The document appears to be two attachments related to a pre-solicitation notice for a federal contract opportunity to perform repairs to the Lake Marting Recreation Area (LMRA).
Attachment 1 and Attachment 2 both indicate that the contractor will be required to replace underground power in the specified locations, with the new cable having similar capacity to the existing and buried at least 24 inches underground. Termination at two pedestals is also required, and both pedestals will be made operational.
The related federal contract opportunity is a pre-solicitation notice for a firm-fixed price contract to perform various repairs to dock decking, stairs and railings, repair a lift station, and replace railroad tie stairs at the LMRA. The contract value is expected to be between $100,000 and $200,000, and will be a 100% Service-Disabled Veteran-Owned Small Business Set-Aside. The solicitation is anticipated to be issued on or about May 29, 2024, with a site visit on or about May 31, 2024, and proposals due on or about June 12, 2024. The anticipated project completion date is 120 days after the government issues the notice to proceed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW.pdf | ||
| Decking Repairs at LMRA - Pre-Solicitation Notice.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1
Contractor will Replace underground power in the location indicated.
New cable will have similar capacity to existing and will be buried at least 24 inches underground.
Termination at two pedestals is required. Both pedestals will be made operational (Contractor to verify details in the field)
Attachment 2
Contractor will Replace underground power in the location indicated.
New cable will have similar capacity to existing and will be buried at least 24 inches underground.
Termination at two pedestals is required. Both pedestals will be made operational (Contractor to verify details in the field)