LIGHTING INSTALLATION
Solicitation number
RFP SPSD 260000001328 1
Issued by
Saginaw County, Michigan

About this file

Summary: Saginaw Public Schools LED Lighting Installation RFP #BP-01

This is a Request for Proposal issued by Saginaw Public Schools for LED lighting installation and retrofit services across 16 school district buildings and facilities. The project involves a comprehensive lighting upgrade including new fixture installations, fixture retrofits, lighting controls with vacancy/dimming sensors, and Bluetooth switch installations. The scope encompasses interior and exterior lighting work across multiple building types, including elementary schools, middle schools, academies, and administrative facilities located throughout Saginaw, Michigan. The mandatory site visit is scheduled for Thursday, March 5, 2026, at 8:30 AM at the Board of Education building (550 Millard St, Saginaw, MI 48607). Proposals must be received by Thursday, March 26, 2026, at 2:00 PM EST, delivered physically to Tim Furtaw at the Board of Education address. The project must reach substantial completion by August 1, 2026, with work occurring Monday through Friday during second shift hours (approximately 3:00 PM to 11:30 PM), with flexibility to first shift during summer break. Work may extend to weekends with advance coordination through Ameresco.

Each proposal must include a 5% surety bid bond and address specific requirements including detailed construction schedules with manpower projections, measurement and verification data collection, system commissioning, daily progress reporting, weekly toolbox talks, and comprehensive safety documentation. All light fixtures, tubes, and bulbs are provided by Ameresco, while contractors must supply installation materials such as wiring, whips, wire nuts, and switch plates. The contractor bears responsibility for lifts, material transportation, storage, and equipment startup coordination. Required insurance includes $1,000,000 commercial general liability per occurrence, $1,000,000 automobile liability, $1,000,000 employers liability, and $5,000,000 commercial umbrella liability. Performance and payment bonds are required for quotations exceeding $100,000. Prevailing wage is not required, and the project is tax-exempt. Questions must be submitted by Friday, March 13, 2026, with responses provided by Wednesday, March 18, 2026. Ameresco reserves the right to conduct interviews, negotiate best and final offers, make multiple awards by building or groups of buildings, or cancel and reissue the RFP at its discretion.

View the file

Other files

File Type Posted
Familial Disclosure Statement.pdf PDF
Iran Business Relationship Affidavit.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Saginaw Public Schools Lighting RFP #BP-01

BP-01 LED LIGHTING INSTALLATION

REQUEST FOR PROPOSAL (RFP)

RFP Requirements & Scope of Work

LED Lighting Upgrade for the Interior of Multiple Buildings

ISSUE DATE: Wednesday, February 25, 2026

MANDATORY SITE VISIT: Thursday, March 5, 2026

RESPONSE DUE DATE: Thursday, March 26, 2026, by 2:00 PM EST

For additional bid documents and any questions, please reach out to

Josh Foor (jfoor@ameresco.com) and Scott Rychel (srychel@ameresco.com)

Instructions for Proposal Submission

Proposal Preparation Proposals should be prepared providing a straight-forward, concise description of Proposer’s capabilities to satisfy the requirements of this Request for Proposal.

Respondent may include any optional data not requested yet considered by the Proposer to be pertinent to this RFP as an addendum to the proposal.

Any Proposal that does not include the express requirements of this RFP and any issued addenda may be considered an incomplete Proposal and may be rejected.

Ownership of all data, materials and documentation originated and prepared for Ameresco pursuant to the RFP shall belong exclusively to Ameresco. Any confidential or proprietary data must be clearly marked as such.

Final acceptance contingent upon approval by Ameresco and Saginaw Public Schools review.

General Information and Notice to Respondents RFP Schedule Proposals must be received on or before Thursday, March 26, 2026, at 2:00 PM EST.

Mandatory Walk Through A mandatory site visit will be held on Thursday, March 5, 2026, at 8:30 AM. All participating RFP contractors must attend if planning to bid. Meet at the Board of Education building at 550 Millard St, Saginaw, MI 48607. All attendees must park in the lost across Millard St on the north side of the building, then enter through the main doors. The meeting will begin with an initial project summary and overview by Ameresco, with the remainder of the day blocked for site visits as needed.

Delivery of Pricing/Response A physical copy of all proposal material should be delivered directly to Tim Furtaw at the address below and in accordance with the stated RFP Schedule. Response envelope should be marked “Do Not Open prior to Thursday, March 26, by 2:00 PM EST.”

Saginaw Board of Education Attn: Tim Furtaw 550 Millard St Saginaw, MI 48607

Direct all questions to Scott Rychel (srychel@ameresco.com) and Josh Foor (jfoor@ameresco.com) via email by close of business on Friday, March 13, 2026. Responses will be emailed to all respondents who have provided contact information on or before Wednesday, March 18, 2026. Subcontractor interviews, if necessary, will be held in the days following bid opening.

PROPOSAL GUARANTY:

Each proposal must be accompanied by a satisfactory Surety Bid Bond in an amount not less than five percent (5%) of the total bid price as guaranty. No bid shall be considered unless it is accompanied by the required signed guaranty.

Rights Reserved Ameresco, at their discretion and upon determination that such actions would be in the Districts best interest, reserves the right to:

• Accept or reject any or all Proposals, or any part thereof, or to withhold the award and to waive, or decline to waive, irregularities, informalities, and technicalities in any Proposal when determined that it is in its best interest to do so;

• Hold all Proposals for a period of up to (60) days after the RFP due date and to accept a Proposal not withdrawn before the scheduled RFP due date;

• Cancel and/or reissue this RFP at any time;

• Invite some, all, or none of the Proposers for interviews, demonstrations, presentations, and further discussion;

• Negotiate a possible contract and may solicit “best and final offers” from some or all

Respondents prior to or during this negotiation process;

• Choose to not evaluate, may deem non-responsive, and/or may disqualify from further consideration any Proposals that do not follow the RFP directives, are difficult to understand, are difficult to read, or are missing any requested information;

• Make an Award by items, groups of items, or as a whole, whichever is deemed most advantageous to the Project. Ameresco also reserves the right to make multiple awards when it is deemed in the best interest of the Project.

Review of Written Proposals Responses must be prepared as described. An evaluation team may review written proposals based on the evaluation identified below.

• Qualification, capability and experience of proposed personnel/company and evidence of successful performance with similar accounts or operations.

• Financial Stability of Proposer.

• Past experience with similar work.

• Fulfilling the request for information per each section of this RFP.

• Understanding of project requirements, phasing and sequencing.

• Cost Summary and final pricing.

Evaluation Process Contractors with proposals deemed competitive may be interviewed by the project evaluation team.

The interview provides the opportunity for the Contractor to address questions and to more fully describe how their approach to this project. Contractor representatives at the interview should include individuals who will be key points of contact and have major responsibility for contract negotiation, supervision of this particular project, management, and implementation of this particular project.

Final Selection Final reference checks will be conducted with the apparent awardee prior to making the final selection.

Final selection may be a single contractor or multiple contractors across separate buildings, depending on the quality of responses and anticipated schedules.

Contract Terms and Conditions Upon final selection, Contractor agrees that the Ameresco standard subcontract will be executed by the selected and awarded Contractor. This includes the following minimum insurance requirements.

• Commercial General Liability o $1,000,000 per occurrence o $2,000,000 per project aggregate o $2,000,000 products completed operations aggregate

• Comprehensive Automobile Liability o Property Damage - $1,000,000 Combined Single Limit per occurrence

• Employers Liability o $1,000,000 each accident o $1,000,000 for disease, each employee o $1,000,000 disease, policy limit

• Commercial Umbrella Liability o $5,000,000 per occurrence and in the aggregate

Prevailing Wage Prevailing wage is not required as part of this project.

Tax Exempt This project is tax exempt.

Bonding Any, and all quotations over $100,000.00 must include a performance and payment bond, as required by Ameresco’s bonding company. Please include bond in your base bid but break out the Bond cost separately as well.

Scope of Work Relating to This Project Project Details General Conditions o All project management and professional personnel assigned to the Project will be subject to the approval of Ameresco and/or the Saginaw Public Schools, and changes shall not be made without prior written approval, except in the case of employee termination.

o All project personnel and subcontractor will be subject to requirements of Saginaw Public Schools, including background checks through the Michigan ICHAT system.

o This contractor will coordinate all work with other subcontractors as necessary.

o This contractor is to consult with Agencies Having Jurisdiction for proper installation and permitting.

o Any service or localized outages must be coordinated with Ameresco and the District as to cause minimum impact upon the customer.

o No equipment will be allowed to be worked on “live”. Proper “Lock out Tag out” policy must be followed.

o Radios and other music may not be played on work site.

o Breaks and lunch will be at designated areas in the building.

o This is a non-smoking facility. No tobacco products are allowed to be used in this facility or on the facility property.

Schedule & Implementation Requirements o Awarded contractor will submit a detailed construction/implementation schedule. Include manpower, tasks to be performed, and breakout work separate showing all tasks considered part of scope.

o Lighting work may begin as soon as materials are available, with work taking place Monday through Friday during second shift hours (approximately 3:00 pm – 11:30 pm depending on site). When summer break begins work hours can be moved to first shift. A detailed schedule will need to be submitted.

o Work is to occur Monday through Friday every week. Saturday and Sunday work is available to meet the schedule but must be coordinated with Ameresco in advance.

o Access to sites for work will need to be coordinated with Ameresco no less than two weeks in advance.

o Indicate the total number of man hours (including startup and commissioning, excluding Supervision) included in your bid (space provided on attached pricing sheet).

o Indicate the total number supervision hours included in your bid (space provided on attached pricing sheet).

o All supervision necessary to assure the project is installed, sequenced and managed properly on site during all installation. This includes submission of a current 3-week look-ahead schedule each month prior to on-site mobilization and each week starting after mobilization. All payments are contingent upon full compliance of this project planning requirement.

o Contractor will maintain daily progress reporting (number of workers, work expected to be done, rooms expected to be working in). Daily reports are to be emailed to Scott Rychel of Ameresco at srychel@ameresco.com.

o Project must be ready for substantial completion by August 1, 2026.

Safety o Submission of your company’s fully detailed and written Site-Specific Work Safety Policy prior to receipt of contract should you be the selected contractor.

o Submission of your company’s fully detailed and written Drug and Alcohol Policy prior to receipt of contract. Drug or alcohol use is strictly prohibited. All personnel of your company are to be free of influence from drug and alcohol use while on site.

o Full compliance with the customer’s safety policy terms & conditions is a condition to contract award. Background testing may be required by the customer and is the responsibility of this contractor.

o Contractor will have all appropriate Material Safety Data Sheets for materials, solvents, fuels, oils, greases, glues, etc. available and onsite during the work.

o Awarded responder/bidder must provide a designated supervisor/project representative and provide a cell phone number and 24-hour emergency number upon signing of subcontract.

o Weekly tool-box talk and documentation required and is to be emailed to Ameresco weekly.

o Hard hat and safety glasses are a 100% project requirement. Contractor personnel must wear all appropriate PPE and operate in a safe manner while on site.

o Contractor will maintain a clean work environment, and clean/sweep those areas worked in, returning them to the existing condition level of cleanliness. All interior spaces shall be cleaned and returned to existing condition daily.

o Lock-out/tag-out Policy and Procedures to be presented to Ameresco and reviewed prior to mobilization and prior to disruption of any electrical service. Proper lock-out/tag-out procedures to be followed at all times by all project personnel.

Demolition o Any potential asbestos IS NOT in this scope of work. If any material is thought to contain asbestos Saginaw Public Schools and Ameresco are to be notified.

o Care must be taken to keep the facility systems operational throughout the course of the construction insofar as possible.

o Any potential shutdowns of the District’s systems must be coordinated through Ameresco.

o All demoed material is to be removed from site and properly disposed of in a safe manner.

o Lamps/fixtures and/or ballasts containing mercury or other hazardous materials must be recycled following all Local, State, and Federal guidelines with documentation to verify.

o Documentation will be required for disposal of all hazardous waste material o All items to be disconnected must be properly locked out and tagged.

o Disconnect and remove all lamps and ballasts.

o Owner has first rights to removed equipment before disposal.

o Any existing LED lamps identified are to be removed & returned to the District unless instructed otherwise.

o District dumpsters (cardboard included) can also be used if pre-approved by District and

Ameresco, this specifically includes, but not limited to Merrill Park, Stone, Professional Development, and Service Center 2.

Installation:

o This contractor is responsible for the installation of all electrical/LED Lighting.

o All light fixtures, lighting controls, tubes, bulbs, etc. will be provided by Ameresco. Contractor to provide any additional installation material such as wiring, whips, wire nuts, switch plates, required tombstones, etc.

o Contractor to supply lifts when needed.

o District to provide ceiling pads and contractor to install as needed.

o Contract is responsible for safe transportation and storage of materials from storage areas or pickup site to individual buildings.

o Materials will be stored on site in cargo containers provided by Ameresco. Contractors must take delivery of materials and verify accuracy compared to the schedule of values for that building. These containers must be locked at all times when someone is not actively in them.

See Appendix 2 for likely storage areas by building.

o Contractor to note and photograph any damage to new equipment and existing spaces BEFORE work begins. Damaged items discovered after work commences will be deemed being caused by the contractor.

o This contractor is to include supervision, manpower and coordination associated with equipment startup. This contractor is responsible for coordinating startup with manufacturer, Ameresco, the owner and any other necessary and participating vendors.

o A classroom or office must be completed in its entirety before work is finished for the day.

Room’s should not be left partially complete at the end of a work period. It’s understood that larger spaces such as gyms, hallways, etc. may carry over into subsequent weekdays, but may not extend into weekends.

o All work areas should be left clean and orderly. Finished surfaces must be protected to ensure they remain damage free. Any property damage caused by this contractor is the responsibility of this contractor.

o Cut sheets provided in Appendix 4 for all materials furnished by Ameresco.

o Attached is a line-by-line audit document with building level material summaries (Appendix 1) and building floor plans (Appendix 3) for each of the (16) buildings. Those 16 buildings are as follows:

Building Name Address City, State, Zip Code Thompson Middle School 3021 Court St Saginaw, MI 48602 Zilwaukee School 500 West Johnson St Saginaw, MI 48604 Arthur Eddy Academy 1000 Cathay St Saginaw, MI 48601 Herig Elementary 1905 Haughton Ave Saginaw, MI 48602 Kempton Elementary 3040 Davenport Ave Saginaw, MI 48602 Loomis MST Academy 2001 Limerick St Saginaw, MI 48601 Merrill Park Elementary 1800 Grout St Saginaw, MI 48602 Chester Miller Elementary 2020 Brockway St Saginaw, MI 48602 Jessie Rouse Elementary 435 Randolph St Saginaw, MI 48601 Stone Elementary 1006 State St Saginaw, MI 48602 Henry Doerr ECC 3270 Perkins St Saginaw, MI 48601 Success Academy 1000 Tuscola St Saginaw, MI 48607 Maintenance / Transportation 1019 E Genesee Ave Saginaw, MI 48607 Professional Development 1925 S Outer Dr Saginaw, MI 48601 Service Center 2 420 S Warren Ave Saginaw, MI 48607 Board of Education 550 Millard St Saginaw, MI 48607 o Installation pricing should include all necessary lifts, tools, whips or other wiring, and any other commonly used installation materials.

o A detailed work schedule should be included with all bid submissions.

o Appendix 1 is color-coded as follows to reflect new fixtures vs retrofits, with areas shown to have red text getting added vacancy/dimming controls. The information in Appendix 1 should take precedence over any generalizations in the summaries below.

Scope of Work Overview (see Appendix 1 for specific quantities) o Thompson o New fixtures for classrooms, halls, offices, media center troffers/cans, gym, lockers, kitchen, and cafeteria troffers o Retrofit restrooms, storage rooms, media center pendants/sconces, cafeteria pendants/sconces, and electrical/mechanical rooms o Auditorium will remain not be changed o Non-LED exterior lights will be a combination of new area lights and retrofit lamps o Zilwaukee o New fixtures for classrooms, most halls, locker rooms, gym, stage, and kitchen o Retrofit restrooms, storage rooms, electrical/mechanical rooms o o Media Center and main office will have a mix of new fixtures and retrofits o Existing LEDs in various restrooms, storage rooms, and classroom 201 will remain o Non-LED exterior lights will be a combination of new wallpacks and retrofit lamps o Arthur Eddy o New fixtures for classrooms, halls, offices, media center, kitchen, and most of cafeteria o Retrofit restrooms, storage rooms, cafeteria PAR lights, electrical/mechanical rooms, and gym o In main hallways, most bugeyes will be removed and new flat panels installed with EM as needed. Cove lights will be gutted but abandoned in place with lamps and ballasts being removed. See Appendix 7 for details.

o Cafeteria LEDs will remain o Herig o New fixtures for halls, offices, most of media center, kitchen, cafeteria o Retrofit restrooms, storage rooms, electrical/mechanical rooms, and non-LEDs in gym o LEDs in main gym will remain o Non-LED exterior lights will be a combination of new wallpacks and retrofit lamps o Kempton o New fixtures for most classrooms, most halls, most offices, stage, cafeteria and kitchen o Retrofit restrooms, storage rooms, electrical/mechanical rooms, and lounge o Linear retrofit kits in a few classrooms where control is required but existing fixtures will remain o Media center and gym will have a mix of new fixtures and retrofits o Non-LED exterior lights will be a combination of new wallpacks, area lights, and retrofit lamps o Loomis o New fixtures for classrooms, halls, locker rooms, gym, stage, and kitchen o Retrofit restrooms, storage rooms, electrical/mechanical rooms

New Fixtures Retrofits Already LED/Do Not Do o Media center and main office will have a mix of new fixtures and retrofits o Non-LED exterior lights will be a combination of new cans, area lights, and retrofit lamps o Merrill Park o New fixtures in office and stairs near kitchen, stairs near 107, 1st floor hall 2x4s, and 2nd floor hall o All other areas will be retrofit o No exterior lights in scope o Chester Miller o New fixtures for offices, lounge, and work room o Retrofit restrooms and electrical/mechanical rooms o Linear retrofit kits in classrooms where control is required but existing fixtures will remain o Classrooms, storage rooms, and halls will have a mix of new fixtures and retrofits o Existing LEDs in door 8 stairs will remain o Non-LED exterior wallpacks will be replaced with new o Egress lighting will be updated as reflected in Appendix 8 o Jessie Rouse o New fixtures for classrooms, halls, offices, media center, kitchen, and cafeteria o Retrofit restrooms, storage rooms, and electrical/mechanical rooms o Existing LEDs in main gym will remain o Non-LED exterior lights will be a combination of new wallpacks and flood lights o Egress lighting will be replaced as noted in the room-by-room, with a few additional bugeyes and exit combos added per the floor plan in Appendix 9 o Stone o New fixtures for classrooms, halls, offices, cafeteria, and kitchen o Retrofit storage rooms and electrical/mechanical rooms o Restrooms and media center will have a mix of new fixtures and retrofits o Existing LEDs will remain o Non-LED exterior lights will be a combination of new wallpacks and area lights o Henry Doerr o New fixtures for classrooms, halls, offices, and kitchen o Retrofit restrooms, storage rooms, and electrical/mechanical rooms o Non-LED exterior lights will be a combination of new wallpacks and retrofit lamps o Egress lighting will be replaced as noted in the room-by-room, with a few additional bugeyes and exit combos added per the floor plan in Appendix 9 o Success Academy o New fixtures for classrooms, offices, most halls, auditorium, kitchen, can most classroom storage cans o Retrofit other storage rooms and electrical/mechanical rooms o Restrooms and main entrance hall will have a mix of new fixtures and retrofits o No exterior lights in scope o Maintenance/Transportation o New fixtures for shop areas, offices, and garage areas o Retrofit restrooms, storage rooms, electrical/mechanical rooms o Halls will have a mix of new fixtures and retrofits o No exterior lights in scope o Professional Development o New fixtures for main office hall RR cans o Retrofit all other non-LED interior lights o Non-LED exterior lights will be a combination of new wallpacks, cans, and area lights o Service Center 2 o New fixtures for majority of the building o Restrooms will have a mix of new fixtures and retrofits o Existing LEDs in various locations will remain o Non-LED exterior lights will be a combination of new wallpacks and retrofit lamps o Board of Education o New fixtures for the majority of the building o Retrofit boiler room, a few storage rooms, stairwells, some fixtures in/around the main entrance, and restrooms near a few stairwells o Superintendent’s office conference room is not in scope o No exterior lights in scope o All Buildings o Color adjustable interior fixtures should all be set to 4000 K color temperature setting upon installation.

o Color adjustable exterior fixtures should all be set 5000 K color temperature.

o Any lamps that are Type A and Type B compatible must be set and installed as Type B.

o In any fixtures where ballasts are no longer being used, all ballasts must be removed in their entirety and disposed of properly.

o Lumen tunable fixtures should all be set to minimum Lumen setting unless otherwise noted in scope of work.

o All linear fluorescents being replaced with TLED type B lamps may also be installed with a new 2 socket non-shunted wiring harness for each lamp – Keystone Technologies KT-SOCKET-T*-U-T-W or equal. – To be provided by contractor if required by local code compliance.

o For areas receiving vacancy/dimming controls, marked with red text in Appendix 1, the following strategies will be used with all new sensors and switches installed by this contractor:

Flat panel and hinge panel fixtures will get fixture mounted sensors Wrap, strip, can, and tube retrofit fixtures will get one AC sensor per circuit unless otherwise noted in Appendix 1 (sometimes more for larger rooms).

Pendant fixtures will get one AC sensor per row or pendant group, again called out in Appendix 1.

New Bluetooth switches will be installed in each room in the quantities noted in

Appendix 1.

o Any existing LED tubes/lamps that are removed as part of this work shall be boxed and returned to the district.

Alternate: Contractor to program each room to pair sensors with switch and set mode to vacancy. This is typically done with an iPad. Ameresco will train the appropriate contractor team members during installation of the first building if requested.

System Commissioning Requirements o All lamps and fixtures installed will be confirmed with Ameresco to be fully operational at final walk through of project.

o A complete project walk-through and punch list report will be done by Ameresco with the subcontractor and/or Saginaw Public Schools staff upon completion of scope at each individual building.

Specifications Relating to This Project o All installation practices will be per at a minimum of the NEC and local jurisdictions. Any required permits or inspections are the responsibility of the contractor as part of the proposal.

o Products will be new and not previously installed.

o Lamps will be installed completely without any gaps or partial installations.

o Reflectors and lenses will be cleaned to remove any dust and fingerprints.

o This contractor will be responsible for updating the proposed lighting room-by-room with as-built conditions (quantity, make and model, what power level was used for variable fixtures, etc.), and that to have the final pay released is dependent upon the timely and accurate provision of such updated records.

Measurement and Verification:

Contractor will obtain voltage and amperage readings at a sample of different lighting circuits throughout prior to commencement of the Work so that the baseline energy consumption can be determined. Sampling will follow a statistical sampling approach with 80/20 precision and confidence criteria on circuits that represent at least 10% of the fixtures in the building. The same readings will be taken after installation has been completed to generate a matching pre- and post-retrofit data set. The data summarized will be used by Ameresco in the calculation of the baseline energy consumption and/or demand.

Data collection should be completed on the included Ameresco M&V Lighting Form (Appendix 5) and based on the quantities detailed in Appendix 6. These total quantities should be spread across a minimum of 4 buildings to ensure an adequate data sampling.

All required M&V activities will be scheduled a minimum of one week in advance and coordinated to allow both Ameresco and Owner personnel to witness all testing.

Readings will be repeated upon completion of each building to verify post-project energy consumption.

BP-01 Lighting Installation Sub Proposal/Bid Sheet – Page 1 (Please complete & submit this sheet along with any clarifications)

Project: Saginaw Public Schools LED Lighting Scopes

Bid/Quote: Lighting Sub Request for Proposal (RFP)

Date: ____________________ Due by: March 26, 2026, at 2:00 PM

Sub: _____________________ Contact: _____________________

Cell #: _____________________ E-mail: ______________________

Preferred Qualifications

Total school projects larger than $250,000 completed in the last 2 years: ________

Total projects utilizing hinge panels completed in the last 2 years: ________

Please provide a list of Michigan School district references

Project As Defined above

Bid 1 LED Lighting and Lighting Controls Installation

Lighting Installation Labor Only: $_____________________

Installation Materials: $_____________________

Labor + Installation Materials Total: $_____________________

Bond Cost: $_____________________

Project Total (Labor+ Install Material + Bond): $_____________________

Alt 1 Programming of lighting control system (with bond) $_____________________

Anticipated timeline/schedule included

TLED Sockets Included (yes/no). If yes, what was the total cost for this portion of the “Installation Materials” line item above.

BP-01 Lighting Installation Sub Proposal/Bid Sheet – Page 2 (Please complete & submit this sheet along with any clarifications)

Lighting Sub Quote/Bid Sheet Submission

This Lighting Sub Quote/Bid Sheet must be submitted to qualify for acceptance. Please include any other vendor generated quote/detail sheet that may support your proposed equipment evaluation.

Acknowledgment of Addenda

# Indicate All Addenda by Number Below Received Comments

1 Click or tap here to enter text ☐ Click or tap here to enter text 2 Click or tap here to enter text ☐ Click or tap here to enter text 3 Click or tap here to enter text ☐ Click or tap here to enter text 4 Click or tap here to enter text ☐ Click or tap here to enter text 5 Click or tap here to enter text ☐ Click or tap here to enter text 6 Click or tap here to enter text ☐ Click or tap here to enter text 7 Click or tap here to enter text ☐ Click or tap here to enter text 8 Click or tap here to enter text ☐ Click or tap here to enter text

AFFIDAVIT OF BIDDER

The undersigned, the owner or authorized officer of ______________________(the “Bidder”), pursuant to the familial disclosure requirement provided in the advertisement for Request for Proposals for LED Lighting Work, hereby represent and warrant, except as provided below, that no familial relationships exist between the owner(s) or any employee of and any member of the Board of Education of the Saginaw Public School District or the Superintendent of the Saginaw Public School District.

List any Familial Relationships:

1.

2.

3.

4.

5.

BIDDER:

Name of Bidder

By:

Its:

Date:

STATE OF )

)ss.

COUNTY OF ____________ )

This instrument was acknowledged before me on the day of , 2026, by

, Notary Public County, My Commission Expires:

Acting in the County of:

AFFIDAVIT OF COMPLIANCE – IRAN ECONOMIC SANCTIONS ACT

Michigan Public Act No. 517 of 2012

The undersigned, the owner or authorized officer of _____________________ (the “Bidder”), pursuant to the compliance certification requirement provided in Saginaw Public Schools’ (the “District”) Request For Proposals For LED Lighting Work, hereby certifies, represents and warrants that the Bidder (including its officers, directors and employees) is not an “Iran Linked Business” within the meaning of the Iran Economic Sanctions Act, Michigan Public Act No. 517 of 2012 (the “Act”), and that in the event Bidder is awarded a contract as a result of the aforementioned Request For Proposal, the Bidder will not become an “Iran Linked Business” at any time during the course of performing under the contract.

The Bidder further acknowledges that any person who is found to have submitted a false certification is responsible for a civil penalty of not more than $250,000.00 or 2 times the amount of the contract or proposed contract for which the false certification was made, whichever is greater, the cost of the District’s investigation, and reasonable attorney fees, in addition to the fine. Moreover, any person who submitted a false certification shall be ineligible to bid on a Request For Proposal for three (3) years from the date that it is determined that the person has submitted the false certification.

BIDDER:

Name of Bidder

By:

Its:

Date:

STATE OF )

)ss.

COUNTY OF ____________ )

This instrument was acknowledged before me on the day of , 2026, by

, Notary Public County, My Commission Expires:

Acting in the County of:

BIDDER ACKNOWLEDGMENT OF RFP REQUIREMENTS AND AUTHORIZATION

The undersigned declares that he/she has carefully examined the instructions and specifications contained in the RFP and will perform the work and services set forth in its sealed Proposal for the price set forth in its sealed Proposal.

Any exceptions to the terms and conditions contained in this RFP or any other special considerations or conditions requested or required by the Bidder MUST be specifically enumerated by the Bidder and be submitted as part of its Proposal, together with an explanation as to the reason such terms and conditions of the RFP cannot be met by, or, in the Bidder’s opinion, are not applicable to, the Bidder.

The Bidder shall be required and expected to meet the specifications and requirements as set forth in this RFP in their entirety, except to the extent exceptions or special considerations or conditions are expressly set forth in the Bidder’s Proposal and those exceptions or special considerations or conditions are expressly accepted by the School District. All Pricing factors must be clearly indicated in the Proposal Forms provided as part of the Bidder’s Proposal.

Name of Bidder: _________________________________________________________

Address: _______________________________________________________________

City/State/Zip: __________________________________________________________

Phone/Fax: _____________________________________________________________

Representative/Title: _____________________________________________________

Signature: _____________________________________________________________

Date: _________________________________________________________________