This document is a Justification for an Exception to Fair Opportunity (J&A) for the Department of the Navy's Mid-Atlantic Regional Maintenance Center. The document seeks to award additional work to an unnamed contractor for maintenance, modernization, and repair of a naval vessel during a Continuous Maintenance Availability (CMAV) scheduled from April 21 to May 30, 2025. The justification cites urgent operational needs, stating that providing fair opportunity to other contractors would result in unacceptable delays of approximately 60 days, potentially disrupting the ship's scheduled deployment.
The key details include a critical timeline where the work must begin by April 21, 2025, and be completed by May 30, 2025. The contractor is described as the only company capable of performing the work under such short notice, enabling the vessel to meet its fleet mission commitments. The Contracting Officer has determined the anticipated costs to be fair and reasonable, based on historical data, an Independent Government Estimate, and the Project Manager's technical knowledge. The document emphasizes the urgency of the work and commits to reviewing future acquisitions to promote full and open competition where possible.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
J&A Number: N50054-25-125
5. RATIONALE JUSTIFYING THE EXCEPTION TO FAIR OPPORUNITY
was awarded delivery order on 11 March 2025 to prepare for and accomplish maintenance, modernization and repair to the during a Continuous
Maintenance Availability (CMAV) that begins on April 21, 2025. The Work Completion Date for 5A1 CMAV is May 30, 2025.
is the only company that is able to perform this work under such short notice, during the current CMAV, allowing to meet its fleet mission commitments.
Providing a fair opportunity to be considered to other awardees under the multiple award delivery order contract would result in unacceptable delays.
The certifying technical and requirements personnel have verified the Government’s minimum needs. This must begin by April 21, 2025, and must be completed by May 30, 2025. has no other availabilities on schedule to complete the required work and will no longer be mission ready nor mission capable.
Due to the ship’s schedule and the duration required for the repairs, using the fair opportunity process would result in unacceptable delays. A competitive award would take approximately 60 days, which would not be allow for the viable work package integration of this urgent new work. Any delay would cause a disruption to ongoing Fleet scheduled maintenance repairs, which would cause an extension to .
The delay required for a competitive award would result in serious injury to the Government, as the ship will be unable to perform its previously scheduled deployment. is the only company that is able to perform this work under such short notice during the current CMAV, allowing the to meet its fleet mission commitments.
6. DETERMINATION OF FAIR AND REASONABLECOSTS
The Contracting Officer has determined that the anticipated cost to the Government for the supplies/services covered by the J&A will be fair and reasonable. The estimated cost of this work item is based upon historical data as well as the Independent Government Estimate (IGE) and the
Project Manager’s (PM) technical knowledge associated with the estimated man hours and material costs to complete this work. Additionally, the contractor’s fully burdened ship repair labor rate and material burden rate were determined to be fair and reasonable at time of contract and delivery order award. The supported information provided should be sufficient to support the fair and reasonable cost determination of the procurement.
7. ACTIONS TO REMOVE BARRIERS TOCOMPETITION
The critical nature of the work required that it be started immediately. Future acquisitions for similar work will be reviewed by the Contracting Officer on a case by case basis to promote the use of full and open competition in the acquisition process where possible and practicable in accordance with the FAR Part 6. In addition, a copy of the change(s) covered by this justification will be forwarded to Code 200, Planning and
Engineering, for consideration of similar work requirements in future solicitations.