear of trash and debris. The Government will inspect the work area around the work site at its discretion.

Any cleaning or trash problems not corrected by the Contractor in a timely manner will result in payment being withheld until the problem is corrected.

E. TOOLS. The Contractor shall supply all tools and equipment to provide services required in this SOW. The Contractor SHALL NOT, at any time, borrow or use any tools or equipment from Key Field shops or its employees (state, contract, or federal). This includes forklifts, motorized lifts, electric carts, hand tools, power tools, etc.

III. PERIOD OF PERFORMANCE: The project shall be accepted as substantially complete within 90 calendar days after issuance of the Notice to Proceed.

IV. ENVIRONMENTAL MANAGEMENT: Key Field ANGB is committed to AFPD 90-8 for all base personnel and operations to include construction and all contractors working on behalf of the Government. The primary tenets of AFPD 90-8 are: Environmental Compliance, Risk Management, and Continuous Improvement. As applicable, the Contractor is responsible for the following:

1. Provide copies of all Hazardous Material SDS’s (oil, paints, adhesives, refrigerant, etc) to the Contracting Officer for approval prior to use, and provide total usage of each item upon completion and prior to project closeout for required EPCRA 313 tracking. Additionally, any reclaimed or re-used refrigerant must be documented at project closeout by weight, type, and management method.

2. Provide secondary containment for all liquid Hazardous Materials in containers 55 gallons or larger.

3. Track and report amount of waste generated and method of disposal (recycled, reused, or landfilled). All waste must be managed or disposed in a legal manner.

Unless specifically noted, all waste belongs to the Contractor. Key Field ANGB’s existing solid waste program, to include green boxes and construction debris containers, SHALL NOT be used for Contractor’s waste unless explicitly authorized in writing.

4. Coordinate and secure MDEQ permits, as applicable, for emissions equipment and Storm Water Construction.

The afore-mentioned items highlight requirements for service and construction contracts but are not all inclusive. A more in-depth Environmental Contractor Packet is available upon request.

V. QUALITY ASSURANCE: The Government will provide visual inspections as needed to ensure that all work described in this SOW are complete.

VI. WORK SCHEDULE: All installation work associated with this contract shall be accomplished during daily work hours between 07:00 a.m. to 04:30 p.m. Monday through Friday except for Federal Holidays and compressed work days. The Government must approve any deviation from these hours.

VII. WARRANTY: The Contractor to finish all work in a professional manner, employing best construction practices, using all new materials as approved by the owner (unless otherwise noted). Labor, equipment and materials installed by the Contractor shall be guaranteed by the Contractor to be free from defect for a period of one year (unless noted otherwise by specification) from the date of final acceptance.

VIII. SAFETY AND FIRE PREVENTION: Contractor must comply with all appropriate Occupational Safety and Health Administration (OSHA) and National Fire Prevention Association (NFPA) regulations during construction. Contractor shall receive a burn permit from the Fire Department at Key Field ANG Base prior to any hot work, welding, or potential fire hazard operations. All personnel working in or around the facility shall be thoroughly briefed on any dangers in the area.

IX. BASE & FACILITY ACCESS: The Contractor shall coordinate with the 186th Security Forces Squadron and Contracting Officer to gain access to Key Field ANG Base and the operating area where work is to be performed. Contractor shall also coordinate with the BCE to avoid adverse impacts to Key Field flying mission or mission support functions. The Contractor will have access to any base infrastructure (power, water) presently available in or nearby the construction area.

Any modifications to base infrastructure to assist in construction must be requested in writing, approved by the Base Civil Engineer, and performed by the Contractor.

X. CONTRACTOR MANAGEMENT REPORTING (CMR): The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor shall report ALL Contractor manpower (including subcontractor manpower) required for performance of this contract. The Contractor shall completely fill in all the information in the format using the following web address www.sam.gov.

The required information includes: (1) Contracting Office, Contracting Officer, Contracting Officer's Technical Representative (COTR) or also known as the Contracting Officer's Representative (COR); (2) Contract number, including task and delivery order number; (3) Beginning and ending dates covered by reporting period; (4) Contractor's name, address, phone number, e-mail address, identity of Contractor employee entering data; (5) Estimated direct labor hours (including sub-Contractors); (6) Estimated direct labor dollars paid this reporting period (including sub-Contractors); (7) Total payments (including sub-Contractors); (8) Predominant Federal Service Code (FSC) reflecting services provided by Contractor (and separate predominant FSC for each sub-Contractor if different); (9) Estimated data collection cost; (10) Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring Activity is responsible for providing the Contractor with its UIC for the purposes of reporting this information); (11) Locations where Contractor and sub-Contractors perform the work (specified by zip code in the United States and nearest city, country, when in an overseas location, using standardized nomenclature provided on website); (12) Presence of deployment or contingency contract language; and (13) Number of Contractor and sub-Contractor employees deployed in theater this reporting period (by country). As part of its submission, the Contractor shall provide the estimated total cost (if any) incurred to comply with this reporting requirement.

Reporting period shall be the period of performance not to exceed 12 months ending September 30 of each government fiscal year and must be reported by 31 October of each calendar year.

Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor's system to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from

END OF STATEMENT OF WORK

MILLWORK TECHNICAL SPECIFICATIONS

SECTION 06 41 16 - PLASTIC-LAMINATE-FACED ARCHITECTURAL

CABINETS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Plastic-laminate-faced architectural cabinets.

2. Wood furring, blocking, shims, and hanging strips for installing plastic-laminate-faced architectural cabinets unless concealed within other construction before cabinet installation.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product including panel products, high-pressure decorative laminate, adhesive for bonding plastic laminate and cabinet hardware and accessories.

B. Shop Drawings: Show location of each item, dimensioned plans and elevations, large-scale details, attachment devices, and other components.

C. Samples:

1. Plastic laminates, for each color, pattern, and surface finish.

2. Thermoset decorative panels, for each color, pattern, and surface finish.

1.3 INFORMATIONAL SUBMITTALS

A. Woodwork Quality Standard Compliance Certificates: AWI Quality Certification

Program certificates.

1.4 QUALITY ASSURANCE

A. Fabricator Qualifications: Certified participant in AWI's Quality Certification Program.

B. Installer Qualifications: Certified participant in AWI's Quality Certification Program

PART 2 - PRODUCTS

2.1 PLASTIC-LAMINATE-FACED ARCHITECTURAL CABINETS

A. Quality Standard: Unless otherwise indicated, comply with the "Architectural

Woodwork Standards" for grades of architectural plastic-laminate cabinets indicated for construction, finishes, installation, and other requirements.

1. Provide labels and certificates from AWI and WI certification program indicating that woodwork, including installation, complies with requirements of grades specified.

B. Grade: Custom.

C. Regional Materials: Plastic-laminate cabinets shall be manufactured within 500 miles

(800 km) of Project site.

D. Type of Construction: Face frame or European flush frame.

E. Cabinet, Door, and Drawer Front Interface Style: Flush overlay.

F. Reveal Dimension: As indicated.

G. High-Pressure Decorative Laminate: NEMA LD 3, grades as indicated or if not indicated, as required by woodwork quality standard.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. Abet Laminati, Inc.

b. Formica Corporation.

c. Lamin-Art, Inc.

d. Panolam Industries International, Inc.

e. Wilsonart International; Div. of Premark International, Inc.

H. Laminate Cladding for Exposed Surfaces:

1. Horizontal Surfaces: Grade HGS.

2. Postformed Surfaces: Grade HGP.

3. Vertical Surfaces: Grade HGS.

4. Pattern Direction: Vertically for doors and fixed panels, horizontally for drawer fronts.

I. Materials for Semiexposed Surfaces:

1. Surfaces Other Than Drawer Bodies: High-pressure decorative laminate, NEMA LD 3, Grade VGS.

2. Drawer Sides and Backs: Solid-hardwood lumber.

3. Drawer Bottoms: Hardwood plywood.

J. Dust Panels: 1/4-inch (6.4-mm) plywood or tempered hardboard above compartments and drawers unless located directly under tops.

K. Colors, Patterns, and Finishes: Provide materials and products that result in colors and textures of exposed laminate surfaces complying with the following requirements:

1. As selected by Architect from laminate manufacturer's full range.

2.2 WOOD MATERIALS

A. Wood Products: Provide materials that comply with requirements of referenced quality standard for each type of woodwork and quality grade specified unless otherwise indicated.

1. Wood Moisture Content: 5 to 10 percent.

B. Composite Wood and Agrifiber Products: Provide materials that comply with requirements of referenced quality standard for each type of woodwork and quality grade specified unless otherwise indicated.

1. Softwood Plywood: DOC PS 1.

C. All cabinet panels shall be constructed of plywood except door panels may be constructed of MDF.

2.3 CABINET HARDWARE AND ACCESSORIES

A. General: Provide cabinet hardware and accessory materials associated with architectural cabinets except for items specified in Section 087111 "Door Hardware (Descriptive Specification)."

B. Butt Hinges: 2-3/4-inch (70-mm), five-knuckle steel hinges made from 0.095-inch- (2.4-mm-) thick metal, and as follows:

1. Semiconcealed Hinges for Overlay Doors: BHMA A156.9, B01521.

C. Wire Pulls: Back mounted, solid metal, 4 inches (100 mm) long, 5/16 inch (8 mm) in diameter.

D. Catches: Magnetic catches, BHMA A156.9, B03141.

E. Adjustable Shelf Standards and Supports: BHMA A156.9, B04071; with shelf rests, B04081.

F. Drawer Slides: BHMA A156.9.

1. Grade 1HD-100 and Grade 1HD-200: Side mounted; full-extension type; zinc-plated- steel ball-bearing slides.

G. Door and Drawer Silencers: BHMA A156.16, L03011.

H. Exposed Hardware Finishes: For exposed hardware, provide brushed nickel.

2.4 MISCELLANEOUS MATERIALS

A. Furring, Blocking, Shims, and Hanging Strips: Softwood or hardwood lumber kiln dried to less than 15 percent moisture content.

B. Anchors: Select material, type, size, and finish required for each substrate for secure anchorage. Provide metal expansion sleeves or expansion bolts for post-installed anchors.

Use nonferrous-metal or hot-dip galvanized anchors and inserts at inside face of exterior walls and at floors.

C. Adhesives: Do not use adhesives that contain urea formaldehyde.

D. Adhesives: Use adhesives that meet the testing and product requirements of the California

Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

E. Adhesive for Bonding Plastic Laminate: Unpigmented contact cement.

1. Adhesive for Bonding Edges: Hot-melt adhesive or adhesive specified above for faces.

2.5 FABRICATION

A. Complete fabrication, including assembly and hardware application, to maximum extent possible before shipment to Project site. Disassemble components only as necessary for shipment and installation. Where necessary for fitting at site, provide ample allowance for scribing, trimming, and fitting.

B. Shop-cut openings to maximum extent possible to receive hardware, appliances, electrical work, and similar items. Locate openings accurately and use templates or roughing-in diagrams to produce accurately sized and shaped openings. Sand edges of cutouts to remove splinters and burrs.

C. Install glass to comply with applicable requirements in Section 088000 "Glazing" and in GANA's

"Glazing Manual." For glass in wood frames, secure glass with removable stops.

PART 3 - EXECUTION

3.1 PREPARATION

A. Before installation, condition cabinets to average prevailing humidity conditions in installation areas.

3.2 INSTALLATION

A. Grade: Install cabinets to comply with same grade as item to be installed.

B. Install cabinets level, plumb, true, and straight. Shim as required with concealed shims. Install level and plumb to a tolerance of 1/8 inch in 96 inches (3 mm in 2400 mm).

C. Scribe and cut cabinets to fit adjoining work, refinish cut surfaces, and repair damaged finish at cuts.

D. Anchor cabinets to anchors or blocking built in or directly attached to substrates. Secure with countersunk, concealed fasteners and blind nailing. Use fine finishing nails for exposed fastening, countersunk and filled flush with woodwork.

E. Cabinets: Install without distortion so doors and drawers fit openings properly and are accurately aligned. Adjust hardware to center doors and drawers in openings and to provide unencumbered operation. Complete installation of hardware and accessory items as indicated.

1. Install cabinets with no more than 1/8 inch in 96-inch (3 mm in 2400-mm) sag, bow, or other variation from a straight line.

2. Fasten wall cabinets through back, near top and bottom, and at ends not more than

16 inches (400 mm) o.c. with No. 10 wafer-head screws sized for not less than 1-1/2-inch (38-mm) penetration into wood framing, blocking, or hanging strips.

END OF SECTION 06 41 16

SECTION 12 36 61 - SIMULATED STONE COUNTERTOPS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Solid-surface-material countertops and backsplashes.

1.2 ACTION SUBMITTALS

A. Product Data: For countertop and window stool materials and sinks.

B. Shop Drawings: For countertops. Show materials, finishes, edge and backsplash profiles, methods of joining, and cutouts for plumbing fixtures.

C. Samples: For each type of material exposed to view.

PART 2 - PRODUCTS

2.1 SOLID-SURFACE-MATERIAL COUNTERTOPS

A. Configuration: Provide countertops with the following front and backsplash style:

1. Front: Radius edge with apron, 2 inches (50 mm) high with 3/8-inch (9.5-mm) radius.

2. Backsplash: Radius edge with 3/8-inch (9.5-mm) radius.

3. Endsplash: Matching backsplash.

B. Countertops and window stools: 3/4-inch- thick, solid surface material with front edge built up with same material.

C. Backsplashes: 3/4-inch- thick, solid surface material.

2.2 COUNTERTOP MATERIALS

A. Plywood: Exterior softwood plywood complying with DOC PS 1, Grade C-C Plugged, touch sanded.

B. Solid Surface Material: Homogeneous solid sheets of filled plastic resin complying with

ANSI SS1.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. Avonite Surfaces.

b. E. I. du Pont de Nemours and Company.

c. Formica Corporation.

d. LG Chemical, Ltd.

e. Meganite Inc.

f. Samsung Chemical USA, Inc.

g. Swan Corporation (The).

h. Transolid, Inc.

i. Wilsonart International.

2. Type: Provide Standard Type unless Special Purpose Type is indicated.

3. Colors and Patterns: As selected by Architect from manufacturer's full range.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Fasten countertops by screwing through corner blocks of base units into underside of countertop.

Align adjacent surfaces and, using adhesive in color to match countertop, form seams to comply with manufacturer's written instructions. Carefully dress joints smooth, remove surface scratches, and clean entire surface.

END OF SECTION 12 36 61