Lewis_County_Comprehensive_Plan_Periodic_Update_DRAFT_Budget.pdf

PDF 98 KB Posted

Attached to
Lewis County Comprehensive Plan Periodic Update
Solicitation number
2023-GEN-006
Issued by
Kittitas County, Washington

About this file

This document is a draft Commerce Grant Budget for the Lewis County Comprehensive Plan Periodic Update, spanning two years from July 1, 2023, to June 30, 2025. The budget outlines a detailed breakdown of tasks for the comprehensive plan update, including scoping, existing conditions analysis, public engagement, draft and final comprehensive plan development, SEPA review, zoning and development regulations, and critical areas assessment. The project is divided into 14 distinct tasks, with work distributed across two years and allocations split between Mindy (an individual or entity) and a consultant.

The total budget for the project is $350,000, evenly split between Year 1 and Year 2 at $175,000 each. The budget shows varying percentages of work allocation for each task, with some tasks fully completed in Year 1 (such as Zoning & Development Regulations) and others distributed across both years (like Public Engagement and Gap Analysis). The funding appears to be from a Commerce Grant, with tasks ranging from $0 to $45,000 in initial budgeting. The budget demonstrates a collaborative approach, with work percentages carefully allocated between Mindy and the consultant, suggesting a shared responsibility for different aspects of the comprehensive plan update.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Commerce Grant Budget - DRAFT Year 1 = July 1, 2023 - June 30, 2024 Year 2 = July 1, 2024 - June 30, 2025

By percent of Grant

Year 1 Year 2 Task 1 Pop/Housing Allocations $0 100% $0 0% $0 $0 $0 $0 Task 2 Scoping $10,000 50% $5,000 50% $5,000 $0 $0 $0 Task 3 Existing Conditions $45,000 50% $22,500 50% $22,500 $0 $0 $0 Task 4 Public Engagement $35,000 20% $7,000 80% $28,000 $25,000 50% $12,500 50% $12,500 Task 5 Draft Comprehensive Plan $25,000 10% $2,500 90% $22,500 $0 $0 $0 Task 6 Packwood Subarea Plan $0 100% $0 0% $0 $0 $0 $0 Task 7 Onalaska Subarea Plan $0 100% $0 0% $0 $0 $0 $0 Task 8 Urban Growth Areas $0 100% $0 0% $0 $0 $0 $0 Task 9 SEPA Review $10,000 10% $1,000 90% $9,000 $0 $0 $0 Task 10 Final Comprehensive Plan $25,000 10% $2,500 90% $22,500 $0 $0 $0 Task 11 Gap Analysis $10,000 5% $500 95% $9,500 $20,000 5% $1,000 95% $19,000 Task 12 Zoning & Development Regulations $15,000 100% $15,000 0% $0 $15,000 95% $14,250 5% $750 Task 13 SEPA Review $0 $20,000 100% $20,000 0% $0 Task 14 Critical Areas $0 $95,000 5% $4,750 95% $90,250

Total $175,000 $56,000 $119,000 $175,000 $52,500 $122,500

Mindy Consultant Mindy Consultant

Commerce Budget