Market Research Intelligence Questionnaire FTW511 FTW515.pdf
PDF 324 KB Posted
- Solicitation number
- W911KB27RWP03
About this file
This is a Comprehensive Market Research Questionnaire and Sources Sought/Request for Information (RFI) issued by the U.S. Army Corps of Engineers Alaska District to gather industry feedback on optimal project delivery methods and contracting vehicles for two significant military construction (MILCON) projects at Fort Wainwright, Alaska.
The questionnaire addresses two projects: FTW511 (Soldier Performance Readiness Center—$76M, 48,633 sq ft training facility, FY27-FY30) and FTW515 (Unaccompanied Enlisted Housing Barracks—$201M, 133,506 sq ft housing for 256 soldiers, FY27-FY30), with a combined estimated value of approximately $277M. Both projects require Arctic adaptation of Army Standard Designs and involve design phases starting in FY27 and construction starting no earlier than FY28. The Government seeks responses by October 7, 2026, at 14:00 Alaska Time, directed to Mark Corn, Kim Tripp, Katherine Green, and Theresa Afrank. The questionnaire evaluates three delivery methods: Accelerated Design-Build to Budget (DBtB) using FAR-based procurement with fixed-price competition; Construction Manager at Risk (CM@Risk) via OTA allowing design phase collaboration; and Progressive Design-Build (PDB) via OTA for complex/undefined scope requiring single-contract GMP negotiation. Industry respondents provide company information, bidding intent, bonding capacity, and detailed technical feedback addressing Arctic design adaptation, inter-project utility coordination, winter construction mitigation strategies, temporary space requirements, budget realism, cost drivers, supply chain risks, collaboration priorities, stipend preferences, contract incentives, and evaluation criteria rankings. Responses inform the Government's selection of the optimal project delivery path and contracting vehicle to balance cost certainty, schedule feasibility, quality control, and innovation within established budget constraints.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Comprehensive Market Research Questionnaire
Project Delivery & Acquisition Strategy
Originating Agency U.S. Army Corps of Engineers / Alaska District
Document Type Sources Sought / Request for Information (RFI) Template
Target Audience Project Delivery Teams (PDTs) & Industry Partners
Classification Unclassified / Pre-Solicitation
Market Research Questionnaire | Project Delivery & Acquisition Strategy
Table of Contents
1. Project Information Packet (PIP)
Project Overviews & Constraints
2. Industry Questionnaire
Part I: Company Information & Bidding Intent
Part II: Project-Specific Challenges
1. Arctic Adaptation of Army Standard Design ………………
2. Inter-Project Coordination & Site Handover
3. Schedule Risk & Winter Construction .…………
4. Structuring the OTA for Success …………………
5. Temporary Space Requirements
6. Construction Duration & Schedule Realism
7. Mobilization & Start-Work Readiness …
8. Unidentified Project Risks ………
Part III: Budget, Cost Drivers & Schedule
1. Budget Realism
2. Primary Cost Drivers
3. Schedule/Supply Chain Risk
Part IV: Defining Value, Collaboration & Financial Drivers
1. Collaboration Priorities
2. Industry Engagement & Proprietary Meetings
3. Stipends (Honorariums) & Proposal Costs
4. Contract Incentives
5. Program Capability/Interest
Part V: Overall Delivery Recommendation
1. Recommended Project Delivery Path
2. Basis of Recommendation & Contracting Vehicle
3. Evaluation Strategy
4. Commercial Best Practices & Concerns
1. Project Information Packet (PIP)
Project Overviews & Constraints
FTW511
Project Name & Location Soldier Performance Readiness Center (SPRC), Ft Wainright, AK
Mission Statement Design and Construct a Holistic Health and Fitness (H2F) facility building at Fort Wainwright Alaska, adapted to Arctic Conditions and the Ft Wainwright Installation Design Standards.
Facility Type & Scale Training Facility with administrative space
Primary Functional Spaces Project includes all administrative/office areas, all fitness modules (enclosed Warm up (Zone 0), Resistance (Zone 1), Accessory (Zone 2), and Work Capacity/Agility (Zone 3)), Re-conditioning and cognitive area, 2ea classrooms, Break/Team room, restrooms and storage, special foundations, fire protection and alarm with sprinklers systems, carbon monoxide detection and alarm systems, Building Information Systems. Energy Monitoring and Control System (EMCS), security and CCTV systems, and mass notification systems are included. Adjusted Gross building area not to exceed 48,633 square feet.
Funding Type MILCON
Target Budget (CCL) $76M
Period of Performance FY27-FY30
Critical Milestones Design start FY27, Construction starts not earlier than FY28.
FTW515
Project Name & Location Unaccompanied Enlisted Housing Barracks, Ft Wainwright Alaska
Mission Statement Design and Construct a multi-story Barracks building at Fort Wainwright Alaska, adapted to Arctic Conditions and the Ft Wainwright Installation Design Standards. Project shall utilize some form of Volumetric Modular Construction, Kit of Parts, or 3D Printed Structures. These methods offer higher off-site quality control, improve thermal performance, and drastically reduce the time Soldiers wait for new facilities.
Facility Type & Scale Soldier Housing
Primary Functional Spaces Construct a standard design Unaccompanied Enlisted Personnel Housing Facility to accommodate 256 soldiers. Primary facilities include living and sleeping quarters, bathroom, storage, laundry rooms, service areas, a day room on each floor, two elevators, building information systems, fire protection and alarm systems, Mass Notification Systems, Intrusion Detection System, and Energy Monitoring Control Systems connection. Sustainability and energy measures are included. Deep excavation and special foundations will be required to mitigate damage from frozen soils and to mitigate potential seismic effects. Adjusted Gross Area of 133,506 square feet.
Funding Type MILCON
Target Budget (CCL) $201M
Period of Performance FY27 – FY30
Critical Milestones Design Starts FY27 and Construction Starts FY28
2. Industry Questionnaire
Purpose: The Government seeks your expert feedback to select the optimal project delivery method and contracting vehicle (FAR-based or OTA) for the above facilities. Please email your response to Mark Corn (Mark.R.Corn@usace.army.mil), Kim Tripp (Kimberly.D.Tripp@usace.army.mil), Katherine Green ( Katherine.Green@usace.army.mil), and Theresa Afrank (Theresa.M.Afrank@usace.army.mil) by 07 October 2026 at 14:00 Alaska Time.
Accelerated Design-Build to Budget (DBtB) FAR-based delivery approach where the Government develops sufficient project definition to competitively establish a Firm-Fixed-Price before collaborative design development.
Construction Manager at Risk (CM At Risk) - OTA Project delivery method where a construction manager acts as a consultant to the owner during the design phase and transitions to a general contractor role during construction.
Progressive Design-Build (PDB) – OTA Single design-build agreement. Phase 1 collaboratively matures the design and negotiates a Guaranteed Maximum Price cost before the Government decides whether to proceed with construction.
Part I: Company Information & Bidding Intent
Company Name & CAGE Code
Point of Contact
Socioeconomic Status (Check all that apply)
☐ Large Business ☐ Small Business (SB) ☐ 8(a) Business Development Program ☐ HUBZone Small Business ☐ Service-Disabled Veteran-Owned (SDVOSB) ☐ Women-Owned Small Business (WOSB)
Bonding Capacity Single Project Limit: $[Insert Amount Here]_______________ Aggregate Limit: $[Insert Amount Here]_______________
Intent to Propose ☐ Yes as Prime ☐ Yes as Sub ☐ No ☐ Undecided mailto:Mark.R.Corn@usace.army.mil mailto:Kimberly.D.Tripp@usace.army.mil mailto:Katherine.Green@usace.army.mil mailto:Theresa.M.Afrank@usace.army.mil
Anticipated Teaming ☐ Standalone Prime ☐ Joint Venture (JV) ☐ Mentor-Protégé ☐ Subcontractor/Designer Only
Part II: Project-Specific Challenges
1. Arctic Adaptation of Army Standard Design The Barracks and SPRC are based upon Army Standard Designs. The Standard designs have required program areas and adjacencies to be incorporated into the final design. Both standard designs have area waivers which allow them to exceed the baseline standards to the area currently programmed. Approval of the Final designs will require further review and concurrence with the respective Army Centers of Standardization. Therefore, awarded offerors must coordinate extensively with the Centers of Standardization in addition to local Ft Wainwright Directorate of Public Works, End User Groups, and USACE Alaska District project Stakeholders. Which of the project delivery methods, of those identified previously in this questionnaire, offers the most opportunity for engagement and coordination with project stakeholders without incurring risk of project cost increases or delays?
2. Inter-Project Coordination & Site Handover The Government intends to provide mainline utilities to the point of demarcation for each project site. Design and construction coordination with the Government representatives for the final utility installation will be a significant responsibility of an awarded offeror. How would you mitigate risks associated with this, and what specific validation criteria would you require upon site turnover?
3. Schedule Risk & Winter Construction Given the aggressive timelines required to complete design in one year and the realities of the short Alaskan construction season, how would you mitigate weather delays? Please describe off-site prefabrication strategies, modular construction, winter-enclosure techniques, and/or other strategies that you would propose to maintain construction momentum year-round. How could the Government best structure initial design phase collaboration to evaluate the cost-versus-time tradeoffs of the described acquisition methods before finalizing a Guaranteed Maximum Price for Construction phase services?
4. Structuring the OTA for Success Describe which OTA vehicle your firm feels will yield the highest probability of a completed facility at or below the budget target without compromise to project quality. What performance metrics or strategies do you recommend the Government build into an OTA to mitigate the risks of a delay or project cost increase?
5. Temporary Space Requirements For each project identified, what is the estimated space requirement for temporary facilities including, but not limited to: material laydown, worksite offices, workforce parking, etc.?
Furthermore, do you foresee any need for new or upgraded supporting infrastructure, such as access roads or port facilities, to support construction logistics for each of the identified projects?
6. Construction Duration & Schedule Realism What do you believe is a reasonable timeframe (in calendar days or years) to complete each projects’ design and construction phase, assume the awarded agreement is in the fourth quarter of the identified fiscal year?
7. Mobilization & Start-Work Readiness Assuming an award is made, for each separate project, what is your firm's estimated lead time to mobilize Phase 1 (Design and Preconstruction Services) and Phase 2 (Final Design & Construction Services)? What is the optimal time of year for a contract award to align with your mobilization and maximize the active construction season?
8. Unidentified Project Risks Outside of the challenges already identified, what other significant risks do you foresee for projects of this scale, type and complexity at Ft Wainwright? Which project delivery method best supports potential offeror’s ability to address unidentified project risks with minimal cost and/or delay of project delivery?
Part III: Budget, Cost Drivers & Schedule
1. Budget Realism Based on current market data, do the target budgets appear realistic for these facility types and scale?
2. Primary Cost Drivers What specific project needs or functional requirements do you anticipate driving the most cost?
3. Schedule/Supply Chain Risk What systems or trades present the most significant schedule risk (e.g., long-lead MEP, local labor)?
Part IV: Defining Value, Collaboration & Financial Drivers
1. Collaboration Priorities Please rank the areas that would benefit most from early builder involvement during the design phase of the above projects (1 = Greatest Benefit, 5 = Least Benefit).
Area of Collaboration Rank (1–5)
Cost Certainty & Real-Time Estimating _______________
Schedule Certainty & Phasing _______________
Constructability & Quality Control _______________
Innovation & Scope Betterments (Getting more for the money) _______________
Overall Risk Reduction / Site Mitigations _______________
2. Industry Engagement & Proprietary Meetings If the Government utilizes a delivery method that allows for confidential, one-on-one proprietary meetings during the solicitation phase to collaboratively discuss innovative solutions, would your firm participate?
☐ Yes ☐ No
3. Stipends (Honorariums) & Proposal Costs In procurement methods with significant proposal phase efforts, would the Government's offer of a stipend significantly influence your decision to compete?
☐Yes ☐ No
If Yes, what is a commercially reasonable stipend amount for a project of this scale? [Insert Amount/Percentage Here] ______________________________
4. Contract Incentives What specific contract incentives would best drive innovation and maximize your firm's interest in these projects?
☐ Shared Cost Savings (e.g., within a GMP Structure)
☐ Award Fee for Quality / Innovation
☐ Other [Insert Recommendations Here] ______________________________
5. Program Capability/Interest Considering the projects listed in Section 1 for Ft Wainwright with a combined estimated value of approximately $277M:
a) Would your firm be interested in proposing as a prime contractor?
☐Yes ☐ No
b) If yes, does your firm have the necessary bonding capacity to cover the total estimated project value?
☐Yes ☐ No
c) If yes, please state your firm’s current aggregate bonding capacity. [Insert Amount Here]
Part V: Overall Delivery Recommendation
1. Recommended Project Delivery Path Considering all factors, which project delivery path is optimal for these specific projects?
(Provide a response for each project listed in Section 1 above)
FTW511 - SPRC
☐ CM@Risk: Government needs to control the design but needs early builder collaboration.
☐ Design-Build to Budget (DBtB): Requirements are understood enough to drive a competitive (10-15%), fixed-price solution, use of proprietary meetings to advance design solutions (highly collaborative).
☐ Progressive Design-Build (PDB): Scope is highly complex/undefined. Requires a single contract to collaboratively mature the design before locking in a GMP.
FTW515 - Barracks
☐ CM@Risk: Government needs to control the design but needs early builder collaboration.
☐ Design-Build to Budget (DBtB): Requirements are understood enough to drive a competitive (10-15%), fixed-price solution, use of proprietary meetings to advance design solutions (highly collaborative).
☐ Progressive Design-Build (PDB): Scope is highly complex/undefined. Requires a single contract to collaboratively mature the design before locking in a GMP.
2. Basis of Recommendation & Contracting Vehicle Please explain your selections above for each project. Additionally, please indicate if you recommend executing this via a standard FAR-based contract vs the provided OTA type options:
3. Evaluation Strategy For each project, rank what evaluation criteria you believe the Government should weight most heavily to ensure the highest value project?
Evaluation Factors Rank (1–4)
Past Performance _______________
Technical Approach/Design _______________
Price/GMP _______________
Key Personnel & Team Integration _______________
Other [Insert Recommendations] ___________________________________ _______________
4. Commercial Best Practices & Concerns Please provide any additional comments, overly prescriptive constraints to avoid, and/or commercial best practices the Government should consider.
| Table of Contents |
| 1. Project Information Packet (PIP) |
| Project Overviews & Constraints |
| 2. Industry Questionnaire |
| Accelerated Design-Build to Budget (DBtB) |
| Construction Manager at Risk (CM At Risk) - OTA |
| Progressive Design-Build (PDB) – OTA |
| 1. Arctic Adaptation of Army Standard Design |
| 2. Inter-Project Coordination & Site Handover |
| 3. Schedule Risk & Winter Construction |
| 4. Structuring the OTA for Success |
| 5. Temporary Space Requirements |
| 6. Construction Duration & Schedule Realism |
| 7. Mobilization & Start-Work Readiness |
| 8. Unidentified Project Risks |
| Part III: Budget, Cost Drivers & Schedule |
| 1. Budget Realism |
| 2. Primary Cost Drivers |
| 3. Schedule/Supply Chain Risk |
| Part IV: Defining Value, Collaboration & Financial Drivers |
| 1. Collaboration Priorities |
| 2. Industry Engagement & Proprietary Meetings |
| 3. Stipends (Honorariums) & Proposal Costs |
| 4. Contract Incentives |
| 5. Program Capability/Interest |
| Part V: Overall Delivery Recommendation |
| 1. Recommended Project Delivery Path |
| 2. Basis of Recommendation & Contracting Vehicle |
| 3. Evaluation Strategy |
| 4. Commercial Best Practices & Concerns |