MCWS-X Questions and Answers Round 2.xlsx
XLSX spreadsheet 12 KB Posted
- Solicitation number
- M67854-20-R-2025_Amendment_0002
- Issued by
-
United States Marine Corps
About this file
This document contains responses to questions from offerors on a solicitation for the Marine Corps Wideband Satellite Communications - Expeditionary (MCWS-X) program. The government response provides additional details on anticipated purchase quantities in the first two years of the contract, which are expected to be around 100 systems in Year 1 and 80 systems in Year 2. It also notes that video files will not be accepted as evidence for certain performance specifications and that a vendor, government, or test agency test report may be used instead. A one week extension was granted to the proposal due date, which was extended from June 5, 2020 to June 12, 2020 as indicated in Amendment 0002 to the solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| M67854-20-R-2025-0002.docx | DOCX document | |
| Attachment 3 Delivery Schedule 27 May 2020.DOCX | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet2
| Question Number | Document/Section | Paragraph Number | Question/Issue/Concern | Government Response |
| 1 | M67854-20-R-2025-0001.doc/page 7 of 16, Section L 2.2 Organization of Proposal, table 2 Proposal Organization, Volume III Technical Approach, section 3.2 Delivery Schedule | Table 2, section 3.2 Delivery Schedule | The Section L proposal outline in Table 2 specifies only “Attachment 3” for the response on Delivery Schedule. Is any evidence of our support for this schedule allowed in Section 3.2? If so, what page limit should the offeror assume? | Sections L and M have been updated in Amendment 2 for evidence to support delivery schedule. Attachment 3 has also been updated to provide space for the Offeror's proposed delivery schedule. |
| 2 | M67854-20-R-2025-0001.doc/page 9 of 16, Section L 2.2.3 | L-2.3.3 Volume III: Technical Approach, Delivery Schedule | How many MCWE-X terminals does the USMC anticipate purchasing in Year 1 and in Year 2? | The Government expects to purchase roughly 100 systems in Year 1 and 80 systems in Year 2. However, this is just the current plan and does not bind the Government to these quantities. The maximum per year is set by the contract. |
| 3 | MCWX-E Questions and Answers | Question 8 | The government responded that video files will not be accepted as evidence of Performance Specifications. How should an offeror provide evidence for Threshold P-Specs 3.9.6 & 3.11.2 and Objective P-Specs 3.9.7 & 3.11.3 | A vendor, government, or test agency test report may be used as evidence. |
| 4 | General | Given the responses to the questions, would the Government grant a 2 week extension to proposal due date? | A one week extension has been granted in Amendment 2. The new due date for all proposals is 12 June, 2020. | |
| 5 | General | We would like request a one (1) week extension to due date of 5 June, 2020 to 12 June, 2020. We are aware that this was addressed in the response to questions posted with Amendment 0001. The additional time will help in providing a more complete proposal. | A one week extension has been granted in Amendment 2. The new due date for all proposals is 12 June, 2020. |
File details come from the government source that posted it. Updated .