About this file
This is a Standard Form 30 Amendment of Solicitation/Modification of Contract issued by the Commanding General, Marine Corps Base Camp Lejeune on Parris Island, South Carolina. Amendment 0001 to solicitation M0026326QD028, dated August 14, 2026, is effective August 27, 2026. The amendment extends the response due date from August 25, 2026 to September 8, 2026 and updates specifications for CLIN 0001 to reflect a brand name procurement requirement. The contracting officer is Nicole Taylor, and all other terms and conditions remain unchanged.
The solicitation requires procurement and installation of one Hobart FT2000 flight-type dishwasher for mess hall facility MH 6012, deck 2, at Parris Island. The equipment specifications are highly detailed and brand-specific, identifying the complete Hobart model with specific configurations including Complete Delime with Delime Notification, dual rinse, blower dryer, steam coil heating, 480v/60/3ph electrical connection, and a total overall length of 22.313 feet. CLIN 0002 covers comprehensive installation services including demolition and removal of existing equipment, assembly and positioning, utility connections (plumbing and electrical within five linear feet), ventilation integration with custom exhaust transition, sanitary sealing with NSF-approved silicone, commissioning with manufacturer startup procedures, and hands-on operator training for Marine Corps personnel. The contract includes an extended six-month warranty covering parts and labor following the standard one-year manufacturer warranty. Installation requires coordination of military base access, security compliance, and site readiness by the Government, with regular work hours Monday through Friday, 7:00 A.M. to 5:00 P.M., requiring two weeks' scheduling notice.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - M0026326QD028.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section A - Solicitation/Contract Form
The following changes have been made:
INFORMATION FROM TO
Response Due Date 25 Aug 2026 08 Sep 2026
M0026326QD0280001
Section C - Description/Specifications/Statement of Work
Miscellaneous text in this section has been modified to:
MH 6012, deck 2, dishwasher #3
CLIN 1- 1 ea DISHWASHER, FLIGHT TYPE
Hobart Flight Type Base model dish machine, Complete Delime with Booster Guard, Drain to unload, Touch Screen Controls with diagnostics and WiFi connectivity, troubleshooting, and SmartConnect App, capless wash arms, an accessible load and unload platforms that open for easy cleaning, 55 gallons of final rinse consumption per hour, with dual rinse, pumped final rinse, insulated hinged doors, cULus, NSF, ENERGY STAR(r), Factory Startup Free for installations within 100 miles (accessible by public roadway) of a Hobart Service Office during normal business hours with appropriate notice; Installation beyond 100 miles or those not accessible by public roadway will be quoted by Service.
1 ea Oversized units with crated shipping dimensions greater or equal to 72" in length and/or 90" in height. If delivery is to a facility without a standard height dock, additional shipping charges will apply depending on the service requested. consult Factory.
1 ea All FT2000 models are to be quoted by Hobart's internal quotation group
1 ea Standard warranty 1Year parts, labor & travel time during normal working hours within the USA
1 ea FT2000CDLYES Complete Delime with Delime Notification, Auto Dispensing and Booster Guard
1 ea FT2000ASR0NO Without Automatic Soil Removal (ASR)
1 ea Hobart FT2000APP0NO Without Adaptive Washing
1 ea Hobart FT2000DWR0NO Without Drain Water Energy Recovery
1 ea FT2000LPF025 Load Platform 2.5' (Total LOAD length is 2.5' load platform + 3' prewash = 5' 10")
1 ea FT2000DRSYES With Dual Rinse
1 ea FT2000CTRSTD Standard NonSplit 8' Center Joined (Wash/Power Rinse/Dual Rinse)
1 ea FT2000UNL085 8.5' Unload Section Non Split
1 ea FT2000TLG22.313 TLG Total Length of load, center & unload section is: 22.313 feet (overall length)
1 ea FT2000DRYYES With Blower Dryer
1 ea FT2000HGTSTD Standard Height 22"h x 29"w Opening, Will fit 18x26 sheet pans and 27" oval trays
1 ea FT2000HTESCL Steam Coil
1 ea FT2000CON001 (1) Service Connection (refer to specifications sheet for rated amps )
1 ea FT2000ELE0CD 480v/60/3ph (HV), for steam heat
1 ea FT2000CBR0NO Without Circuit Breaker
1 ea FT2000BST120 120 Steam Booster
1 ea FT2000PIPSTD Standard Piping
1 ea FT2000DIR0LR Left to right operation
1 ea NOTE: For water of 3grains of hardness or more, Hobart suggests adding a water softener.
1 ea FT2000DRNUNL Drain in Unload ( Field Convertible to Load)
1 ea FT2000DORHNG Hinge doors, all sections
1 ea FT2000SEC0NO Without added security
1 ea FT2000CNVSTD Standard Conveyor
1 ea FT2000ROD4TH With Cross Rods every 4th row, Conv Type A & STD only (for 22.313 ' machine)
1 ea FT2000SEF0NO Without SEF Options
CLIN 2- INSTALLATION
1 ea
SECTION 1: DETAILED SCOPE OF WORK (SOW)
1.1 Demolition & Removal
- Disconnect & De-integrate: Contractor shall safely disconnect all electrical, water, waste, and ventilation connections from the existing machine and its immediate sub-systems.
- Removal & Disposal: Contractor shall completely remove the existing machine from the mess hall facility and place in the backloading dock or supplied dumpster.
- Receipt & Inspection: Contractor shall receive the new equipment shipment at 500A, inspect for uncrate, damages, and verify inventory against the approved submittal list.
- Assembly & Positioning: Contractor shall fully assemble the new machine and rig/set the unit in its final designated operational footprint.
1.3 Fitting, Sealing, & Sanitation
- Leveling: Contractor shall level and secure the unit to ensure proper drainage and operation.
- Sanitary Sealing: Contractor shall apply mildew-resistant, food-grade, high-temperature NSF-approved silicone sealant at all joints, utility penetrations, and gaps between the equipment, walls, and adjacent tables to maintain strict military public health and sanitation compliance.
1.4 Utility Connections
- Connection Boundary: Contractor shall execute all final plumbing (cold water, hot water, and drain lines) and electrical connections from the new equipment to the Owner/GC-provided utility rough-ins, provided those points are located within five (5) linear feet of the unit's final footprint.
- Materials: All final connection materials (e.g., hoses, fittings, shut-off valves, electrical conduit, and whips) shall be provided by the Contractor and must meet local building and military code requirements.
1.5 Ventilation Integration
- Exhaust Connection: Contractor shall utilize a custom-fabricated "pant leg" transition piece to physically connect the dishwasher's exhaust dampers to the existing mechanical exhaust duct stub.
1.6 Owner-Supplied Equipment Installation
- Waste Collectors: Contractor shall install two (2) owner-supplied waste collectors to replace the existing units, ensuring a watertight connection to the drainage system.
1.7 Commissioning & Training
- Startup & Testing: Contractor shall perform manufacturer-authorized startup procedures, verify correct utility inputs (voltage, water pressure, incoming water temperature), test all safety limits/interlocks, and run consecutive test cycles to ensure the unit operates within manufacturer specifications.
- Personnel Training: Contractor shall provide an on-site, hands-on operational and preventative maintenance (PM) training session for designated Marine Corps mess hall personnel.
SECTION 2: ADDITIONAL WARRANTY TERMS
- Extended Warranty Coverage: In addition to the standard manufacturer's warranty, this contract includes an additional six (6) month extended warranty covering both parts and labor. This extension will run consecutively, immediately following the expiration of the standard factory warranty period.
SECTION 3: GC / OWNER SITE READINESS RESPONSIBILITIES
- Prior to the delivery and installation of the food service equipment to the job site, the General Contractor (GC) and/or Base Facilities (Owner) must guarantee that the following site conditions are fully met.
- Notice: Failure to meet these requirements prior to mobilization may result in a formal delay of work, and any subsequent trip charges or standby labor rates will be billed to the GC/Owner at standard rates.
3.1 Utility Provisions
- Model Matching: The GC/Owner must provide all electrical, water, steam (if applicable), and drainage utility rough-ins precisely matching the engineering specifications of the ordered equipment model.
- Utility Upgrade Exclusion: Any required upgrades to the facility's infrastructure (e.g., upgrading circuit breakers, increasing water pressure, installing backflow preventers, or expanding drain pipes to meet flow rates) are the sole responsibility and financial obligation of the GC/Owner.
3.2 Site Access & Security Compliance
- Military Access Control: The GC/Owner is responsible for coordinating and ensuring that all installation personnel are granted timely, unobstructed access to the military base and the mess hall facility. This includes facilitating base passes, DBIDS registration, or escort requirements as dictated by installation security.
3.3 Waste Management
- Debris Disposal: The GC/Owner shall provide an on-site commercial-grade construction dumpster for the immediate disposal of all uncrating materials, wood pallets, cardboard, and minor installation debris.
Regular work hours are Mon. Fri. 7:00 A.M. - 5:00 P.M. No weekends or holidays. Two-week scheduling notice requested.
| IDCode: J |
| Page: 1 |
| Pages: 5 |
| AmendNo: 0001 |
| EffDate: 27 Aug 2026 |
| ReqNo: See Continuation Sheet |
| ProjNo: |
| IssCode: M00263 |
| AdmCode: |
| IssuedBy: COMMANDING GENERAL |
MCRD PARRIS ISLAND, PO BOX 19001
PARRIS ISLAND, SC 29905-9001
UNITED STATES
Nichole Taylor, Email: nichole.d.taylor.civ@usmc.mil Telephone: 834.228.3622 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: M0026326QD028 |
| SolDate: 14 Aug 2026 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: 1 |
| OffrNoEx: Off |
| NoCopies: 1 |
| ApprData: See Section G - Contract Administration Data |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: This amendment is issued to Solicitation M0026326QD028 to update the specifications for CLIN 0001. The revised specifications identify the requirement as a Brand Name procurement. Additionally, the solicitation closing date is extended to September 8, 2026. All other terms and conditions of the solicitation remain unchanged. |
| ContNameTitle: |
| CoNameTitle: Randy Wentworth |
| ContDate: |
| CODate: 27 Aug 2026 |