Levee security fence Scope of Work.docx
DOCX document 250 KB Posted
- Solicitation number
- 70Z02926QNEWO0000031
About this file
This is a Scope of Work document for the demolition, removal, and reconstruction of two levee security fences at the United States Coast Guard Cutter KANKAKEE in Memphis, Tennessee. The contractor shall furnish all labor, tools, equipment, materials, and personnel necessary to complete the work. The new fencing will total approximately 450 linear feet, stand 8 feet tall, and include barbed wire at the top. The contractor must be certified in Tennessee and is responsible for disposing of the existing fence and all construction debris, with landfill disposal receipts required within 10 working days. The contractor shall coordinate all staging and laydown areas with the Coast Guard prior to work commencement, comply with all applicable federal, state, and local safety and environmental regulations, and maintain daily cleanup of the work area without using Coast Guard waste disposal facilities.
Work shall be performed Monday through Friday from 8:00 AM to 4:00 PM on an operational military installation, with the entire contract performance period not to exceed 90 calendar days from the Notice to Proceed. The contractor must submit personnel rosters for security approval, a construction progress schedule with major milestones, a comprehensive safety plan, product data sheets, and operation and maintenance manuals prior to commencing work. All work site safety is the contractor's responsibility, including barricades, signage, and temporary partitions. The contractor shall verify the location of underground and concealed utilities using electromagnetic and sonic scanning equipment before beginning work and must coordinate with the Contracting Officer's Representative (CPO Matthew Johnson at matthew.j.johnson3@uscg.mil or 985-707-6593) regarding work hours, utility interruptions, and site access. A mandatory site visit is required prior to quote submission.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF1442.pdf | ||
| Construction Clauses.docx | DOCX document | |
| Wage determination.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT SPECIFICATIONS
Levee Security Fence
AT
UNITED STATES COAST GUARD
USCGC KANKAKEE
2 A.W Willis AV Memphis, TN
PROJECT NUMBER 331464005
August 2026
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1. GENERAL DESCRIPTION
1.1.1. General Work Requirements
Furnish all labor, tools, equipment, and materials for the demolition, removal, and rebuild of 02 levee security fences located on USCG Sector Lower Mississippi River Property.
The Base Bid work generally includes, but is not limited to, the following:
A. Contractor shall demolish and remove the existing security fence.
B. The contractor shall construct 02 new levee security fences. Fence will be APPROX 450 ft total length, 8 ft tall and will have barb wire at top.
C. This summary is not all inclusive and delineates only those work items deemed as major to the contract. Ancillary work items necessary to attain the completed project, shall be included in the contract as inherent to the work.
1.1.2. SPECIFIC WORK REQUIREMENTS
A. Qualifications
(1) The construction shall be performed by a contractor certified in the state of Tennessee.
B. Additional Performance Requirements
(1) Contractor shall be responsible for disposing of the existing security fence.
1.1.3. SPECIAL WORK REQUIREMENTS
A. Comply with environmental requirements of the Coast Guard unit.
B. Coordinate all staging and laydown areas with the Coast Guard prior to work starting.
1.2. TEMPORARY FACILITIES OR UTILITIES
None required.
1.3. PROJECT PERFORMANCE PERIOD
A. The total contract performance period shall include not only the time needed to complete the base bid and approved option items, but it also includes the time needed to submit, review, and approve all material submittals, and complete all project record (closeout) documents. After work begins at the site, perform the work continuously during normal working hours and show daily progress until all work is complete.
B. The total contract performance period is 90 calendar days.
1.4. LOCATION
The work is located at:
U.S. Coast Guard Cutter KANKAKEE Levee Security Fence 2 A.W. Willis Ave Memphis 38105, Tennessee Arrangements for visiting the site may be made by contacting:
CPO Matthew Johnson Email: matthew.j.johnson3@uscg.mil Telephone: (985) 707-6593
1.5. DRAWINGS ACCOMPANYING SPECIFICATION
There are no drawings accompanying this specification.
1.6. WORK HOURS
1.6.1. Normal Working Hours
A. Perform all work at the site from Monday through Friday from 8:00am to 4:00 pm, unless otherwise approved. This project requires a special schedule to prevent operational interruptions during the installation process. Please refer to the scope section for detailed coordination of working hours. The contractor shall plan a schedule to minimize disruptions to building operations.
B. Performing the work beyond the listed working hours is at the discretion of the Coast Guard unit and the contractor must gain prior approval.
1.7. SPECIFIC ENVIRONMENTAL REQUIREMENTS
There are no specific environmental requirements. Refer to section titled Environmental for general environmental requirements.
1.8. SAFETY PROGRAM
1.8.1. General
The Contractor is wholly responsible for work site safety. Implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. Provide appropriate safety measures including but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable federal, State and local safety laws, rules and regulations.
1.9. AVAILABILITY OF UTILITY SERVICES
A. Reasonable amounts of the following utilities will be made available to the Contractor without charge.
(1) Electricity, and
(2) Potable Water.
B. The Contractor shall pay all costs incurred in connecting, converting, and transferring the utilities to the work. The contractor shall be responsible for making connections including providing back flow preventers, transformers and for disconnection. The contractor shall provide temporary toilet facilities for their personnel.
1.10. UNDERGROUND AND CONCEALED UTILITIES
A. Any utility locations provided are diagrammatic, not exact.
B. Physically verify the location and elevation of the existing underground and concealed utilities local to the work area. Employ techniques to scan the construction site including electromagnetic and sonic equipment prior to commencing the work. Mark the surface of the ground where existing underground utilities are discovered.
1.11. UTILITY OUTAGES
Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the Contracting Officer’s Representative (COR).
1.12. CONTRACTOR USE OF PREMISES
The work shall be performed on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the COR. Isolate each construction area with temporary partitions and dust controls. Provide movable high-visibility safety fencing about all work areas and equipment laydown areas located outdoors. Provide temporary covers on excavations that remain open overnight.
1.13. CLEANUP
The Contractor shall keep the work area, including the laydown and storage area, free from accumulations of waste materials on a daily basis and comply with all federal, state, and local regulations pertaining to the storage, transport, and disposal of wastes. The Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles, or dumpsters.
1.14. ENVIRONMENTAL
1.14.1. Protection of the Environment
The Contractor shall comply with all applicable federal, state, and local laws and regulations for the protection of the environment, including but not limited to the Endangered Species Act (ESA), Bald and Golden Eagle Protection Act (BGEPA), the Migratory Bird Treaty Act (MBTA), National Historic Preservation Act (NHPA), the Resource Conservation and Recovery Act (RCRA), and Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA).
1.15. DISPOSITION OF MATERIALS
A. All materials including construction debris and equipment shall be removed from Government property. The Government will not be responsible for the condition or loss of, or damage to, such property after notice to proceed. Materials and equipment shall not be viewed by prospective purchasers or sold on the site.
B. The Contractor shall submit the disposal receipt from the landfill within 10 working days of disposal.
1.16. STORM PROTECTION
The Contractor shall take every practicable precaution to minimize danger from storms to personnel, the work, and to adjacent property. Precautions shall include, but not be limited to, closing all opening, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.
1.17. RECEIPT OF MATERIALS
The Contractor is responsible to receive all equipment, materials, and supplies.
1.18. DELIVERY AND STORAGE
The Contractor is responsible for the proper transport and storage of all equipment and materials.
1.19. SECURITY
A. Submit a list of the names of all personnel working on the project site prior to the preconstruction conference for approval. The roster shall be submitted via email, and at a minimum, include the first name, last name, job description, and company of employment.
B. Immediately submit a new list upon a change in on-site project personnel. Refer to the paragraph titled, Special Notice Prior Notification, for notification requirements. Only personnel on the approved list are allowed onto the project site.
C. All approved personnel shall carry a valid, Government-issued identification while on Government property in conformance with the Real ID Act of 2005. Non-compliant personnel shall be escorted off Government property.
1.20. FINAL INSPECTION AND ACCEPTANCE
A. Electronically submit a written request for final acceptance to the Coast Guard.
1.21. WARRANTIES
A. Endorse all warranties or guarantees to the Government.
1.22. TRAINING
A. The Contractor shall provide training to unit personnel in the operation of the equipment. The Operation and Maintenance Manuals shall be approved and provided to the unit prior to the training.
1.23. SUBMITTALS
A. Submittals will be reviewed by the Coast Guard and returned within 10 working days after receipt, unless otherwise stated.
1.24. SUBMITTAL LIST
A. ROSTER OF PERSONNEL
(1) As required by the paragraph titled Security.
B. PROJECT SCHEDULE
(1) Prepare a Construction Progress Schedule. It shall include all major milestones and events for the entire duration of the construction contract.
C. SAFETY PLAN
(1) At a minimum, describe the general safety program and identify specific safety provisions for hazards incidental to the contract work such as elevated working surfaces, or similar conditions of the work. Comply with the paragraph titled Safety Program.
D. PRODUCT DATA
(1) Submit the product data sheet for each manufactured item. It shall include the manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves and catalog cuts. Submit complete descriptive data for each type of material. Clearly mark data to indicate the type of material to be provided.
1.24.2. OPERATION AND MAINTENANCE MANUALS
A. Submit electronically and provide the following:
(1) Contact information for the prime contractor, sub-contractor, and major equipment vendor/supplier;
(2) Warranty information;
(3) Test procedures;
(4) Results of all testing and commissioning procedures;
(5) Performance data;
(6) A control sequence describing start-up, operation and shut-down instructions;
(7) Installation instructions;
(8) Maintenance instructions;
(9) Operating instructions;
(10) Parts list.
-- End of Section --