STATEMENT OF WORK

Project No. MDVL212104

Key Field Air National Guard Base, Meridian, Mississippi

RENOVATE SQUADRON OPERATIONS BREAKROOM BLDG 308

3 DECEMBER 2021

I. PURPOSE: This Statement of Work provides the requirements necessary to renovate the break room in Bldg 308.

A. APPLICABLE REFERENCE DOCUMENTS:

1. Technical Specifications

2. Construction Plan Set

3. As-Built Facility Construction Plans (available upon request)

II. REQUIREMENTS: The Contractor shall provide all, labor, supervision, parts, materials, equipment, tools, freight, rigging, temporary toilet facilities (if required) and transportation required at Key Field Air National Guard Base, as requested and described below.

A. DEMOLITION:

1. Generally, refer to D-1 of the Construction Plan Set for demolition requirements. This project affects existing room numbers 109, 109A, and 109B. Work may also be required, but is not anticipated, in other areas for electrical and mechanical improvements.

2. Demolish and dispose of all existing ceramic tile flooring, lay-in acoustical tile ceiling systems, and lighting in Rooms 109 and 109A. Contractor is responsible for safely relocating mass notification (MNS), fire alarm, and speaker devices in the ceiling.

Government (Base Communications) will assist in disconnecting and reinstalling

MNS.

3. Demolish existing ceramic tile flooring in Room 109B.

4. Demolish all existing HVAC grills and diffusers within the project area. Modify duct as required for improvements as shown on Sheet M-1.

5. Demolish existing walls as shown on Sheet D-1.

6. Remove and/or modify existing infrastructure to include water supply and drains, receptacles, and data as shown on Sheets D-1, E-1, and M-1.

7. Saw-cut and demolish existing floor slab as shown on Sheets D-1 and M-1 for installation of new drain for icemaker in accordance with manufacturer’s recommendation (Gov to provide icemaker data upon contract award).

8. Disconnect and remove all power and wiring along with conduit not planned for reuse back to the nearest junction box.

9. Demolish, remove, and/or modify existing features as required for construction as noted in the plan set.

10. All features of the facility not set to be demolished must be protected or restored to original condition at project completion.

B. IMPROVEMENTS:

1. Provide finishes as shown on Sheet A-1 and A-2 to include: replace/install flooring, install new wall finishes, paint door frames and walls, install cabinetry and countertops, and replace ceiling system. Refer to the finish schedule on Sheet A-1for limits of finish improvements and for room-specific information.

2. Provide finishes for existing walls throughout the construction area as shown on Sheet A-1. All walls to be finished as shown in the details on Sheet A-1 to include gypsum, wainscoting, and/or brick veneer. Gypsum shall be ½” thickness fire-rated, moisture resistant. Government may select accent colors for wainscoting.

3. Provide and install thin brick veneer wall covering as shown on Sheets A-1 and A-2. Thin brick shall be ½” nominal thickness and shall include corner pieces where necessary. Basis of design is OldMill Thin Brick Systems (or approved equal). Physical samples will be required and the manufacturer’s full color line shall be available for selection. Type S mortar will be selected from the manufacturer’s standard color options.

4. Provide and install new door (1) in existing frame as noted on Sheet A-1. Door slab shall be clear finish, flush solid wood with birch veneer and full lite. Existing lockset shall be re-installed on the new door. Door (2) shall be painted. Color to be selected by Gov. Door (3) shall remain but all glazing shall be replaced. Door glazing for doors (1) and (3) shall both be frosted tempered glass units.

5. Paint all interior door frames throughout the project area (quantity 2) with enamel, color TBD by Government.

6. Install new ceiling grid and ceiling tile (Armstrong Calla or approved equal, all color options to be available to Gov) in 2’x2’ pattern in identified areas throughout project area. Note: as much as possible, all features within the ceiling (e.g. new lights, HVAC grilles, etc. shall match the selected color of the ceiling system).

7. Provide and install glue-down luxury vinyl plank flooring with micro bevel edges in Rooms 109 and 109B (approximately 662 square foot). Flooring shall be 6” wide, minimum 0.10” overall thickness and 20 mil wear layer, 10-year commercial warranty (Mannington Nature’s Path, or approved equal). Provide transitional thresholds as necessary at the project limits.

8. Provide and install custom painted wood cabinets as shown on Sheets A-1 and A- 2 and in accordance with the specifications herein.

9. Provide and install new solid-surface counters as shown on Sheets A-1 and A-2 and in accordance with the specifications herein.

10. Provide new duplex receptacles, data infrastructure, and lighting controls as shown on Sheet E-1.

11. Install all new lighting throughout the project area as noted on Sheet E-1. Lay-in 2’x4’ fixtures are existing and to be re-used. Proposed circuitry and location is similar to existing conditions. New recessed and under cabinet lighting shall be as shown on Sheet E-1. Government shall be provided manufacturer’s standard color options for recessed and under-cabinet lighting trim.

12. Furnish new receptacles, switches, and covers in all existing fixtures to remain throughout the project area.

13. All new distribution circuitry (homeruns) above the ceiling and all circuitry in or on walls should be installed in EMT. “MC” type cable may be installed to new fixtures and devices above the ceiling.

14. Replace all existing HVAC supply and return diffusers/grilles. Existing supply strip diffusers shall be replaced with standard 2’x2’ grilles and will require minor duct modifications to accommodate. All new grilles for supply and return shall match the selected ceiling system color.

15. Install all new plumbing infrastructure and fixtures as shown on Sheet M-1 (or approved equals).

16. All features of the facility not set to be repaired or replaced must be protected or restored to original condition at project completion.

C. Contractor shall take care not to damage the facility any more than necessary to perform the work, and shall protect and restore the area throughout construction. The Contractor is responsible to repair any damage to bring the facility back to pre-construction conditions.

D. JOB SITE INSPECTION. The Contractor shall keep all work sites clear of trash and debris. The Government will inspect the work area around the work site at its discretion.

Any cleaning or trash problems not corrected by the Contractor in a timely manner will result in payment being withheld until the problem is corrected.

E. TOOLS. The Contractor shall supply all tools and equipment to provide services required in this SOW. The Contractor SHALL NOT, at any time, borrow or use any tools or equipment from Key Field shops or its employees (state, contract, or federal). This includes forklifts, motorized lifts, electric carts, hand tools, power tools, etc.

III. PERIOD OF PERFORMANCE: The project shall be accepted as substantially complete within 120 calendar days after issuance of the Notice to Proceed.

IV. ENVIRONMENTAL MANAGEMENT: Key Field ANGB is committed to AFPD 90-8 for all base personnel and operations to include construction and all contractors working on behalf of the Government. The primary tenets of AFPD 90-8 are: Environmental Compliance, Risk Management, and Continuous Improvement. As applicable, the Contractor is responsible for the following:

1. Provide copies of all Hazardous Material SDS’s (oil, paints, adhesives, refrigerant, etc) to the Contracting Officer for approval prior to use, and provide total usage of each item upon completion and prior to project closeout for required EPCRA 313 tracking. Additionally, any reclaimed or re-used refrigerant must be documented at project closeout by weight, type, and management method.

2. Provide secondary containment for all liquid Hazardous Materials in containers 55 gallons or larger.

3. Track and report amount of waste generated and method of disposal (recycled, reused, or landfilled). All waste must be managed or disposed in a legal manner.

Unless specifically noted, all waste belongs to the Contractor. Key Field ANGB’s existing solid waste program, to include green boxes and construction debris containers, SHALL NOT be used for Contractor’s waste unless explicitly authorized in writing.

4. Coordinate and secure MDEQ permits, as applicable, for emissions equipment and Storm Water Construction.

The afore-mentioned items highlight requirements for service and construction contracts but are not all inclusive. A more in-depth Environmental Contractor Packet is available upon request.

V. QUALITY ASSURANCE: The Government will provide visual inspections as needed to ensure that all work described in this SOW are complete.

VI. WORK SCHEDULE: All installation work associated with this contract shall be accomplished during daily work hours between 07:00 a.m. to 04:30 p.m. Monday through Friday except for Federal Holidays and compressed work days. The Government must approve any deviation from these hours.

VII. WARRANTY: The Contractor to finish all work in a professional manner, employing best construction practices, using all new materials as approved by the owner (unless otherwise noted). Labor, equipment and materials installed by the Contractor shall be guaranteed by the Contractor to be free from defect for a period of one year (unless noted otherwise by specification) from the date of final acceptance.

VIII. SAFETY AND FIRE PREVENTION: Contractor must comply with all appropriate Occupational Safety and Health Administration (OSHA) and National Fire Prevention Association (NFPA) regulations during construction. Contractor shall receive a burn permit from the Fire Department at Key Field ANG Base prior to any hot work, welding, or potential fire hazard operations. All personnel working in or around the facility shall be thoroughly briefed on any dangers in the area.

IX. BASE & FACILITY ACCESS: The Contractor shall coordinate with the 186th Security Forces Squadron and Contracting Officer to gain access to Key Field ANG Base and the operating area where work is to be performed. Contractor shall also coordinate with the BCE to avoid adverse impacts to Key Field flying mission or mission support functions. The Contractor will have access to any base infrastructure (power, water) presently available in or nearby the construction area.

Any modifications to base infrastructure to assist in construction must be requested in writing, approved by the Base Civil Engineer, and performed by the Contractor.

END OF STATEMENT OF WORK

ATTACHMENT 1 – TECHNICAL SPECIFICATIONS

SECTION 12 32 00 – MANUFACTURED WOOD CASEWORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Face frame architectural cabinets.

2. Wood furring, blocking, shims, and hanging strips for installing face frame architectural cabinets unless concealed within other construction before cabinet installation.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product including panel products, paint, adhesives, and cabinet hardware and accessories.

B. Shop Drawings: Show location of each item, dimensioned plans and elevations, large-scale details, attachment devices, and other components.

C. Samples:

1. Painted cabinet door samples for up to 3 colors, patterns, and finish.

2. Solid-surface countertop, manufacturer’s color samples.

3. Thin brick veneer, manufacturer’s color samples.

4. As requested.

1.3 INFORMATIONAL SUBMITTALS

A. Woodwork Quality Standard Compliance Certificates: AWI Quality Certification Program certificates.

1.4 QUALITY ASSURANCE

A. Fabricator Qualifications: Certified participant in AWI's Quality Certification Program.

B. Installer Qualifications: Certified participant in AWI's Quality Certification Program

PART 2 - PRODUCTS

2.1 RAISED PANEL FACE-FRAME ARCHITECTURAL CABINETS

A. Quality Standard: Unless otherwise indicated, comply with the "Architectural

Woodwork Standards" for grades of architectural cabinets indicated for construction, finishes, installation, and other requirements.

1. Provide labels and certificates from AWI and WI certification program indicating that woodwork, including installation, complies with requirements of grades specified.

B. Grade: Custom.

C. Regional Materials: Cabinets shall be manufactured within 500 miles (800 km) of

Project site.

D. Type of Construction: Face frame.

E. Cabinet, Door, and Drawer Front Interface Style: Raised panel.

F. Reveal Dimension: As indicated.

G. Cabinet Construction: Construct wall and base cabinets with frame fronts and solid ends, or frame construction throughout. Provide 3/4 by 1-1/2 inch kiln-dried hardwood framing members, using mortise and tenon, dovetailed, grove and lapped, biscuit and dado, or doweled, with glue assembly. Brace top and bottom corners with hardwood blocks that are glued with water-resistant glue and nailed in place. Provide base cabinets with an integral toe space at least 2-1/2 inches deep and 4 inches high. Mount drawers on metal guides. Provide removable and adjustable shelving throughout.

Provide minimum thicknesses of materials for frame-front, solid-end cabinet construction as follows:

a. Backs and bottoms of base cabinets and tops of wall cabinets: 1/8 inch tempered hardboard. Brace bottoms with wood members glued in place.

b. Cabinet ends: 1/2 inch hardwood plywood

c. Doors: 3/4 inch moisture proof MDF.

d. Drawer fronts: 3/4 inch moisture proof MDF.

e. Drawer bottoms: 1/4 inch plywood or tempered hardboard. Brace drawer bottoms over 15 inches wide with wood members glued in place.

f. Drawer sides and backs: 1/2 inch hardwood plywood

g. Interior partitions or dividers: 1/2 inch hardwood plywood

h. Shelves: 1/2 inch Grade A-B plywood, supported on ends and 24 inches on centers

i. Adjustable shelves: 3/4 inch plywood

H. Dust Panels: 1/4-inch (6.4-mm) plywood or tempered hardboard above compartments and drawers unless located directly under tops.

I. Colors, Patterns, and Finishes: Provide materials and products that result in colors and textures of exposed surfaces complying with the following requirements:

1. As selected by Government from manufacturer's full range of paint colors. Apply a prime coat and two coats of synthetic enamel of air-drying quality conforming to MPI standards. Apply finish in a controlled environment prior to delivery.

2.2 WOOD MATERIALS

A. Wood Products: Provide materials that comply with requirements of referenced quality standard for each type of woodwork and quality grade specified unless otherwise indicated.

1. Wood Moisture Content: 5 to 10 percent.

B. Composite Wood and Agrifiber Products: Provide materials that comply with requirements of referenced quality standard for each type of woodwork and quality grade specified unless otherwise indicated.

C. All cabinet panels shall be constructed of plywood except door panels may be constructed of MDF (CPA A208.1 and CPA A208.2).

2.3 CABINET HARDWARE AND ACCESSORIES

A. General: Provide cabinet hardware and accessory materials associated with architectural cabinets except for items specified in Section 087111 "Door Hardware (Descriptive Specification)."

B. Butt Hinges: 2-3/4-inch (70-mm), five-knuckle so f t - c lose steel hinges made from 0.095-inch- (2.4-mm-) thick metal, and as follows:

1. Semiconcealed Hinges for Overlay Doors: BHMA A156.9, B01521.

C. Wire Pulls: Back mounted, solid metal, 4 inches (100 mm) long, 5/16 inch (8 mm) in diameter.

D. Catches: Magnetic catches, BHMA A156.9, B03141.

E. Adjustable Shelf Standards and Supports: BHMA A156.9, B04071; with shelf rests, B04081.

F. Drawer Slides: BHMA A156.9.

1. Grade 1HD-100 and Grade 1HD-200: Side mounted; full-extension type;

zinc-plated- steel ball-bearing slides.

G. Door and Drawer Silencers: BHMA A156.16, L03011.

H. Exposed Hardware Finishes: For exposed hardware, provide full range of manufacturer’s options.

2.4 MISCELLANEOUS MATERIALS

A. Furring, Blocking, Shims, and Hanging Strips: Softwood or hardwood lumber kiln dried to less than 15 percent moisture content.

B. Anchors: Select material, type, size, and finish required for each substrate for secure anchorage. Provide metal expansion sleeves or expansion bolts for post-installed anchors. Use nonferrous-metal or hot-dip galvanized anchors and inserts at inside face of exterior walls and at floors.

C. Adhesives: Do not use adhesives that contain urea formaldehyde.

D. Adhesives: Use adhesives that meet the testing and product requirements of the

California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

2.5 FABRICATION

A. Complete fabrication, including assembly and hardware application, to maximum extent possible before shipment to Project site. Disassemble components only as necessary for shipment and installation. Where necessary for fitting at site, provide ample allowance for scribing, trimming, and fitting.

B. Shop-cut openings to maximum extent possible to receive hardware, appliances, electrical work, and similar items. Locate openings accurately and use templates or roughing-in diagrams to produce accurately sized and shaped openings. Sand edges of cutouts to remove splinters and burrs.

C. Install glass to comply with applicable requirements in Section 088000 "Glazing" and in GANA's "Glazing Manual." For glass in wood frames, secure glass with removable stops.

PART 3 - EXECUTION

3.1 PREPARATION

A. Before installation, condition cabinets to average prevailing humidity conditions in installation areas.

3.2 INSTALLATION

A. Grade: Install cabinets to comply with same grade as item to be installed.

B. Install cabinets level, plumb, true, and straight. Shim as required with concealed shims.

Install level and plumb to a tolerance of 1/8 inch in 96 inches (3 mm in 2400 mm).

C. Scribe and cut cabinets to fit adjoining work, refinish cut surfaces, and repair damaged finish at cuts.

D. Anchor cabinets to anchors or blocking built in or directly attached to substrates.

Secure with countersunk, concealed fasteners and blind nailing. Use fine finishing nails for exposed fastening, countersunk and filled flush with woodwork.

E. Cabinets: Install without distortion so doors and drawers fit openings properly and are accurately aligned. Adjust hardware to center doors and drawers in openings and to provide unencumbered operation. Complete installation of hardware and accessory items as indicated.

1. Install cabinets with no more than 1/8 inch in 96-inch (3 mm in 2400-mm) sag, bow, or other variation from a straight line.

2. Fasten wall cabinets through back, near top and bottom, and at ends not more than 16 inches (400 mm) o.c. with No. 10 wafer-head screws sized for not less than 1-1/2-inch (38-mm) penetration into wood framing, blocking, or hanging strips.

END OF SECTION 12 32 00

SECTION 12 36 61 - SIMULATED STONE COUNTERTOPS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Solid-surface-material countertops and backsplashes.

1.2 ACTION SUBMITTALS

A. Product Data: For countertop and window stool materials and sinks.

B. Shop Drawings: For countertops. Show materials, finishes, edge and backsplash profiles, methods of joining, and cutouts for plumbing fixtures.

C. Samples: For each type of material exposed to view.

PART 2 - PRODUCTS

2.1 SOLID-SURFACE-MATERIAL COUNTERTOPS

A. Configuration: Provide countertops with the following front and backsplash style:

1. Front: Radius edge with apron, 2 inches (50 mm) high with 3/8-inch (9.5-mm) radius.

2. Backsplash: Radius edge with 3/8-inch (9.5-mm) radius.

3. Endsplash: Matching backsplash.

B. Countertops and window stools: 3/4-inch- thick, solid surface material with front edge built up with same material.

C. Backsplashes: 3/4-inch- thick, solid surface material.

2.2 COUNTERTOP MATERIALS

A. Plywood: Exterior softwood plywood complying with DOC PS 1, Grade C-C Plugged, touch sanded.

B. Solid Surface Material: Homogeneous solid sheets of quartz complying with ANSI SS1.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. Silestone

b. Cambria

c. Caesarstone

d. LG Viatera

e. Corian

2. Type: Provide Standard Type unless Special Purpose Type is indicated.

3. Colors and Patterns: As selected by Government from manufacturer's full range.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Fasten countertops by screwing through corner blocks of base units into underside of countertop. Align adjacent surfaces and, using adhesive in color to match countertop, form seams to comply with manufacturer's written instructions. Carefully dress joints smooth, remove surface scratches, and clean entire surface.

END OF SECTION 12 36 61