Market Research Intelligence Questionnaire EIE485 .pdf
PDF 322 KB Posted
- Solicitation number
- W911KB27RWP04
- Issued by
-
Department of Defense
About this file
This is a Comprehensive Market Research Questionnaire and Request for Information (RFI) issued by the U.S. Army Corps of Engineers Alaska District to solicit industry feedback on project delivery methods and contracting strategies for a military construction project at Eielson Air Force Base in Alaska.
The project, designated EIE485 – Consolidated Munitions on Quarry Hill, involves designing and constructing seven munitions storage facilities totaling approximately 64,125 square feet at Quarry Hill, including a warm storage vehicle facility (24,700 SF), cold inert munitions storage facility (10,075 SF), four heated 4-bay munition storage magazines (1,350 SF each), and a munitions production facility (26,700 SF). The project also includes demolition of 27,550 square feet of existing facilities at Engineer Hill located 12 miles away. The project is funded under MILCON with a target budget of $196.4 million and a performance period spanning FY27 through FY31, with design commencing in FY27 and construction starting no earlier than FY29. Responses should address three proposed delivery methods: Accelerated Design-Build to Budget (DBtB) using FAR-based procedures, Construction Manager at Risk (CM@Risk) using an OTA structure, and Progressive Design-Build (PDB) using an OTA structure. The questionnaire requests industry input on site and environmental constraints (high water table, permafrost, soil contamination including PFAS), Air Force Standard Design coordination requirements, scheduling strategies for Alaska's limited construction window, budget realism, cost drivers, mobilization timelines, collaboration priorities, contract incentives, bonding capacity, and evaluation criteria. Responses should be emailed to Kim Tripp (Kimberly.D.Tripp@usace.army.mil) and Michelle Nelsen (Michelle.Nelsen@usace.army.mil). This is a pre-solicitation market research activity and does not represent an actual contract award opportunity.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Comprehensive Market Research Questionnaire
Project Delivery & Acquisition Strategy
Originating Agency U.S. Army Corps of Engineers / Alaska District
Document Type Sources Sought / Request for Information (RFI)
Target Audience Project Delivery Teams (PDTs) & Industry Partners
Classification Unclassified / Pre-Solicitation
Market Research Questionnaire | Project Delivery & Acquisition Strategy
Table of Contents
1. Project Information Packet (PIP)
Project Overviews & Constraints
2. Industry Questionnaire
Part I: Company Information & Bidding Intent
Part II: Project-Specific Challenges
1. Site and Environmental Constraints ………………
2. Air Force Standard Design
3. Site Preparation Phasing Options……………………………………………………………………………..6
4. Schedule Risk & Limited Construction Window
5. Structuring the OTA for Success …………………
6. Temporary Space Requirements
7. Construction Duration & Schedule Realism
8. Mobilization & Start-Work Readiness …
9. Unidentified Project Risks ………
Part III: Budget, Cost Drivers & Schedule
1. Budget Realism
2. Primary Cost Drivers
3. Schedule/Supply Chain Risk
Part IV: Defining Value, Collaboration & Financial Drivers
1. Collaboration Priorities
2. Industry Engagement & Proprietary Meetings
3. Stipends (Honorariums) & Proposal Costs
4. Contract Incentives
5. Program Capability/Interest
Part V: Overall Delivery Recommendation
1. Recommended Project Delivery Path
2. Basis of Recommendation & Contracting Vehicle
3. Evaluation Strategy
4. Commercial Best Practices & Concerns
1. Project Information Packet (PIP)
Project Overviews & Constraints EIE485 – Consolidated Munitions on Quarry Hill
Project Name & Location Consolidated Munitions on Quarry Hill, Eielson AFB, AK
Mission Statement Design and construct the consolidation of munitions storage functions to Quarry Hill and demolition of existing munitions storage facilities at Engineer Hill. The two sites are approximately 12 miles apart on Eielson AFB, Alaska. Design and construction at Quarry Hill will include a warm storage vehicle facility, a cold inert munitions storage facility, four heated 4-bay munition storage magazines, and a munitions production facility. Demolition and debris removal will include 12x facilities totaling to 3,613 SM on Engineer Hill includes earth-covered reinforced concrete munitions storage igloos, and above ground utilidor, a communications tower, and a 60,000-gallon fire water tank. Demolition work will take place as part of site improvement on Quarry hill for supporting facilities totaling to 5,875 SM of demolition work
Facility Type & Scale
Seven Facilities for Munition Storage Operations: Vehicle Storage 24,700 SF, Cold Inert Storage 10,075 SF, 4x Multi-Bay Magazines 1,350 SF each, Munition Production Facility 26,700 SF.
Demolition 27,550 SF
Primary Functional Spaces Project includes the design and construction of a warm storage vehicle facility, a cold inert munitions storage facility, four heated 4-bay munition storage magazines, a munitions production facility, and the demolition of facilities at Quarry Hill on Eielson AFB, AK.
Additional construction will include concrete aprons/pads surrounding the buildings and their outside doors and other site improvements.
Funding Type MILCON
Target Budget (CCL) $196.4M
Period of Performance FY27-FY31
Critical Milestones Design start FY27, Construction starts not earlier than FY29
2. Industry Questionnaire
Purpose: The Government seeks your expert feedback to select the optimal project delivery method and contracting vehicle (FAR-based or OTA) for the above facilities. Please email your response to Kim Tripp (Kimberly.D.Tripp@usace.army.mil) and Michelle Nelsen (Michelle.Nelsen@usace.army.mil)
Accelerated Design-Build to Budget (DBtB) FAR-based delivery approach where the Government develops sufficient project definition to competitively establish a Firm-Fixed-Price before collaborative design development.
Construction Manager at Risk (CM At Risk) - OTA Project delivery method where a construction manager acts as a consultant to the owner during the design phase and transitions to a general contractor role during construction.
Progressive Design-Build (PDB) – OTA Single design-build agreement. Phase 1 collaboratively matures the design and negotiates a Guaranteed Maximum Price cost before the Government decides whether to proceed with construction.
Part I: Company Information & Bidding Intent
Company Name & CAGE Code
Point of Contact
Socioeconomic Status (Check all that apply)
☐ Large Business ☐ Small Business (SB) ☐ 8(a) Business Development Program ☐ HUBZone Small Business ☐ Service-Disabled Veteran-Owned (SDVOSB) ☐ Women-Owned Small Business (WOSB)
Bonding Capacity Single Project Limit: $[Insert Amount Here]_______________ Aggregate Limit: $[Insert Amount Here]_______________
Intent to Propose ☐ Yes as Prime ☐ Yes as Sub ☐ No ☐ Undecided mailto:Kimberly.D.Tripp@usace.army.mil mailto:Michelle.Nelsen@usace.army.mil
Anticipated Teaming ☐ Standalone Prime ☐ Joint Venture (JV) ☐ Mentor-Protégé ☐ Subcontractor/Designer Only
Part II: Project-Specific Challenges
1. Site and Environmental Constraints
Site location contains a high-water table (3’ below ground level in several areas) and likely soil contamination to include PFAS. Demolition of existing facilities to include Engineer Hill and construction may encounter asbestos or PCB contamination. Some site locations for the projects are impacted by permafrost creating ground instability when thawed requiring specialized foundation designs and engineering strategies to maintain structural integrity of the projects. What risks do you anticipate associated with the high groundwater conditions, the potential for permafrost, and contaminated soils during construction? What methods would you use to help mitigate these risks?
What information or project requirements would you recommend be established during preconstruction to reduce these risks?
2. Air Force Standard Design
Munition facilities are based upon Air Force Standard Designs including Defense Explosives Safety Regulation (DESR) 6055.09, and Air Force Manual AFMAN 91-01 Explosives Safety Standards. The Standard designs have required program areas and adjacencies to be incorporated into the final design. Both standard designs have area waivers which allow them to exceed the baseline standards to the area currently programmed. Approval of the Final designs will require further review and concurrence with the respective Centers of Standardization. Therefore, awarded offerors must coordinate extensively with the Centers of Standardization in addition to local Eielson AFB Civil Engineering Squadron, End User Groups, and USACE Alaska District project Stakeholders. Which of the project delivery methods, of those identified previously in this questionnaire, offers the most opportunity for engagement and coordination with project stakeholders without incurring risk of project cost increases or delays?
3. Site Preparation Phasing Options
During the Agreement Phase 1 (Green Phase) of PDB with OT Pre-Construction Work can take place such as site readiness. What would your approach be to mitigate cost/rework while decreasing schedule risk to conduct site preparation during the Green Phase? Take into consideration site preparation could include placing long lead materials on order, demolition of select nonoperational facilities, earthwork, debris removal, etc.
4. Schedule Risk & Limited Construction Window
Given the timelines required to complete design and construction for these projects and the realities of the short Alaskan limited construction window, how would you mitigate weather delays? Please describe off-site prefabrication strategies, modular construction, winter-enclosure techniques, and/or other strategies that you would propose to maintain construction schedule. How could the
Government best structure initial design phase collaboration to evaluate the cost-versus-time tradeoffs of the described acquisition methods before finalizing a Guaranteed Maximum Price for Construction phase services?
5. Structuring the OTA for Success Describe which OTA vehicle your firm feels will yield the highest probability of a completed facility at or below the budget target without compromise to project quality. What performance metrics or strategies do you recommend the Government build into an OTA to mitigate the risks of a delay or project cost increase?
6. Temporary Space Requirements For the project identified, what is the estimated space requirement for temporary facilities including, but not limited to: material laydown, worksite offices, workforce parking, etc.? Furthermore, do you foresee any need for new or upgraded supporting infrastructure, such as access roads or port facilities, to support construction logistics for each of the identified projects?
7. Construction Duration & Schedule Realism What do you believe is a reasonable timeframe (in calendar days or years) to complete the project’s design and construction phase, assume the awarded agreement is in the fourth quarter of the identified fiscal year?
8. Mobilization & Start-Work Readiness Assuming an award is made, for the project, what is your firm's estimated lead time to mobilize Phase 1 (Design and Preconstruction Services) and Phase 2 (Final Design & Construction Services)? What is the optimal time of year for a contract award to align with your mobilization and maximize the active construction season?
9. Unidentified Project Risks Outside of the challenges already identified, what other significant risks do you foresee for projects of this scale, type and complexity at Eielson AFB? Which project delivery method best supports potential offeror’s ability to address unidentified project risks with minimal cost and/or delay of project delivery?
Part III: Budget, Cost Drivers & Schedule
1. Budget Realism Based on current market data, do the target budgets appear realistic for these facility types and scale?
2. Primary Cost Drivers What specific project needs or functional requirements do you anticipate driving the most cost?
3. Schedule/Supply Chain Risk What systems or trades present the most significant schedule risk (e.g., long-lead MEP, local labor)?
Part IV: Defining Value, Collaboration & Financial Drivers
1. Collaboration Priorities Please rank the areas that would benefit most from early builder involvement during the design phase of the above projects (1 = Greatest Benefit, 5 = Least Benefit).
Area of Collaboration Rank (1–5)
Cost Certainty & Real-Time Estimating _______________
Schedule Certainty & Phasing _______________
Constructability & Quality Control _______________
Innovation & Scope Betterments (Getting more for the money) _______________
Overall Risk Reduction / Site Mitigations _______________
2. Industry Engagement & Proprietary Meetings If the Government utilizes a delivery method that allows for confidential, one-on-one proprietary meetings during the solicitation phase to collaboratively discuss innovative solutions, would your firm participate?
☐ Yes ☐ No
3. Stipends (Honorariums) & Proposal Costs In procurement methods with significant proposal phase efforts, would the Government's offer of a stipend significantly influence your decision to compete?
☐Yes ☐ No
If Yes, what is a commercially reasonable stipend amount for a project of this scale? [Insert Amount/Percentage Here] ______________________________
4. Contract Incentives What specific contract incentives would best drive innovation and maximize your firm's interest in these projects?
☐ Shared Cost Savings (e.g., within a GMP Structure)
☐ Award Fee for Quality / Innovation
☐ Other [Insert Recommendations Here] ______________________________
5. Program Capability/Interest Considering the projects listed in Section 1 for Eielson AFB with a combined estimated value of approximately $196.4M:
a) Would your firm be interested in proposing as a prime contractor?
☐Yes ☐ No
b) If yes, does your firm have the necessary bonding capacity to cover the total estimated project value?
☐Yes ☐ No
c) If yes, please state your firm’s current aggregate bonding capacity. [Insert Amount Here]
Part V: Overall Delivery Recommendation
1. Recommended Project Delivery Path Considering all factors, which project delivery path is optimal for these specific projects?
(Provide a response for each project listed in Section 1 above)
☐ CM@Risk: Government needs to control the design but needs early builder collaboration.
☐ Design-Build to Budget (DBtB): Requirements are understood enough to drive a competitive (10-15%), fixed-price solution, use of proprietary meetings to advance design solutions (highly collaborative).
☐ Progressive Design-Build (PDB): Scope is highly complex/undefined. Requires a single contract to collaboratively mature the design before locking in a GMP.
2. Basis of Recommendation & Contracting Vehicle Please explain your selections above for each project. Additionally, please indicate if you recommend executing this via a standard FAR-based contract vs the provided OTA type options:
3. Evaluation Strategy For the project, rank what evaluation criteria you believe the Government should weight most heavily to ensure the highest value project?
Evaluation Factors Rank (1–4)
Past Performance _______________
Technical Approach/Design _______________
Price/GMP _______________
Key Personnel & Team Integration _______________
Other [Insert Recommendations] ___________________________________ _______________
4. Commercial Best Practices & Concerns Please provide any additional comments, overly prescriptive constraints to avoid, and/or commercial best practices the Government should consider.
| Table of Contents |
| 1. Project Information Packet (PIP) |
| Project Overviews & Constraints |
| 2. Industry Questionnaire |
| Accelerated Design-Build to Budget (DBtB) |
| Construction Manager at Risk (CM At Risk) - OTA |
| Progressive Design-Build (PDB) – OTA |
| 2. Air Force Standard Design |
| 3. Site Preparation Phasing Options |
| 4. Schedule Risk & Limited Construction Window |
| 5. Structuring the OTA for Success |
| 6. Temporary Space Requirements |
| 7. Construction Duration & Schedule Realism |
| 8. Mobilization & Start-Work Readiness |
| 9. Unidentified Project Risks |
| Part III: Budget, Cost Drivers & Schedule |
| 1. Budget Realism |
| 2. Primary Cost Drivers |
| 3. Schedule/Supply Chain Risk |
| Part IV: Defining Value, Collaboration & Financial Drivers |
| 1. Collaboration Priorities |
| 2. Industry Engagement & Proprietary Meetings |
| 3. Stipends (Honorariums) & Proposal Costs |
| 4. Contract Incentives |
| 5. Program Capability/Interest |
| Part V: Overall Delivery Recommendation |
| 1. Recommended Project Delivery Path |
| 2. Basis of Recommendation & Contracting Vehicle |
| 3. Evaluation Strategy |
| 4. Commercial Best Practices & Concerns |