AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Reason for ammendment is to clarify the trash containers required are( 8 yard trash containers). Change Brittany Jackson email to brittany.jackson1@usmc.mil

1. CONTRACT ID CODE PAGE OF PAGES

1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 09-Mar-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X M6700421Q1009

X 9B. DATED (SEE ITEM 11)

05-Mar-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-Mar-2021

CODE

USMC BLOUNT ISLAND COMMAND

ATTN: DUANE CHASE

5880 CHANNEL VIEW BLVD

JACKSONVILLE FL 32226-3404

M67004 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

M6700421Q1009

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SUPPLIES OR SERVICES AND PRICES

CLIN 0004

The CLIN extended description has changed from:

Contractor shall provide four dumpsters and perform services in accordance with the Performance Work Statement

(PWS).

To:

Contractor shall provide five ( 8 yard trash containers/ dumpsters and perform services in accordance with the

Performance Work Statement (PWS).

The following have been modified:

PERFORMANCE WORK STATEMENT

Performance Work Statement

Maritime Prepositioning Force Exercise (MPFEX) 2021

Marine Corps Support Facility Blount Island

1. GENERAL

1.1 Description of Services/Introduction: The Contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, direction, and other items necessary to perform Life Support Services as defined in this Performance Work Statement.

1.2 Background: Blount Island Command (BICmd) is a United States Marine Corps Logistics Command located in

Jacksonville, Florida and routinely hosts Maritime Prepositioning Force Exercises. Such exercises require the sustainment of life through the provision of resources. These resources are identified in Section 1.4.

1.3 Objectives: The objective is to provide life support services to approximately 170 personnel with MEF II aboard

Marine Corps Support Facility Blount Island (MCSF-BI) in Jacksonville, FL in support of Maritime Prepositioning

Force Exercise (MPFEX), Dynamic Cape 21.

1.4 Scope: The contractor's responsibilities and tasks are as follows:

1.4.1 Port A Johns Services

1.4.1.1 The Contractor shall execute the following tasks:

1.4.1.1.1 Provide 21 Port a Johns to be staged in four locations. The Port a Johns staging requirements are as follows:

Location 1 - Clamshell 4 (Quantity 7)

Location 2 - Rail Offload Area (Quantity of 2)

Location 3 - S & D Lot (Quantity of 4)

Location 4 - Longshoremen Parking Lot (Quantity of 8)

1.4.1.1.2 Port a Johns shall be clean upon arrival and prepared for use. Port a Johns shall be fully stocked with toilet paper and toilet seat covers. All shall be delivered and operational no later than 8 April 2021.

1.4.1.1.3 Contractor shall pump and clean each port a john at least once daily and ensure each are stocked with toilet paper and toilet seat covers.

1.4.1.1.4 The removal date for the Port a Johns is 29 April 2021.

1.4.2 Hand Wash Stations

1.4.2.1 The Contractor shall execute the following tasks:

1.4.2.1.1 Provide 10 hand wash stations to be staged in three locations. The hand wash stations staging requirements are as follows:

Location 1 - Clamshell 4 (Quantity of 4)

Location 2 - Rail Offload Area (Quantity of 1)

Location 3 - S & D Lot (Quantity of 1)

Location 3 - Longshoremen Parking Lot (Quantity of 4)

1.4.2.1.2 Hand wash stations shall be clean upon arrival, fully stocked with soap and paper towels and prepared for use. All shall be delivered and operational no later than 8 April 2021.

1.4.2.1.3 Contractor shall ensure each hand wash station is fully stocked with water, soap and paper towels at least once daily.

1.4.2.1.4 The removal date for the hand wash stations is 29 April 2021.

1.4.3 Shower Services

1.4.3.1 The Contractor shall execute the following tasks:

1.4.3.1.1 Provide three (7-head shower trailers) to be staged in one location.

1.4.3.1.2 Two shower trailers will be designated for males and one designated for females. Showers shall be clean upon arrival and prepared for use. All shall be delivered and operational no later than 8 April 2021.

1.4.3.2 The Contractor will supply water to the showers. There may be no fire hydrant located directly near the staging area of the showers. This concern may require the Contractor to transport water to the location of the showers. The Contractor may access a fire hydrant on base by first obtaining a permit and meter containing a backflow preventer from JEA. The Contractor may apply for a

Fire Hydrant Permit at:

JEA

21 W. Church Street

Jacksonville, FL 32202

The application fee and permit are at no cost to the Government. Additionally, all metered water will be billed to the Contractor.

1.4.3.3 The hours of operation for the showers is 0500-0900 and 1700-2000.

1.4.3.4 Contractor shall clean showers at least once daily.

1.4.3.5 Contractor must provide a generator to operate showers as one will not be provided. The generator must include a spill-kit and conform to the environmental standards on base. The generator and spill kit are subject to inspection by the Installation Division prior to use.

1.4.3.6 The Contractor is responsible for properly collecting and disposing of gray water. It is NOT to be disposed of onsite.

1.4.3.7 The removal date for the showers is 29 April 2021.

1.4.3 Dumpster Service

1.4.3.1 The Contractor shall provide five ( 8 yard trash containers) to be staged in the following locations no later than 8 April 2021:

Location 1 - Clamshell 4 (Quantity of 3)

Location 2 - S&D Lot (Quantity of 1)

Location 3 - Longshoreman (Quantity of 1)

1.4.3.2 The Contractor shall empty each dumpster twice a week and provide a schedule for trash days and times.

1.4.3.3 The removal date for the dumpsters is 29 April 2021.

1.4.4 Icebox Rental and Ice Supply

1.4.4.1 The Contractor shall provide one icebox to be staged at Clamshell 4.

1.4.4.1.1 The icebox shall be clean upon arrival, prepared for use, and stocked with 10, 10-pound bags of ice. The icebox shall be delivered and operational no later than 8 April 2021.

1.4.4.1.1.1 Contractor shall deliver 10, 10-pound bags of ice weekly, totaling 30 bags, and be prepared to maintain ice stock of (10) bags.

1.4.4.1.2 The removal date for the icebox is 29 April 2021.

1.4.5 Flood Lights

1.4.5.1 The Contractor shall provide a quantity of two flood lights. The flood lights must be capable of a

12-hour run-time and must provide up to five acres of 360-degree illumination.

1.4.5.2 If the flood lights require a generator to power the lights, the Contractor must provide the generator. The generator must include an environmental spill-kit. Both the generator and spill kit are subject to inspection by the Installation Division prior to use.

1.4.5.3 The removal date for the flood lights is 29 April 2021.

1.4 Period of Performance: Except as otherwise defined in this PWS, the period of performance for this effort is 8 April 2021 to 30 April 2021. All items can be delivered and setup as early as 8

April 2021. The Contractor shall remove all items from the base no later than 30 April 2021.

Delay in removal of items is at no cost to the Government.

1.5 Generators, fuel and water will not be provided by the Government and will not be billed to the

Government. Each piece of equipment running on fuel is required to sit on a containment berm to hold fuel and oil if it leaks.

1.6 In the event of inclement weather, the Contractor is responsible for tying down all equipment. The

Government is not responsible for the damage of equipment due to weather. In the event of

Government-caused damages, the Contractor may submit in writing to the Contracting Officer, a

Request for Equitable Adjustment (REA).

1.7 Quality Control: The applicable contract quality requirements are for commercial standards. The

Contractor shall maintain an effective quality control program to ensure services are performed in accordance with this PWS and commercial industry standards. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The

Contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract.

1.8 Base Access: All Contractors and visitors accessing MCSF-BI are subject to a background check.

Persons with felonies or a criminal history may be denied access. All Contractors and visitors must have a valid driver’s license or state issued identification card. All drivers are required to provide the following information:

A valid driver’s license

Current vehicle registration

Current vehicle insurance

Failure to pass a background check and/or furnish the documents listed above will result in base access denial.

SF 1449 CONTINUATION

Any questions regarding the requirements identified herein must be submitted no later than 12:00 p.m. Eastern

Standard Time on March 10, 2021. Questions must be submitted by email to Brittany.Jackson1@usmc.mil, Duane.Chase@usmc.mil and Carbon Copy (Cc) Calvin.Caldwell@usmc.mil. Offerors are responsible for confirming receipt of questions submitted.

mailto:Brittany.Jackson1@usmc.mil mailto:Duane.Chase@usmc.mil mailto:Calvin.Caldwell@usmc.mil

All prices submitted in response to this Request for Quote will be Firm Fixed Price inclusive of all material(s), equipment, services, and transportation, etc. Generators, fuel, and water will not be provided by the Government.

Each generator is required to have an environmental spill kit. All generators and spill kits will be inspected prior to use. Each piece of equipment running on fuel is required to sit on a containment berm to hold fuel and/oil if it leaks.

There may be no fire hydrant located directly near the staging areas and may require the Contractor to transport water to the staging locations. The Contractor may access a fire hydrant on base by obtaining a permit and meter containing a backflow preventer from JEA. The Contractor may apply for a Fire Hydrant Permit at:

JEA | 21 W. Church Street | Jacksonville, FL 32202

The application fee and permit are at no cost to the Government. Additionally, all metered water is billed to the Contractor.

(End of Summary of Changes)