This Performance Work Statement (PWS) details a project for the US Department of Agriculture's Idaho Panhandle National Forest to replace an existing pit toilet at the Lone Mountain Tree Improvement Area. The project involves decommissioning the current small pit toilet and installing a new prefabricated concrete vault toilet approximately 7 miles north of Rathdrum, Idaho. The contractor will be responsible for complete removal of the existing toilet structure, proper pit closure, and installation of a new vault toilet building with a septic tank and necessary connections.

Key project requirements include mobilization, waste disposal, site clearing, and toilet installation, with all tasks to be completed by December 31, 2025. The site is fenced with a locked gate, has flat terrain, and is accessible by vehicle. Specific technical requirements mandate adherence to fire restrictions, working hours from 6:00 AM to 5:00 PM PST (Monday-Friday), and disposal of materials using designated methods. The project's objective is to improve health and safety for employees working at the Lone Mountain Tree Improvement Area, with all work subject to inspection by the Contracting Officer's Representative (COR).

View the file

Other files

File Type Posted
Lone Mtn Toilet Replacement_Construction Specs.docx DOCX document
Experience Questionnaire.pdf PDF
Wage Determinations id112.pdf PDF
1240LU25Q0006 Lone Mt Vault Toilet.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Performance Work Statement

Contents

Project Title3
General Information3
1.0 Background and Purpose3
2.0 Definitions3
Contractor Requirements3
3.0 Technical Requirements / Tasks3
4.0 Deliverable / Schedule4
5.0 Government Furnished4
6.0 Travel4
7.0 Contractor’s Key Personnel4
8.0 Security Requirements4
9.0 Data Rights4
10.0 Section 508 - Electronic and Information Technology Standards4
11.0 Performance Requirement Measures4
Attachment5

Project Title Lone Mountain Vault Toilet Replacement

General Information

1.0 Background and Purpose

This project is located at the Lone Mountain Tree Improvement Area (TIA) located on the Coeur d’Alene River Ranger District on the Idaho Panhandle National Forest. The objective is to improve health and safety for employees who work at the site and support increased employee activity at Lone Mountain TIA.

Project work consists of the decommissioning/removal of a small existing pit toilet and replacing it with a new prefabricated vault toilet. The vault toilet will be provided by the contractor as part of this contract.

The site is approximately 7 miles north of Rathdrum, Idaho on West Seasons Road off on State Highway 41. The site is fenced, and access is through a locked gate located immediately off the paved road. The terrain is flat with little to no elevation change. Installation location of the new vault toilet is easily accessible for vehicles and equipment. The existing vault toilet to be demolished could be accessed and removed by hand, however the pit itself may need equipment to properly rehabilitate. Equipment access may require the removal of trees.

2.0 Definitions

TIA- Tree Improvement Area

Quality Control. Those actions taken by a Contractor to control the production of outputs to ensure that they conform to the contract requirements. The methods for inspecting for quality control are described in the Contractor’s Quality Control Plan (QCP).

Contracting officer’s representative (COR) means an individual, including a contracting officer’s technical representative (COTR), designated and authorized in writing by the contracting officer to perform specific technical or administrative functions.

Contracting Officer - A person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings.

Contractor Requirements

3.0 Technical Requirements / Tasks

· Only the contractor and their employees will be permitted in the designated work areas.

· The Contractor must adhere to all fire requirements when operating equipment during burn bans and all active levels of Hoot Owl Fire Restrictions, and the contractor must have a water tank on-site during burn bans.

· No warming or cooking fires will be permitted anywhere on the work site.

· All deliveries/services shall be performed during working hours (6:00AM-5:00PM PST, Monday through Friday), excluding Federal Holidays unless specifically approved.

Task 3.1 Section 017113 - Mobilization

· Complete all movement of personnel, equipment, supplies, and incidentals to the project site.

· Remove all dirt and plant material from equipment prior to entering work area.

Task 3.2 Section 024100 – Waste Material Disposal

· Complete all loading, handling, hauling, and placing of excess excavation material, unsuitable excavation material, clearing and grubbing debris, and construction and demolition debris.

· Use COR designated burn pit on site for disposal of clean vegetative material.

Task 3.3 Section 024116 - Removal and Disposal of Existing Structures

· Remove and dispose of existing pit toilet structure completely and appropriately, including painted wood.

· To properly close the pit toilet, remove the toilet structure, add a layer of absorbent material like lime to the pit, then fill it completely with soil, compacting it as you go, and finally create a mound of dirt on top to prevent water from pooling and deter flies from entering; mark the area to indicate the pit's location for future reference.

· Use soil from new vault toilet excavation to backfill the existing pit toilet.

Task 3.4 Section 311100 - Clearing and Grubbing

· Complete clearing, grubbing, trimming, removing, and disposing of or treatment of timber, construction slash, and debris.

Task 3.5 Section 333600 - Precast Concrete Toilet Building Installation

· Install one (1) precast concrete vault toilet building to include septic vault tank and connections for a fully functional vault toilet.

4.0 Deliverable / Schedule

Tasks 3.1 – 3.5 must be completed by 12/31/2025.

5.0 Government Furnished

· One (1) Yale key provided for Contractor access to the site, to be returned to the Agency upon completion of work.

6.0 Travel

N/A

7.0 Contractor’s Key Personnel

At all times during performance of this contract and until work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent (Contractor’s Representative) who is satisfactory to the Contracting Officer and has authority to act for the Contractor. The Contractor’s onsite representative shall be fully conversant and literate in English and in the work area whenever work is in progress.

8.0 Security Requirements

N/A

9.0 Data Rights

N/A

10.0 Section 508 - Electronic and Information Technology Standards N/A

11.0 Performance Requirement Measures

Performance Objective
Required Task or Deliverable
Performance Standard
Performance Objective
PWS Task 3.1
Mobilization
Section 017113 - Movement of personnel, equipment, supplies, and incidentals to the project site, must be completed.
COR Inspection
PWS Task 3.2
Waste Material Disposal
Section 024100 - loading, handling, hauling, and placing of excess excavation material, unsuitable excavation material, clearing and grubbing debris, and construction and demolition debris.
COR Inspection
PWS Task 3.3
Removal and Disposal of Existing Structures
Section 024116 - Removal and disposal of all members and materials comprising the existing pit toilet structure. Includes backfilling pit and cleanup.
COR Inspection
PWS Task 3.4
Clearing and Grubbing
Section 311100 - Clearing, grubbing, trimming, removing, and disposing of or treatment of timber, construction slash, and debris.
COR Inspection
PWS Task 3.4
Precast Concrete Toilet Building Installation
Section 333600 - Fabrication and installation of a Precast Concrete Vault Toilet Building with associated septic tank and fittings.
COR Inspection

Attachment Attachment 1: NUR Lone Mountain Toilet Replacement Map A Attachment 2: NUR Lone Mountain Toilet Replacement Map B Attachment 3: Single Vault Engineered Drawings

Figure 1. Existing pit toilet exterior.

Figure 2. Existing pit toilet interior.

Figure 3. Proposed location for concrete vault toilet.

Figure 4. Approximate locations of existing pit toilet and proposed vault toilet. Access road to designated burn pit shown in orange dashed line.