This is an Advertisement for Bids issued by Marysville Public Schools for a partial roof replacement project at Marysville Washington Elementary School located at 905 16th Street, Marysville, Michigan. The project involves the complete removal of designated sections of existing built-up roof (BUR) covering approximately 36,110 square feet and replacement with new fully adhered EPDM roof membrane over polyisocyanurate insulation. A mandatory pre-bid meeting is scheduled for Tuesday, March 10, 2026 at 4:00 PM at Marysville Middle School. Bid documents, including plans and specifications, will be available for download on or about Thursday, March 5, 2026 from the Marysville Public Schools website. Sealed bids are due by Thursday, March 19, 2026 at 12:00 PM at the Marysville Public Schools Administrative Offices (495 East Huron Boulevard, Marysville, Michigan 48040), where they will be publicly opened and read aloud immediately thereafter.

Each proposal must be accompanied by a bid bond in the amount of 5% of the base bid amount, executed by an acceptable Surety Company, or a cashier's check payable to Marysville Public Schools. The successful bidder will be required to furnish and pay for satisfactory Performance and Payment Bonds. The Owner reserves the right to accept or reject any or all bids, waive any informalities, and award the contract to other than the low bidder at its discretion. The project is managed by NTH Consultants, Ltd., with contact information provided through Mike Neal at 734-391-5511, and is overseen by Mrs. Jennifer McKay, Director of Finance for Marysville Public Schools, at (810) 455-6012.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADVERTISEMENT FOR BIDS

PROJECT: MARYSVILLE PUBLIC SCHOOLS

Partial Roof Replacement Marysville Washington Elementary School

905 16th St, Marysville, Michigan 48040

DESCRIPTION: Complete removal of designated sections of existing BUR roofs ( approximately 36,110 square feet) and replacement with new fully adhered EPDM roof membrane over polyisocyanurate insulation.

OWNER: Marysville Public Schools 495 East Huron Boulevard Marysville, Michigan 48040

CONSULTANT: NTH Consultants, Ltd.

41780 Six Mile Rd.

Northville, Michigan 48168

Contact: Mike Neal 734-391-5511

BID DUE DATE: Thursday March 19, 2026 at 12:00 PM at the Marysville Public

Schools Administrative Offices (see address above). All bids will be publicly opened and read aloud immediately thereafter. Bids will not be accepted or considered after 12:00 PM on the bid due date.

DOCUMENTS: Bid documents, including plans and specifications, will be available to download on or about Thursday March 5, 2026 from the Marysville Public Schools website:

http://www.marysville.k12.mi.us

BID BOND: A bid bond in the amount of 5% of the base bid amount, executed by an acceptable Surety Company, or a cashier’s check, payable to Marysville Public Schools shall be submitted with each proposal. The successful bidder will be required to furnish and pay for satisfactory Performance and Payment Bonds.

PRE-BID MEETING: A “mandatory” pre-bid meeting will be held on Tuesday March 10, 2026 at 4:00 PM at Marysville Middle School.

RIGHTS OF OWNER: The Owner reserves the right to accept or reject any or all bids, in whole or in part, waive any informalities, accept any bid when, in the opinion of the Owner such action will serve in the best interest of Marysville Public Schools consistent with competitive bidding requirements, and award the Contract to other than the low bidder.

SIGNED: Owner’s Representative:

Mrs. Jennifer McKay Director of Finance Marysville Public Schools 495 E. Huron Blvd.

Marysville, Michigan 48040

(810) 455-6012

File details come from the government source that posted it. Updated .