M0026422Q0033 Attachment 2 (QASP).pdf
PDF 217 KB Posted
- Attached to
- Pool Dome Services
- Solicitation number
- M00264-22-Q-0033
- Issued by
-
United States Marine Corps
About this file
This document is a Quality Assurance Surveillance Plan (QASP) for solicitation number M00264-22-Q-0033 for pool dome services with the United States Marine Corps. The QASP outlines the methods and performance requirements that will be used to evaluate the contractor's performance in maintaining the Zembiec Pool Facility Winter Dome Enclosure at Henderson Hall. Surveillance methods will include demonstrations, inspections using random or stratified sampling, and periodic, judgmental, or planned sampling. Performance will be evaluated on quality of work, schedule, cost control, management, and regulatory compliance. Key performance characteristics and their associated weights are identified, including quality of work at 85% and schedule, cost control, management, and regulatory compliance each at 5%. Corresponding ratings of excellent, acceptable, or unacceptable will be generated monthly for each performance area based on a scale of 0.1 to 0.99.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| M0026422Q0033.pdf | ||
| M0026422Q0033 Attachment 1 (WD 2015-4281).pdf | ||
| M0026422Q0033 PPQ (Attachment S-1).DOCX | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN
1. Objective. This Quality Assurance Surveillance Plan (QASP) serves as the principal basis for assessing overall performance quality associated with the general upkeep, maintenance, installation, and removal of H&S Bn Henderson
Hall’s Zembiec Pool Facility Winter Dome Enclosure. This document will be used by the Government to assess the effectiveness of the Contractor’s quality with respect to management and technical services provided. This QASP provides the methodology by which the Contractor's performance will be monitored to determine compliance with established performance objectives and to establish performance benchmarks that ensure a quantifiable basis for measuring effectiveness. The plan is designed so that surveillance is limited to that which is necessary to verify the
Contractor is performing management and technical services satisfactorily and relates directly to performance objectives of the performance objectives delineated in the PWS.
2. Government Surveillance. The Technical Point of Contact (TPOC) will serve as the administering authority for this task, and her/his authority will be limited to administering specific technical aspects of the task order as set forth at Inspection and Acceptance. The TPOC will not provide direction that is outside the scope of responsibilities delineated under this task order and will defer any conditional interpretations to the Contracting Officer. The TPOC will:
Maintain a detailed knowledge of the technical requirements of the contract;
Document Contractor performance in accordance with the QASP;
Identify and immediately forward notifications of deficient, or non-compliant performance to the
Contracting Officer;
Approve priorities of support, resources, and associated schedules.
3. Surveillance Methods. Surveillance of Contractor performance is the method used by the Government to determine whether the contractor is effectively and efficiently complying with all terms and conditions of the task order. In addition to statistical analysis, the functional expertise of the Technical Representative plays a critical role in adequately evaluating contractor performance. The below listed methods of surveillance shall be used in the administration of this QASP and the standards are delineated by WBS element in the Performance Requirements
Survey (PRS) table:
Demonstration - A qualification method that is carried out by operation and relies on observable functional operation.
It does not require the use of instrumentation or special test equipment;
Inspections: A qualitative inspections can be accomplished through one of the following techniques:
Random or Stratified Sampling: With random sampling, services are sampled to determine if the level of performance is acceptable. Random sampling works best when the number of instances of the services being performed is very large and a statistically valid sample can be obtained. Stratified sampling focuses on selected parts of total contractor output for sampling. Computer programs may be available to assist in establishing sampling procedures.
Periodic Inspection, Judgmental Inspection or Planned Sampling: This method, sometimes called "planned sampling, " consists of the evaluation of tasks selected on other than a 100% or random basis.
4. Performance Requirements. The performance requirements set forth in this section correspond to the material content cited in the PWS and the evaluation factors at FAR 52.212-2 ADDENDUM. Corresponding ratings will be generated for each of the weighted performance areas and aggregated monthly. The TPOC will track performance using a moving average and reconcile performance with the Contractors Program Mgr. This information will also be shared with the Contracting Officer and any past performance assistance requests:
Performance Characteristic / Wt. RFP Relationship Evaluation Rating1
Quality of Work Performed: .85 Technical Approach
Excellent / Exceeds: >.1
Acceptable / Meets: .95-.99
Unacceptable: <.95
Responsiveness / Planning: .10 Technical Approach
Excellent / Exceeds: >.1
Acceptable / Meets: .95-.99
Unacceptable: <.95
Management & Administration: .05 Technical Approach
Excellent / Exceeds: >.1
Acceptable / Meets: .95-.99
Unacceptable: <.95
1 Numerical values for the adjectival ratings are: >.1 – Excellent – Exceeds standard compliance; .95 - .99 standard compliance – Acceptable; and <.95 – unacceptable.
The criteria that will used to accomplish the evaluation ratings is derived from the RFQ and from the elements of performance determined to be most influential to performance.
PERFORMANCE REQUIREMENTS SURVEY (PRS)
Performance
Objective / PWS Performance Standards
Acceptable Quality
Level Incentive/Remedy
Install Phase
-Contractor installs and raises the Winter
Dome Enclosure meeting requirement established in section 4.
100% of services completed on time and in accordance with regulations and guidelines.
Exceptional-100%
Very Good- 97%
Satisfactory- 95%
Trends of less than acceptable performance could result in reductions in payments at the discretion of the
Contracting Officer.
Removal Phase -Contractor lowers and installs the Winter
Dome Enclosure meeting requirement established in section 4.
100% of services completed on time and in accordance with regulations and guidelines.
Exceptional-100%
Very Good- 97%
Satisfactory- 95%
Trends of less than acceptable performance could result in reductions in payments at the discretion of the
Contracting Officer.
File details come from the government source that posted it. Updated .