Document Summary: MARESA Office Improvements Project
This is a bidding document package for the Marquette-Alger Regional Education Service Agency (MARESA) office improvements project located at 321 East Ohio Street, Marquette, Michigan. The scope of work includes replacement of the building roof, HVAC systems, existing windows and window treatments, renovation of flooring finishes throughout the building, and renovation of office spaces including metal stud framing, drywall, HVAC, electrical work, finishes, and updates to the building's fire alarm system. The project is a stipulated sum contract (fixed-price) with a bid opening date of April 8, 2021, at 1:00 PM local time. A mandatory pre-bid walkthrough was scheduled for March 25, 2021, at 10:00 AM. The contract completion date is specified as August 20, 2021, with liquidated damages of $300 per calendar day assessed for delays beyond the substantial completion date. Bidding documents were available for purchase at $70 for paper copies or $35 for PDF format on flash drive.
The contract will be executed using the AIA Document A101-2017 Standard Form of Agreement between Owner and Contractor on a single-prime basis, governed by AIA Document A201-2017 General Conditions with modifications by the Owner. Bids must be accompanied by bid security (bid bond) in an amount not less than 10 percent of the total bid sum and must remain irrevocable for 45 days after submission. The Contractor is required to provide performance and payment bonds each in the penal sum of 100 percent of the contract amount. Contract requirements include comprehensive general liability insurance with minimum limits of $1,000,000 per occurrence and $2,000,000 aggregate, workers' compensation insurance, automobile liability coverage, and additional insured endorsements naming the Owner and Architect. The contract includes a 10 percent retainage provision on progress payments with specific closeout allocations for as-built documents (1.0 percent), training and O&M manuals (1.0 percent), attic stock materials (0.5 percent), punchlist completion (2.0 percent), and warranty documents (0.5 percent). The project is funded by MARESA, an educational service agency, and all work must comply with Michigan law and local building codes.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BIDDING DOCUMENTS
FOR
MARQUETTE ALGER REGIONAL EDUCATION SERVICE AGENCY
OFFICE IMPROVEMENTS
MARQUETTE, MICHIGAN
Prepared by:
U.P. Engineers & Architects, Inc.
424 S Pine Street
Ishpeming, MI 49849
March 5, 2021
[M337-00621]
TABLE OF CONTENTS 000110 - 1
SECTION 000110 - TABLE OF CONTENTS
Division Section Title
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 10 Table of Contents
PROCUREMENT REQUIREMENTS
00 11 16 Advertisement for Bid
00 21 13 Instructions to Bidders
00 41 13 Bid Form - Stipulated Sum (single-prime Contract)
CONTRACTING REQUIREMENTS
00 52 14 Agreement Form - AIA Stipulated Sum (single-prime Contract)
AIA Agreement A105 - 2017
DIVISION 01 – GENERAL REQUIREMENTS
01 10 00 Summary
01 20 00 Price and Payment Procedures
01 30 00 Administrative Requirements
01 33 00 Submittal Procedures
01 40 00 Quality Requirements
01 50 00 Temporary Facilities and Controls
01 60 00 Product Requirements
01 70 00 Execution and Closeout Requirements
TECHNICAL SPECS
END OF TABLE OF CONTENTS
Advertisement for Bids
00 11 16 - 1
SECTION 00 11 16 – ADVERTISEMENT FOR BID
Project: Marquette Alger Regional Education Service Agency Office Improvements
Owner: Marquette-Alger RESA
321 E Ohio Street
Marquette, Michigan 49855
Architect/Engineer:
U.P. Engineers & Architects, Inc.
424 South Pine Street
Ishpeming, Michigan 49849
(906) 485-1011 www.upea.com
Date: March 5, 2021
Bids will be accepted under seal to the Owner for renovations to the Marquette-Alger RESA, located at 321 E
Ohio Street, Marquette, Michigan.
Owner will receive Bids at the office of Marquette-Alger RESA address above, until 1:00 PM local time on the
Eighth day of April, 2021, at which time and place the Bids will be privately opened. Bids not received by the indicated time will not be opened.
A walkthrough will be held for interested contractors on March 25, 2021 at 10:00 a.m. eastern standard time. Meet at Marquette-Alger RESA, located at 321 E Ohio Street, Marquette, Michigan, 49855. All interested contractors are encouraged to attend. Meet in the main lobby (south entrance).
Project Description: Replace building roof, HVAC systems, existing windows and window treatments. Renovate flooring finish throughout building, and renovate office spaces including metal stud, drywall, HVAC, electrical and finishes.
Bidding Documents for a Stipulated Price contract may be obtained by contacting UPEA, whose contact information is listed above, in either paper form or as pdf documents on a flash drive, as follows:
Paper copy: for a $70 non-refundable fee
PDF: for a $35 non-refundable fee
Documents will also be available for viewing at the office of the Architect and at the following Builders
Exchanges: Iron Mountain-Kingsford, Marquette, Michigan, Northwest Michigan, and McGraw Hill
Construction-Dodge (Lansing).
Bidders will be required to provide Bid security according to the requirements in Section 00 21 13 - Instructions to
Bidders. Bidders are required to submit qualifications to the approval of the Architect and Owner with their bid.
Submit your Bid on the Bid Form provided. Refer to other Bidding requirements described in Section 00 21 13.
Bids are required to be submitted under a condition of irrevocability for a period of 45 days after submission.
Owner reserves the right to waive irregularities and to accept or reject any or all Bids.
Marquette-Alger RESA
Anthony Bertucci, Associate Superintendent for Finance, Facilities and Information Systems
END OF DOCUMENT
Instructions To Bidders
002113 - 1
SECTION 00 21 13
INSTRUCTIONS TO BIDDERS
1.1 SUMMARY
A. Document Includes:
1. Bid submission.
2. Intent.
3. Work identified in Contract Documents.
4. Contract Time.
5. Definitions.
6. Contract Documents identification.
7. Availability of documents.
8. Examination of documents.
9. Inquiries and Addenda.
10. Product substitutions.
11. Site examination.
12. Prebid meeting.
13. Bidder qualifications.
14. Subcontractors.
15. Submission procedure.
16. Bid ineligibility.
17. Bid Security.
18. Bid Form requirements.
19. Bid Form signature.
20. Bid opening.
21. Duration of offer.
22. Acceptance of offer.
B. Related Documents:
1. Document 00 11 16 - Invitation to Bid.
2. Document 00 41 13 - Bid Form - Stipulated Sum (Single-Prime Contract).
1.2 BID SUBMISSION
A. Bids signed and sealed, executed, and dated will be received by Owner located at the office of the Architect as noted on the Advertisement for Bids.
B. Bids submitted after the above time may be returned to Bidder unopened.
C. Amendments to submitted Bids will be permitted when received in writing prior to
Bid closing and when endorsed by the same party or parties who signed and sealed the Bid.
D. Bidders may withdraw their Bid by written request before the above time.
1.3 INTENT
002113 - 2
A. The intent of this Bid request is to obtain an offer to perform work to complete the
Work for a Stipulated Sum contract, according to Contract Documents.
1.4 WORK IDENTIFIED IN CONTRACT DOCUMENTS
A. Work of this proposed Contract as described in the Advertisement for Bids.
1.5 CONTRACT TIME
A. Perform the Work within time stated in the Bid Form. Bidder, in submitting an offer, accepts Contract Time period stated for performing the Work. Owner requires Work of this Contract be completed as soon as possible.
1.6 DEFINITIONS
A. Bidding Documents: Contract Documents supplemented with Advertisement for
Bids, Instructions to Bidders, Bid Form, and Bid securities.
B. Contract Documents: AIA A105-2017.
C. Bid: Executed Bid Form and required attachments submitted according to
Instructions to Bidders.
D. Bid Sum: Monetary sum identified by the Bidder in the Bid Form.
1.7 CONTRACT DOCUMENTS IDENTIFICATION
A. Contract Documents are identified as Project number M337-00621 as prepared by
U.P. Engineers & Architects, Inc. and identified in the Project Manual.
1.8 AVAILABILITY OF DOCUMENTS
A. Bidding Documents may be obtained as stated in Advertisement for Bids.
B. Bidding Documents are made available only for the purpose of obtaining offers for this Project. Their use does not grant a license for other purposes.
1.9 EXAMINATION OF DOCUMENTS
A. Upon receipt of Bidding Documents verify that documents are complete. Notify
Architect if documents are incomplete.
B. Immediately notify Architect upon finding discrepancies or omissions in Bidding
Documents.
1.10 INQUIRIES AND ADDENDA
A. Requests for Information/Clarification:
1. Direct questions in writing to mtreado@upea.com or Fax: 906.485.1013.
2. Submit questions not less than seven days before date set for receipt of Bids.
3. Verbal answers are not binding on any party.
002113 - 3
4. Replies will be made by Addenda.
5. Responses to inquiries affecting clarity of documents or perceived to affect cost will be addressed by Addenda, to be issued during Bidding period.
B. Addenda:
1. Addenda will be sent to known Bidders and to those who are known to have received a complete set of Bidding Documents.
2. Addenda become part of Contract Documents.
3. Include resultant costs in Bid Price.
1.11 PRODUCT SUBSTITUTIONS
A. Where Bidding Documents stipulate particular products, substitution requests will be considered by Architect up to 10 days before receipt of Bids.
B. With each substitution request, provide sufficient information for Architect to determine acceptability of proposed products. Comply with substitution request submittal requirements in Section 01 60 00 - Product Requirements including the use of the Substitution Request Form.
C. When a request to substitute a product is made, Architect may approve the substitution. Approved substitutions will be identified by Addenda.
D. In submission of substitutions to products specified, Bidders shall include in their
Bid changes required in the Work changes to Contract Time and changes to
Contract Sum to accommodate such approved substitutions. Later claims by the
Bidder for an addition to the Contract Time or Contract Sum because of changes in
Work necessitated by use of substitutions will not be considered.
1.12 SITE EXAMINATION
A. Examine the Project site before submitting a Bid.
1.13 PREBID MEETING
A. A prebid meeting is scheduled as listed in the Advertisement for Bids.
B. General Contract Bidders are required to attend.
C. Representatives of the Architect and Owner will attend.
D. Information relevant to Bidding Documents will be issued by Addenda.
1.14 BIDDER QUALIFICATIONS
A. To demonstrate qualification for performing the Work of this Contract, Bidders may be requested to submit written evidence of financial position, previous experience, and current commitments.
1.15 SUBCONTRACTORS
002113 - 4
A. Owner reserves the right to reject a proposed Subcontractor for reasonable cause.
1.16 SUBMISSION PROCEDURE
A. Bidders shall be solely responsible for delivery of Bids in manner and time prescribed.
B. Submit two copies of executed offer on Bid Forms provided, signed and sealed with required security deposit in a closed opaque envelope, clearly identified with
Bidder's name and address, Project name, and Owner's name on the outside.
C. Improperly completed information, including irregularities in Bid bond, may be cause not to open the Bid Form envelope and to declare the Bid invalid or informal.
D. An abstract summary of submitted Bids will be made available to all Bidders following Bid opening.
1.17 BID INELIGIBILITY
A. Bids that are unsigned, improperly signed or sealed, conditional, illegible, and obscure, or Bids that contain arithmetical errors, erasures, alterations, or irregularities of any kind, may be declared unacceptable at Owner's discretion.
B. Bid Forms, Appendices, and enclosures that are improperly prepared may be declared unacceptable at Owner's discretion.
C. Failure to provide security deposit, may invalidate the Bid at Owner's discretion.
1.18 BID SECURITY
A. Bids shall be accompanied by Bid security as follows:
1. Bid bond of a sum no less than 10 percent of the Bid Sum on AIA A310 -
Bid Bond or on standard surety company form.
B. Endorse Bid bond in name of the Owner as obligee, signed and sealed by the principal (Contractor) and surety.
C. If the accepted Bidder fails to execute the Agreement and the indicated bonds within 10 days after the Notice of Award, the Notice of Award may be annulled and the Bid security of the Bidder will be forfeited.
D. Include the cost of Bid security in the Bid Sum.
E. If no contract is awarded, Bid security will be returned.
1.19 BID FORM SIGNATURE
A. Sign Bid Form as follows:
002113 - 5
1. Sole Proprietorship: Signature of sole proprietor in the presence of a witness who will also sign. Include the words "Sole Proprietor" under the signature.
Affix seal.
2. Partnership: Signature of all partners in the presence of a witness who will also sign. Include the word "Partner" under each signature. Affix seal to each signature.
3. Corporation: Signature of at least one duly authorized signing officer.
Include the officer's capacity under each signature. Affix the corporate seal.
If Bid is signed by officials other than the president, secretary, or treasurer of the company, submit a copy of the bylaws or a resolution of the board of directors authorizing them to do so, with the Bid Form in the Bid envelope.
4. Joint Venture: Signature of all parties of the joint venture under their respective seals in a manner appropriate to such party as described above, similar to requirements for Partnerships.
1.20 BID OPENING
A. Bids will be opened publicly immediately after time for receipt of Bids. Bidders may be present.
1.21 DURATION OF OFFER
A. Bids shall remain open to acceptance and shall be irrevocable for a period of 30 days after Bid closing date.
1.22 ACCEPTANCE OF OFFER
A. Owner reserves the right to waive irregularities and to accept or reject any or all offers.
B. After acceptance by Owner, Architect, on behalf of Owner, will issue to the accepted Bidder a written Notice of Award.
C. Notwithstanding delay in the preparation and execution of the Agreement, accepted
Bidder shall be prepared, upon written Notice to Proceed, to commence work within seven days following receipt of official written order of Owner to proceed, or on date stipulated in such order.
D. The accepted Bidder shall assist and cooperate with Owner to prepare Agreement and shall execute Agreement and return it to Owner within seven days following its presentation.
004113 - 1
DOCUMENT 00 41 13
BID FORM - STIPULATED SUM
Project: Marquette Alger Regional Education Service Agency Office Improvements
Owner: Marquette-Alger RESA 321 E Ohio Street Marquette, Michigan 49855
Date:
Submitted by:
(Firm name and address)
(Telephone Number)
1. OFFER
1.1 Having examined the Place of The Work and all matters referred to in the Instructions to Bidders and the Contract Documents prepared by U.P. Engineers and Architects, Inc., Architect for the above mentioned project, we, the undersigned, hereby offer to enter into a Contract to perform the Work for the Bid Sum of:
$ , ( dollars), in lawful money of the United States of America.
- We have included the Bid Bond as required by the Instruction to Bidders.
- All applicable federal taxes are included and State of Michigan taxes are included in the Bid.
1.2 VALUE OF ROOFING: Included in the above is the cost of re-roofing, at the sum of
$___________________(___________________________________________dollars).
a. Unit Price to Remove and Replace Blocking and Nailers:
As directed by Architect upon discovery of damaged materials, provide all labor, materials, tools and equipment required to remove and replace damaged existing blocking and nailers.
Match existing material.
Unit Price: $ ( dollars), per Board foot.
b. Unit Price to Remove and Replace Insulation:
As directed by Architect upon discovery of damaged materials, provide all labor, materials, tools and equipment required to remove and replace damaged existing insulation with matching thickness of specified material. INCLUDE 100 s.f. of insulation removed and replaced in Base Bid.
Unit Price: $ ( dollars), per s.f. of 2” thickness.
004113 - 2
1.3 VALUE OF HVAC: Included in the above is the cost of new HVAC systems, at the sum of
1.4 VALUE OF WINDOWS: Included in the above is the cost of replacing windows and window treatments, at the sum of
1.5 VALUE OF INTERIOR RENOVATIONS: Included in the above is the cost of interior office renovations, at the sum of
1.6 VALUE OF FLOORING: Included in the above is the cost of replacing carpeting, at the sum of
1.7 VALUE OF FIRE ALARM: Included in the above is the cost of revising the existing fire alarm system, at the sum of
1.8 ALTERNATES
Alternate No. 1, Renovate Offices 180-180.4 of Enlarged Plan A. (Circle ADD / DEDUCT )
$ ( dollars).
2. ACCEPTANCE
This offer shall be open to acceptance and irrevocable for forty-five days from the bid closing date.
If this bid is accepted by the Owner within the time period stated above, we will:
- Execute the Agreement within seven days of receipt of Notice of Award.
- Furnish the required bonds at the time of the execution of the Agreement.
- Commence work in conformance with requirements found in Instructions to Bidders.
If this bid is accepted within the time stated, and we fail to commence the Work or we fail to provide the required bonds, the bid bond shall be forfeited as damages to the Owner by reason of our failure.
3. CONTRACT TIME
If this Bid is accepted, we will Complete Work within the time specified in Section 01 10 00.
Bidder agrees to pay as liquidated damages the sum of $300 for each calendar day thereafter as provided in Article 3 of the Contract.
4. CHANGES TO THE WORK
004113 - 3
On Work added to the Contract, changes in the Work will be net cost plus a percentage fee of ______ percent overhead and profit on the net cost of our own Work, and _____ percent on the gross cost of Work performed by any Subcontractor.
On Work deleted from the Contract, our credit to the Owner shall be the approved net cost plus ______percent of the overhead and profit percentage noted above.
5. ADDENDA
The following Addenda have been received. The modifications to the Bid Documents noted below have been considered and all costs are included in the Bid Sum.
Addendum # Dated
6. SUBCONTRACTORS
The following firms have submitted costs for their portion of the Work, and it is the intent of this Contractor to enter into a Subcontractor agreement if we are awarded the Work:
Roofing:________________________________
Sprinkler System:
Plumbing/HVAC:
Electrical:
7. APPENDICES
The Bid Bond documents are attached to and made a condition of the Bid
8. BID FORM SIGNATURES
(Seal)
The Corporate Seal of:
(Bidder - print the full name of your firm) was hereunto affixed in the presence of:
(Authorized signing officer) (Title)
If the Bid is a joint venture or partnership, add additional forms of execution for each member of the joint venture in the appropriate form or forms as above.
Agreement Form - AIA (Single-Prime Contract)
00 52 14 - 1
SECTION 00 52 14 - AGREEMENT FORM - AIA STIPULATED SUM (SINGLE-PRIME CONTRACT)
1.1 SUMMARY
A. Document Includes:
1. Agreement.
2. General Conditions.
1.2 DOCUMENTS
A. Basis of Agreement between Owner and Contractor: AIA Document A105 – 2017, Standard
Form of Agreement between Owner and Contractor.
AIA
Document A101TM – 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 14:47:21 on 02/16/2017 under Order No. 8252420293 which expires on 07/14/2017, and is not for resale.
User Notes: (3B9ADA16)
ADDITIONS AND DELETIONS:
The author of this document has added information needed for its completion.
The author may also have revised the text of the original AIA standard form.
An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.
This document has important legal consequences.
Consultation with an attorney is encouraged with respect to its completion or modification.
AIA Document A201™–2007, General Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.
ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.
AGREEMENT made as of the « » day of « » in the year « » (In words, indicate day, month and year.)
BETWEEN the Owner:
(Name, legal status, address and other information)
«Marquette-Alger RESA»« » «321 E Ohio Street Marquette, Michigan 49855» «Telephone Number: (906) 226-5106» and the Contractor:
(Name, legal status, address and other information) for the following Project:
(Name, location and detailed description)
«Marquette Alger Regional Education Service Agency Office Improvements» «321 E Ohio Street Marquette, Michigan 49855» « Replace building roof, HVAC systems, existing windows and window treatments.
Renovate flooring finish throughout building, and renovate office spaces including metal stud, drywall, HVAC, electrical and finishes. »
The Architect:
(Name, legal status, address and other information)
«U.P. Engineers & Architects, Inc.»« » «424 South Pine Street Ishpeming, MI 49849» «Telephone Number: (906) 485-1011» «Fax Number: (906) 485-1013»
The Owner and Contractor agree as follows.
AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 14:47:21 on 02/16/2017 under Order No. 8252420293 which expires on 07/14/2017, and is not for resale.
TABLE OF ARTICLES
1 THE CONTRACT DOCUMENTS
2 THE WORK OF THIS CONTRACT
3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
4 CONTRACT SUM
5 PAYMENTS
6 DISPUTE RESOLUTION
7 TERMINATION OR SUSPENSION
8 MISCELLANEOUS PROVISIONS
9 ENUMERATION OF CONTRACT DOCUMENTS
10 INSURANCE AND BONDS
ARTICLE 1 THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9.
ARTICLE 2 THE WORK OF THIS CONTRACT
The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others.
ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
§ 3.1 The date of commencement of the Work shall be the date of this Agreement unless a different date is stated below or provision is made for the date to be fixed in a notice to proceed issued by the Owner.
(Insert the date of commencement if it differs from the date of this Agreement or, if applicable, state that the date will be fixed in a notice to proceed.)
If, prior to the commencement of the Work, the Owner requires time to file mortgages and other security interests, the Owner’s time requirement shall be as follows:
§ 3.2 The Contract Time shall be measured from the date of commencement.
§ 3.3 The Contractor shall achieve Substantial Completion of the entire Work not later than «» ( «» ) days from the date of commencement, or as follows:
AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 14:47:21 on 02/16/2017 under Order No. 8252420293 which expires on 07/14/2017, and is not for resale.
(Insert number of calendar days. Alternatively, a calendar date may be used when coordinated with the date of commencement. If appropriate, insert requirements for earlier Substantial Completion of certain portions of the Work.)
«The Contractor shall achieve Substantial Completion of the entire Work not later than November 14, 2021.»
Portion of Work Substantial Completion Date
, subject to adjustments of this Contract Time as provided in the Contract Documents.
(Insert provisions, if any, for liquidated damages relating to failure to achieve Substantial Completion on time or for bonus payments for early completion of the Work.)
«Liquidated Damages, in the amount of $300 per calendar day, will be deducted from the Contract Sum for late com pletion past the contractual date.»
ARTICLE 4 CONTRACT SUM
§ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract. The Contract Sum shall be « » ($ « » ), subject to additions and deductions as provided in the Contract Documents.
§ 4.2 The Contract Sum is based upon the following alternates, if any, which are described in the Contract Documents and are hereby accepted by the Owner:
(State the numbers or other identification of accepted alternates. If the bidding or proposal documents permit the Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other alternates showing the amount for each and the date when that amount expires.)
§ 4.3 Unit prices, if any:
(Identify and state the unit price; state quantity limitations, if any, to which the unit price will be applicable.)
Item Units and Limitations Price Per Unit ($0.00)
§ 4.4 Allowances included in the Contract Sum, if any:
(Identify allowance and state exclusions, if any, from the allowance price.)
Item Price
ARTICLE 5 PAYMENTS
§ 5.1 PROGRESS PAYMENTS
§ 5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.
§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows:
§ 5.1.3 Provided that an Application for Payment is received by the Architect not later than the « » day of a month, the Owner shall make payment of the certified amount to the Contractor not later than the « » day of the « » month.
If an Application for Payment is received by the Architect after the application date fixed above, payment shall be made by the Owner not later than « » ( « » ) days after the Architect receives the Application for Payment.
(Federal, state or local laws may require payment within a certain period of time.)
AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 14:47:21 on 02/16/2017 under Order No. 8252420293 which expires on 07/14/2017, and is not for resale.
§ 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect may require. This schedule, unless objected to by the Architect, shall be used as a basis for reviewing the Contractor’s Applications for Payment.
§ 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment.
§ 5.1.6 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
.1 Take that portion of the Contract Sum properly allocable to completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Contract Sum allocated to that portion of the Work in the schedule of values, less retainage of « » percent ( « » %).
Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute shall be included as provided in Section 7.3.9 of AIA Document A201™–2007, General Conditions of the Contract for Construction;
.2 Add that portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction (or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing), less retainage of « » percent ( « » %);
.3 Subtract the aggregate of previous payments made by the Owner; and
.4 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Section 9.5 of AIA Document A201–2007.
§ 5.1.7 The progress payment amount determined in accordance with Section 5.1.6 shall be further modified under the following circumstances:
.1 Add, upon Substantial Completion of the Work, a sum sufficient to increase the total payments to the full amount of the Contract Sum, less such amounts as the Architect shall determine for incomplete Work, retainage applicable to such work and unsettled claims; and (Section 9.8.5 of AIA Document A201–2007 requires release of applicable retainage upon Substantial Completion of Work with consent of surety, if any.)
.2 Add, if final completion of the Work is thereafter materially delayed through no fault of the Contractor, any additional amounts payable in accordance with Section 9.10.3 of AIA Document A201–2007.
§ 5.1.8 Reduction or limitation of retainage, if any, shall be as follows:
(If it is intended, prior to Substantial Completion of the entire Work, to reduce or limit the retainage resulting from the percentages inserted in Sections 5.1.6.1 and 5.1.6.2 above, and this is not explained elsewhere in the Contract Documents, insert here provisions for such reduction or limitation.)
§ 5.1.9 Except with the Owner’s prior approval, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site.
§ 5.2 FINAL PAYMENT
§ 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Contractor when
.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct Work as provided in Section 12.2.2 of AIA Document A201–2007, and to satisfy other requirements, if any, which extend beyond final payment; and
.2 a final Certificate for Payment has been issued by the Architect.
§ 5.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 days after the issuance of the Architect’s final Certificate for Payment, or as follows:
AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 14:47:21 on 02/16/2017 under Order No. 8252420293 which expires on 07/14/2017, and is not for resale.
ARTICLE 6 DISPUTE RESOLUTION
§ 6.1 INITIAL DECISION MAKER
The Architect will serve as Initial Decision Maker pursuant to Section 15.2 of AIA Document A201–2007, unless the parties appoint below another individual, not a party to this Agreement, to serve as Initial Decision Maker.
(If the parties mutually agree, insert the name, address and other contact information of the Initial Decision Maker, if other than the Architect.)
§ 6.2 BINDING DISPUTE RESOLUTION
For any Claim subject to, but not resolved by, mediation pursuant to Section 15.3 of AIA Document A201–2007, the method of binding dispute resolution shall be as follows:
(Check the appropriate box. If the Owner and Contractor do not select a method of binding dispute resolution below, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be resolved by litigation in a court of competent jurisdiction.)
[ « » ] Arbitration pursuant to Section 15.4 of AIA Document A201–2007
[ « » ] Litigation in a court of competent jurisdiction
[ « » ] Other (Specify)
ARTICLE 7 TERMINATION OR SUSPENSION
§ 7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201–2007.
§ 7.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201–2007.
ARTICLE 8 MISCELLANEOUS PROVISIONS
§ 8.1 Where reference is made in this Agreement to a provision of AIA Document A201–2007 or another Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents.
§ 8.2 Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located.
(Insert rate of interest agreed upon, if any.)
§ 8.3 The Owner’s representative:
(Name, address and other information)
«Anthony Bertucci» «321 E Ohio Street Marquette, Michigan 49855» «Telephone Number: (906) 226-5106»
«Email Address: abertucci@maresa.org»
AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 14:47:21 on 02/16/2017 under Order No. 8252420293 which expires on 07/14/2017, and is not for resale.
§ 8.4 The Contractor’s representative:
(Name, address and other information)
§ 8.5 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days written notice to the other party.
§ 8.6 Other provisions:
« Contractor responsible for obtaining a performance bond for the project »
ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS
§ 9.1 The Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated in the sections below.
§ 9.1.1 The Agreement is this executed AIA Document A101–2007, Standard Form of Agreement Between Owner and Contractor.
§ 9.1.2 The General Conditions are AIA Document A201–2007, General Conditions of the Contract for Construction.
§ 9.1.3 The Supplementary and other Conditions of the Contract:
Document Title Date Pages
§ 9.1.4 The Specifications:
(Either list the Specifications here or refer to an exhibit attached to this Agreement.)
« Marquette Area Regional Education Service Agency Improvements »
Section Title Date Pages « » Bidding Documents for
MARESA Office Improvements
3/9/21 58
§ 9.1.5 The Drawings:
(Either list the Drawings here or refer to an exhibit attached to this Agreement.)
« Marquette Area Regional Education Service Agency Improvements »
Number Title Date « 29 Pages » MARESA
Improvements 3/05/2021
§ 9.1.6 The Addenda, if any:
Number Date Pages
Portions of Addenda relating to bidding requirements are not part of the Contract Documents unless the bidding requirements are also enumerated in this Article 9.
AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 14:47:21 on 02/16/2017 under Order No. 8252420293 which expires on 07/14/2017, and is not for resale.
§ 9.1.7 Additional documents, if any, forming part of the Contract Documents:
.1 AIA Document E201™–2007, Digital Data Protocol Exhibit, if completed by the parties, or the following:
«n/a»
.2 Other documents, if any, listed below:
(List here any additional documents that are intended to form part of the Contract Documents. AIA Document A201–2007 provides that bidding requirements such as advertisement or invitation to bid, Instructions to Bidders, sample forms and the Contractor’s bid are not part of the Contract Documents unless enumerated in this Agreement. They should be listed here only if intended to be part of the Contract Documents.)
ARTICLE 10 INSURANCE AND BONDS
The Contractor shall purchase and maintain insurance and provide bonds as set forth in Article 11 of AIA Document A201–2007.
(State bonding requirements, if any, and limits of liability for insurance required in Article 11 of AIA Document A201–2007.)
Type of insurance or bond Limit of liability or bond amount ($0.00)
This Agreement entered into as of the day and year first written above.
OWNER (Signature) CONTRACTOR (Signature)
«Anthony Bertucci»«Associate Superintendent» « »« » (Printed name and title) (Printed name and title)
AIA
Document A201
TM
– 2007
General Conditions of the Contract for Construction
AIA Document A201™ – 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The
American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International
Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 14:53:27 on
02/16/2017 under Order No. 8252420293 which expires on 07/14/2017, and is not for resale.
User Notes: (3B9ADA1A)
ADDITIONS AND DELETIONS:
The author of this document has added information needed for its completion.
The author may also have revised the text of the original AIA standard form.
An Additions and Deletions
Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.
This document has important legal consequences.
Consultation with an attorney is encouraged with respect to its completion or modification.
ELECTRONIC COPYING of any portion of this AIA Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.
for the following PROJECT:
(Name and location or address)
«Marquette Alger Regional Education Service Agency Office Improvements»
«321 E Ohio Street
Marquette, Michigan 49855»
THE OWNER:
(Name, legal status and address)
«Marquette-Alger RESA»« »
«321 E Ohio Street
Marquette, Michigan 49855»
THE ARCHITECT:
(Name, legal status and address)
«U.P. Engineers & Architects, Inc.»« »
«424 South Pine Street
Ishpeming, Michigan 49849»
TABLE OF ARTICLES
1 GENERAL PROVISIONS
2 OWNER
3 CONTRACTOR
4 ARCHITECT
5 SUBCONTRACTORS
6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS
7 CHANGES IN THE WORK
8 TIME
9 PAYMENTS AND COMPLETION
10 PROTECTION OF PERSONS AND PROPERTY
11 INSURANCE AND BONDS
12 UNCOVERING AND CORRECTION OF WORK
13 MISCELLANEOUS PROVISIONS
14 TERMINATION OR SUSPENSION OF THE CONTRACT
15 CLAIMS AND DISPUTES
AIA Document A201™ – 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The
American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International
Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 14:53:27 on
INDEX
(Topics and numbers in bold are section headings.)
Acceptance of Nonconforming Work 9.6.6, 9.9.3, 12.3
Acceptance of Work
9.6.6, 9.8.2, 9.9.3, 9.10.1, 9.10.3, 12.3
Access to Work 3.16, 6.2.1, 12.1
Accident Prevention
Acts and Omissions
3.2, 3.3.2, 3.12.8, 3.18, 4.2.3, 8.3.1, 9.5.1, 10.2.5, 10.2.8, 13.4.2, 13.7, 14.1, 15.2
Addenda
1.1.1, 3.11
Additional Costs, Claims for
3.7.4, 3.7.5, 6.1.1, 7.3.7.5, 10.3, 15.1.4
Additional Inspections and Testing 9.4.2, 9.8.3, 12.2.1, 13.5
Additional Insured
11.1.4
Additional Time, Claims for 3.2.4, 3.7.4, 3.7.5, 3.10.2, 8.3.2, 15.1.5
Administration of the Contract 3.1.3, 4.2, 9.4, 9.5
Advertisement or Invitation to Bid
1.1.1
Aesthetic Effect
4.2.13
Allowances 3.8, 7.3.8
All-risk Insurance
11.3.1, 11.3.1.1
Applications for Payment 4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5.1, 9.6.3, 9.7, 9.10, 11.1.3
Approvals
2.1.1, 2.2.2, 2.4, 3.1.3, 3.10.2, 3.12.8, 3.12.9, 3.12.10, 4.2.7, 9.3.2, 13.5.1
Arbitration 8.3.1, 11.3.10, 13.1, 15.3.2, 15.4
ARCHITECT
Architect, Definition of
4.1.1 Architect, Extent of Authority
2.4, 3.12.7, 4.1, 4.2, 5.2, 6.3, 7.1.2, 7.3.7, 7.4, 9.2, 9.3.1, 9.4, 9.5, 9.6.3, 9.8, 9.10.1, 9.10.3, 12.1, 12.2.1, 13.5.1, 13.5.2, 14.2.2, 14.2.4, 15.1.3, 15.2.1
Architect, Limitations of Authority and
Responsibility
2.1.1, 3.12.4, 3.12.8, 3.12.10, 4.1.2, 4.2.1, 4.2.2, 4.2.3, 4.2.6, 4.2.7, 4.2.10, 4.2.12, 4.2.13, 5.2.1, 7.4, 9.4.2, 9.5.3, 9.6.4, 15.1.3, 15.2
Architect’s Additional Services and Expenses
2.4, 11.3.1.1, 12.2.1, 13.5.2, 13.5.3, 14.2.4
Architect’s Administration of the Contract
3.1.3, 4.2, 3.7.4, 15.2, 9.4.1, 9.5
Architect’s Approvals
2.4, 3.1.3, 3.5, 3.10.2, 4.2.7
Architect’s Authority to Reject Work
3.5, 4.2.6, 12.1.2, 12.2.1
Architect’s Copyright
1.1.7, 1.5
Architect’s Decisions
3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 4.2.14, 6.3, 7.3.7, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4.1, 9.5, 9.8.4, 9.9.1, 13.5.2, 15.2, 15.3
Architect’s Inspections
3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 13.5
Architect’s Instructions
3.2.4, 3.3.1, 4.2.6, 4.2.7, 13.5.2
Architect’s Interpretations
4.2.11, 4.2.12
Architect’s Project Representative
4.2.10
Architect’s Relationship with Contractor
1.1.2, 1.5, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.7.5, 3.9.2, 3.9.3, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.2, 4.1.3, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3.7, 12, 13.4.2, 13.5, 15.2
Architect’s Relationship with Subcontractors
1.1.2, 4.2.3, 4.2.4, 4.2.6, 9.6.3, 9.6.4, 11.3.7
Architect’s Representations
9.4.2, 9.5.1, 9.10.1
Architect’s Site Visits
3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.5
Asbestos
10.3.1
Attorneys’ Fees
3.18.1, 9.10.2, 10.3.3
Award of Separate Contracts
6.1.1, 6.1.2
Award of Subcontracts and Other Contracts for
Portions of the Work 5.2 Basic Definitions 1.1 Bidding Requirements
1.1.1, 5.2.1, 11.4.1
Binding Dispute Resolution
9.7, 11.3.9, 11.3.10, 13.1, 15.2.5, 15.2.6.1, 15.3.1, 15.3.2, 15.4.1
Boiler and Machinery Insurance 11.3.2 Bonds, Lien
7.3.7.4, 9.10.2, 9.10.3
Bonds, Performance, and Payment 7.3.7.4, 9.6.7, 9.10.3, 11.3.9, 11.4
AIA Document A201™ – 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The
American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International
Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 14:53:27 on
Building Permit
3.7.1
Capitalization 1.3 Certificate of Substantial Completion
9.8.3, 9.8.4, 9.8.5
Certificates for Payment 4.2.1, 4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 14.1.1.3, 14.2.4, 15.1.3
Certificates of Inspection, Testing or Approval
13.5.4
Certificates of Insurance
9.10.2, 11.1.3
Change Orders 1.1.1, 2.4, 3.4.2, 3.7.4, 3.8.2.3, 3.11, 3.12.8, 4.2.8, 5.2.3, 7.1.2, 7.1.3, 7.2, 7.3.2, 7.3.6, 7.3.9, 7.3.10, 8.3.1, 9.3.1.1, 9.10.3, 10.3.2, 11.3.1.2, 11.3.4, 11.3.9, 12.1.2, 15.1.3
Change Orders, Definition of
7.2.1
CHANGES IN THE WORK
2.2.1, 3.11, 4.2.8, 7, 7.2.1, 7.3.1, 7.4, 8.3.1, 9.3.1.1, 11.3.9
Claims, Definition of
15.1.1
CLAIMS AND DISPUTES
3.2.4, 6.1.1, 6.3, 7.3.9, 9.3.3, 9.10.4, 10.3.3, 15, 15.4
Claims and Timely Assertion of Claims
15.4.1
Claims for Additional Cost 3.2.4, 3.7.4, 6.1.1, 7.3.9, 10.3.2, 15.1.4
Claims for Additional Time 3.2.4, 3.7.4, 6.1.1, 8.3.2, 10.3.2, 15.1.5
Concealed or Unknown Conditions, Claims for 3.7.4 Claims for Damages
3.2.4, 3.18, 6.1.1, 8.3.3, 9.5.1, 9.6.7, 10.3.3, 11.1.1, 11.3.5, 11.3.7, 14.1.3, 14.2.4, 15.1.6
Claims Subject to Arbitration
15.3.1, 15.4.1
Cleaning Up 3.15, 6.3
Commencement of the Work, Conditions Relating to
2.2.1, 3.2.2, 3.4.1, 3.7.1, 3.10.1, 3.12.6, 5.2.1, 5.2.3, 6.2.2, 8.1.2, 8.2.2, 8.3.1, 11.1, 11.3.1, 11.3.6, 11.4.1, 15.1.4
Commencement of the Work, Definition of
8.1.2 Communications Facilitating Contract
Administration 3.9.1, 4.2.4
Completion, Conditions Relating to
3.4.1, 3.11, 3.15, 4.2.2, 4.2.9, 8.2, 9.4.2, 9.8, 9.9.1, 9.10, 12.2, 13.7, 14.1.2
COMPLETION, PAYMENTS AND
Completion, Substantial
4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 13.7
Compliance with Laws
1.6, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 4.1.1, 9.6.4, 10.2.2, 11.1, 11.3, 13.1, 13.4, 13.5.1, 13.5.2, 13.6, 14.1.1, 14.2.1.3, 15.2.8, 15.4.2, 15.4.3
Concealed or Unknown Conditions
3.7.4, 4.2.8, 8.3.1, 10.3
Conditions of the Contract
1.1.1, 6.1.1, 6.1.4
Consent, Written
3.4.2, 3.7.4, 3.12.8, 3.14.2, 4.1.2, 9.3.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3, 11.3.1, 13.2, 13.4.2, 15.4.4.2
Consolidation or Joinder 15.4.4
CONSTRUCTION BY OWNER OR BY
SEPARATE CONTRACTORS
1.1.4, 6
Construction Change Directive, Definition of
7.3.1 Construction Change Directives 1.1.1, 3.4.2, 3.12.8, 4.2.8, 7.1.1, 7.1.2, 7.1.3, 7.3, 9.3.1.1
Construction Schedules, Contractor’s
3.10, 3.12.1, 3.12.2, 6.1.3, 15.1.5.2
Contingent Assignment of Subcontracts 5.4, 14.2.2.2
Continuing Contract Performance 15.1.3 Contract, Definition of
1.1.2
CONTRACT, TERMINATION OR
SUSPENSION OF THE
5.4.1.1, 11.3.9, 14
Contract Administration
3.1.3, 4, 9.4, 9.5
Contract Award and Execution, Conditions Relating to
3.7.1, 3.10, 5.2, 6.1, 11.1.3, 11.3.6, 11.4.1
Contract Documents, Copies Furnished and Use of
1.5.2, 2.2.5, 5.3
Contract Documents, Definition of
1.1.1 Contract Sum 3.7.4, 3.8, 5.2.3, 7.2, 7.3, 7.4, 9.1, 9.4.2, 9.5.1.4, 9.6.7, 9.7, 10.3.2, 11.3.1, 14.2.4, 14.3.2, 15.1.4, 15.2.5
Contract Sum, Definition of
9.1 Contract Time
3.7.4, 3.7.5, 3.10.2, 5.2.3, 7.2.1.3, 7.3.1, 7.3.5, 7.4, 8.1.1, 8.2.1, 8.3.1, 9.5.1, 9.7, 10.3.2, 12.1.1, 14.3.2, 15.1.5.1, 15.2.5
Contract Time, Definition of
8.1.1
CONTRACTOR
AIA Document A201™ – 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The
American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International
Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 14:53:27 on
Contractor, Definition of
3.1, 6.1.2 Contractor’s Construction Schedules 3.10, 3.12.1, 3.12.2, 6.1.3, 15.1.5.2
Contractor’s Employees
3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3, 11.1.1, 11.3.7, 14.1, 14.2.1.1
Contractor’s Liability Insurance 11.1 Contractor’s Relationship with Separate Contractors and Owner’s Forces
3.12.5, 3.14.2, 4.2.4, 6, 11.3.7, 12.1.2, 12.2.4
Contractor’s Relationship with Subcontractors
1.2.2, 3.3.2, 3.18.1, 3.18.2, 5, 9.6.2, 9.6.7, 9.10.2, 11.3.1.2, 11.3.7, 11.3.8
Contractor’s Relationship with the Architect
1.1.2, 1.5, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.3, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3.7, 12, 13.5, 15.1.2, 15.2.1
Contractor’s Representations
3.2.1, 3.2.2, 3.5, 3.12.6, 6.2.2, 8.2.1, 9.3.3, 9.8.2
Contractor’s Responsibility for Those Performing the
Work
3.3.2, 3.18, 5.3, 6.1.3, 6.2, 9.5.1, 10.2.8
Contractor’s Review of Contract Documents
3.2
Contractor’s Right to Stop the Work
9.7
Contractor’s Right to Terminate the Contract
14.1, 15.1.6
Contractor’s Submittals
3.10, 3.11, 3.12.4, 4.2.7, 5.2.1, 5.2.3, 9.2, 9.3, 9.8.2, 9.8.3, 9.9.1, 9.10.2, 9.10.3, 11.1.3, 11.4.2
Contractor’s Superintendent
3.9, 10.2.6
Contractor’s Supervision and Construction
Procedures
1.2.2, 3.3, 3.4, 3.12.10, 4.2.2, 4.2.7, 6.1.3, 6.2.4, 7.1.3, 7.3.5, 7.3.7, 8.2, 10, 12, 14, 15.1.3
Contractual Liability Insurance
11.1.1.8, 11.2
Coordination and Correlation
1.2, 3.2.1, 3.3.1, 3.10, 3.12.6, 6.1.3, 6.2.1
Copies Furnished of Drawings and Specifications
1.5, 2.2.5, 3.11
Copyrights
1.5, 3.17
Correction of Work
2.3, 2.4, 3.7.3, 9.4.2, 9.8.2, 9.8.3, 9.9.1, 12.1.2, 12.2
Correlation and Intent of the Contract Documents 1.2 Cost, Definition of
7.3.7 Costs
2.4, 3.2.4, 3.7.3, 3.8.2, 3.15.2, 5.4.2, 6.1.1, 6.2.3, 7.3.3.3, 7.3.7, 7.3.8, 7.3.9, 9.10.2, 10.3.2, 10.3.6, 11.3, 12.1.2, 12.2.1, 12.2.4, 13.5, 14
Cutting and Patching 3.14, 6.2.5
Damage to Construction of Owner or Separate
Contractors
3.14.2, 6.2.4, 10.2.1.2, 10.2.5, 10.4, 11.1.1, 11.3, 12.2.4
Damage to the Work
3.14.2, 9.9.1, 10.2.1.2, 10.2.5, 10.4, 11.3.1, 12.2.4
Damages, Claims for
3.2.4, 3.18, 6.1.1, 8.3.3, 9.5.1, 9.6.7, 10.3.3, 11.1.1, 11.3.5, 11.3.7, 14.1.3, 14.2.4, 15.1.6
Damages for Delay
6.1.1, 8.3.3, 9.5.1.6, 9.7, 10.3.2
Date of Commencement of the Work, Definition of
8.1.2 Date of Substantial Completion, Definition of
8.1.3 Day, Definition of
8.1.4 Decisions of the Architect
3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 15.2, 6.3, 7.3.7, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4, 9.5.1, 9.8.4, 9.9.1, 13.5.2, 14.2.2, 14.2.4, 15.1, 15.2
Decisions to Withhold Certification 9.4.1, 9.5, 9.7, 14.1.1.3
Defective or Nonconforming Work, Acceptance, Rejection and Correction of
2.3, 2.4, 3.5, 4.2.6, 6.2.5, 9.5.1, 9.5.2, 9.6.6, 9.8.2, 9.9.3, 9.10.4, 12.2.1
Definitions
1.1, 2.1.1, 3.1.1, 3.5, 3.12.1, 3.12.2, 3.12.3, 4.1.1, 15.1.1, 5.1, 6.1.2, 7.2.1, 7.3.1, 8.1, 9.1, 9.8.1
Delays and Extensions of Time 3.2, 3.7.4, 5.2.3, 7.2.1, 7.3.1, 7.4, 8.3, 9.5.1, 9.7, 10.3.2, 10.4, 14.3.2, 15.1.5, 15.2.5
Disputes
6.3, 7.3.9, 15.1, 15.2
Documents and Samples at the Site 3.11 Drawings, Definition of