Amendment 0001 - Responses to Questions
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| MCC-17-RFQ-0074_-_Attachment_J.3.docx | DOCX document | |
| MCC-17-RFQ-0074_-_(JN).pdf | ||
| MCC-17-RFQ-0074_-_Template_Worksheet_for_Page_5.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
BY
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 3
SEE BLOCK 16C
Millennium Challenge Corporation Contracts and Grants Management Division 1099 Fourteenth Street, NW Suite 700 Washington, DC 20005-3553
Millennium Challenge Corporation Contracts and Grants Management Division 1099 Fourteenth Street, NW Suite 700 Washington, DC 20005-3553 Ray Staniewski, Contract Specialist (KTR) (202)521-3656
To all Offerors/Bidders
MCC-17-RFQ-0074
07-07-2017
X
X X
The purpose of this amendment is to provide MCC’s answers to questions received from interested parties.
See “Continuation Page” at top of page two for all details.
JACQUELINE H. NARANJO
Contracting Officer naranjoj Typewritten Text 7/18/2017
CONTINUATION PAGE
MCC-17-RFQ-0074 0001 (Q & A) Page 2 of 3
Block 14. DESCRIPTION OF AMENDMENT/MODIFICATION (Continued)
The following questions were received. MCC’s response to each question is shown in red text:
1. If the contractor and key personnel are based in Mongolia, how does MCC envision the various interactions between MCC and key personnel taking place?
a. Would video conferences be acceptable?
Yes, MCC typically uses Skype for Business for its videoconferencing.
b. Should the contractor budget for trips from Ulaanbaatar to Washington DC for in-person consultations at MCC offices?
MCC believes this work can mostly be completed through video conferences, and no in-person trips are required. However, one in-person briefing at MCC may be necessary to complete the tasks. If the contractor thinks more or fewer trips are needed, they should budget for them accordingly within their cost quotation.
c. Or would MCC staff travel from Washington DC to Mongolia?
MCC staff may be able to travel to Mongolia for consultations, depending on budget availability.
2. On page 11, section F.1. states that the period of performance is 12 months. However, in section F.3.3, the deliverable time frame is 16 weeks. Would MCC please clarify this discrepancy?
• Timeliness is very important in order for this work to be useful. It is important the dates in the deliverables table be met (i.e. the work must be completed within 16 weeks). The length of the period of performance (12 months) accounts for MCC’s formal process for reviewing and accepting all deliverables, which may add some additional time to the performance period. However, MCC acknowledges that the existing “buffer period” is quite prolonged and hereby revises the performance period to a total of six (6) months from the date of award.
3. On page 27, in section H.16.6, the RFQ states “to be completed by offeror.” Does this mean the offeror should propose a 3rd key personnel position to be determined by the offeror?
• Only if the Offeror determines such a position is necessary to complete the work. The “to be completed by offeror” statement refers to the names of the key personnel candidates (hence the blank lines next to each labor category).
4. On page 27, in section H.17.1, the RFQ states that “contractors are encouraged to partner with local NGOs or research organizations as appropriate to meet this requirement.” Besides including a Researcher-Local Mongolian Expert from a local NGO as non-key personnel, how does MCC envision a partnership forming for this contract?
• That is an example of the type of partnership MCC envisioned; offerors are free to propose other partnership arrangements as needed to suit their proposed approach.
5. On page 66, in section L.9.8, the RFQ states “description of the evaluation team”. Would MCC please clarify what the evaluation team refers to?
• The statement should read “description of the proposed team” and not “evaluation team.”
6. On page 67, in section L.9.9 for past performance, is there a limitation in terms of how recent a past project was completed (i.e. past projects completed within the last 10 or 5 years?)
CONTINUATION PAGE
MCC-17-RFQ-0074 0001 (Q & A) Page 3 of 3
• Past projects must have been completed within the last 3 years in order to be considered recent.
7. On page 68, in section L.9.10, the RFQ states that past performance questionnaires are not required for MCC projects. Are past performance questionnaires required for Millennium Challenge Account (MCA) projects?
• Yes.
8. On page 74, the Gantt Chart template is for 5 years. Given that the period of performance is for 12 months, and the deliverable time frame is 16 weeks, would MCC please clarify how long the Gantt Chart for the work plan should be?
• The Gantt Chart on page 74 should be for the performance period beginning on the date of contract award through receipt of the final deliverables (i.e., 16 weeks).
9. In Section F.1. Period of Performance it states that the period of performance would be for 12 months from the date of award; however, in Section F.3.3. Deliverables the final report and presentation are due 16 weeks after contract award. Can MCC kindly clarify the anticipated period of the award and when the final deliverables are due?
• See response to Question 2 above.
10. Section F.1. of the RFQ states that “there are no option periods for this contract.” However, section L.10.1 makes reference to option periods. Can MCC kindly confirm if there will be option periods in addition to the base period of performance?
• Section L.10.1 makes a general statement. The part of the section in parenthesis is simply explaining what each “contract period” could be; it does not imply that there are option periods for this requirement. The requirement is for a 6-month base period with no options.
11. Will a six day work week be authorized for consultants providing short-term technical assistance?
• Yes. However, overtime is not authorized on this contract. Additional hours/days must be billed at the agreed-upon labor rate.
12. Will the staffing plan count against the 20 page limit for the technical submission or can it be submitted as an annex?
• Yes. The staffing plan is considered part of the “Technical Quotation.”