5. PROJECT NO. (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NO.

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NO. 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR AC-

KNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 10-83)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

BY

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(No., street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 3

0001 See Block 16C.

Millennium Challenge Corporation

Contracts and Grants Management Division

1099 Fourteenth Street NW

Suite 700

Washington DC 20005

Millennium Challenge Corporation

Contracts and Grants Management Division

1099 Fourteenth Street NW

Suite 700

Washington DC 20005

To all Offerors/Bidders

MCC-17-RFQ-0017

01/09/2017

X

X X

This solicitation is hereby extend to 27 January 2017 2 PM

X

This Amendment amends RFQ MCC-17-RFQ-0017 as follows:

The Proposal Submittal Date is hereby extended until 27 January 2017; 2 pm EST. All references in the RFQ to the submittal day and time shall reflect this change.

The continuation page reflects amendments; clarifications; and Questions and Answers to the RFQ as noted.

Please see continuation pages…

Taylor J. Wolf

Contracting Officer

MCC-17-RFQ-0017 Amendment 0001 Africa’s Promise Internship Coordination Project 2

CONTINUATION PAGE………

QUESTIONS AND ANSWERS TO REQUEST FOR QUOTE (RFQ) MCC-17-RFQ-0017

AFRICA’S PROMISE INTERNSHIP PROJECT

Format Questions: Please disregard any and all inferences to 4 hard copies and redacted copies. Only 1 electronic copy is required. Also, any of the word files shall be compatible with Word 2010 and the pricing section shall be in Excel format that is compatible with the latest Excel application.

Clarification: Under F.3 Deliverables please note:

The list of tasks are documentation/instructions that will be developed by the vendor which will allow each MCA to set up and successfully maintain an internship program. The contractor is not responsible for executing and maintaining the internship program.

1. Question: What is the expected time frame of the internship?

Answer: Per the RFQ “The initial goal of this procurement is to develop a general program that each MCA easily apply,” Thus this RFQ does not request the bidder to propose or be involved in maintaining or overseeing the internship program once the program is developed.

2. Question: Will the selected contractor have direct contact with each of the MCAs?

Answer: Along with the COR and Technical POC, the contractor shall be briefed and brainstorm with the MCAs on how best to successfully complete the tasking per RFQ C.1 Scope of Services.

3. Will the MCAs have input on the design on their internship program?

Answer: The final product will be used across multiple MCA’s. MCC will select one to two MCA’s to participate in the development.

4. Will the selected contractor be required to travel to any of the MCAs?

Answer: The following shall replace the current verbiage at:

F.2 PLACE OF PERFORMANCE

“The work will be performed remotely, with regular engagement with MCC staff. The work may require travel to one or two MCAs. All travel must have prior coordination and approval from the COR.”

5. On your website, it states that Interns will support the implementation of MCC projects in areas like clean water, electricity, land rights and education. Are there other project areas not listed on your site that the Interns would help further?

Answer: These are illustrative areas, not comprehensive. That will depend on the scope of the Compact and the venues where the Interns would be most advantageous.

6. What are the anticipated topics of training for the interns?

Answer: The anticipated topics of training for the interns is not required information in order to successfully achieve this endeavor.

MCC-17-RFQ-0017 Amendment 0001 Africa’s Promise Internship Coordination Project 3

7. Do the training and other materials need to be provided in languages other than English?

Answer: Ability to translate documents into French is highly desired, but not required.

8. Should travel to MCC Headquarters be included in the price portion of the proposal?

Answer: No. Meeting with MCC can be conducted via email, phone, Skype, WebEx or other means. The vendor is not required to travel to MCC HQ.

9. Approximately how many interns will need to be trained?

Answer: Since the contractor shall not be training the interns that information is not included in the RFQ.

10. What is the approximate length of the internships? Are they paid or unpaid internships?

Answer: This is not part of the Tasking for this RFQ, thus not required for proposing. Each local MCA will determine the appropriate length of their locally-administered internship program.

11. Will any portion of the contractor’s deliverables be required to be performed on-site in the foreign countries?

Answer: Travel to an MCA maybe required to gather specifics related to Human Resource practices, and program types. However the goal would be to select one of two MCA’s to gather information. The final product shall be used across multiple MCA’s.