M67001-13-T-1142__AMENDMENT.doc
DOC document 42 KB Posted
- Attached to
- 4 POST FORK LIFT SERVICE LIFT AND INSTALLATION
- Solicitation number
- M67001-13-T-1142
- Issued by
-
United States Marine Corps
About this file
AMENDMENT ISSUED TO REMOVE MANDATORY SITE VISIT FROM SOLICITATION SO THAT ALL QUOTES CAN BE RECEIVED WITHOUT VENDOR'S ATTENDING SITE VISIT.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| M67001-13-T-1142__MHE_LIFT_AS118.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been modified:
BASIS OF AWARD
INSTRUCTIONS TO VENDORS
THIS IS A BRAND NAME OR EQUAL PROCUREMENT FOR A 25,000 LB FORK LIFT SERVICE LIFT AND INSTALLATION. IF YOU ARE QUOTING AN EQUAL, PROVIDE DESCRIPTIVE LITERATURE THAT SHOWS THE PRODUCT IS EQUAL TO THE BRAND NAME.
MFR: MOHAWK RESOURCES
P/N: MODEL FL-25
This procurement is 100% set-aside for small business. All responsible small business sourceS may submit a response which, if timely received, will be considered by the agency.
This procurement is subject to the buy american act. If the product you are quoting on is not american made you must identify the country in which it is made.
“Quotes will be evaluated and ranked according to price, from lowest to highest. The Government reserves the right to evaluate only the technical proposal of the lowest price offeror. Other technical proposals may not be evaluated unless the Government determines the lowest price offeror to be unacceptable or non-responsive. In the event the Government determines the lowest price offeror to be unacceptable, the technical proposal of the next lowest price offeror will be evaluated .This process will continue until a technical proposal is determined to be acceptable.”
Technical acceptability will be based on the demonstrated ability to meet the technical requirements, including the delivery requirement. A mere statement that the vendor “will meet the Government’s requirements” is insufficient; the vendor must demonstrate how it will meet the requirement. Low Price Technically Acceptable (LPTA) will be evaluated on: (1) price; (2) technical specifications; and (3) delivery.
The Government will issue a firm fixed price contract. It is the Government’s intent to award this requirement on an “all or none basis”. The Government intends to award a single contract for this requirement. The requirements are detailed in the below listed line items.
To ensure technical compliance with the requirements, vendor quotes shall include the following information:
a. Vendor Specifications. The vendor’s quote shall provide a description of how the vendor will meet the Government’s requirements as stated above. The manufacturer's name and manufacturer’s complete part numbers of items shall be submitted in the quote. Drawings, product literature, pictures, and description of all quoted items shall be included.
b. Delivery Information. Clearly state if the quoter can meet the requested delivery of 30 days ARO. If not then state delivery date.
(End of Summary of Changes)