This document is a U.S. Army Corps of Engineers Mississippi Valley Division (MVD) construction timeline for levee and floodwall projects scheduled from October 2025 to October 2030. The comprehensive chart details 36 infrastructure projects across multiple states including Missouri, Arkansas, Illinois, and Louisiana, with project lengths ranging from 0.14 to 12 miles and estimated budgets from $0-5M to $25-100M. Projects are categorized as either "Under Construction" (green bars) or "Proposed Work" (orange bars), with specific focus on levee replacements, enlargements, slide repairs, gravity flow structures, and floodwall renovations at various locations such as Caruthersville, Helena, Avondale, and Cairo. The document notes that several projects are intended to be awarded under Multiple Award Task Order Contracts, and emphasizes that all project information is subject to change as designs are refined and impacts are quantified.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Caruthersville, MO Floodwall Replacement: MVM

MRL Item 460-L: MVK+

St Rose Levee Enlargement: MVN+

MRL Item 368-R: MVK+

System 1 Gravity Flow Strcutures: MVM

System 3 Gravity Flow Structures: MVM

MTG Reach A Levee: MVN

MRL Item 525-R :MVK+

Goose Pond Pump Station Renovation: MVM

Dugas to Celotex Seepage: MVN+

MRL Item 409-R: MVK+

MRL Item 411-R: MVK

Item 206.7-R - Plaquemines/Reveille: MVK

Levee Slide Repairs MO - MATOC Task Order 1: MVM+

Levee Slide Repairs MO - MATOC Task Order 2: MVM+

MRL Slide Repair - SATOC: MVK

Helena, AR Floodwall Replacement: MVM

System 6 - Segment 20 Levee Gravel Resurfacing

Item 154-L - Welham Plantation: MVK

System 8 Levee Gravel Resurfacing Ramps

MRL Item 393-R: MVK+

Item 228-R - Port Allen Levee: MVK

Item 611-L: MVK

Item 614/615/616-L: MVK

Item 465-L: MVK+

Items 152/156.8/163-L - Bel/Rome-Coll/Rome: MVK

Bayou Sale East West Tie In Phase I: MVN

MRL Item 367-R: MVK+

MTG Reach F Upper: MVN

Item 110.4-R - Waggaman: MVK

Items 240.3/246-R - Thomas Point/Smithfield: MVK

Item 178-R - Smoke Bend: MVK

Avondale Levee and Floodwall: MVN

Item 555-R: MVK

MRL Item 189/217.6/181-R: MVK+

Item 520-R: MVK

Item 194.5-R - Bayou Goula to Alhambra: MVK

Pecan Point, AR: MVM

E73.3 - E74 Levee Lift Phase I: MVN

Item 370-R: MVK+

Bayou Alabama Levee Lift: MVN

Barfield, AR: MVM

Dumaine St Floodwall: MVN

Algiers Lock - Levee: MVN+

ABLD-1 180R: MVN+

Cairo, IL Floodwall: MVM

U.S. Army Corps of Engineers 1400 Walnut Street, Vicksburg, MS 39180 www.mvd.usace.army.mil

MVD Levee Items

OCTOBER 2025

CONSTRUCTION DURATION

ONGOING AWARDED PROPOSED WORK

U.S. ARMY CORPS OF ENGINEERS MISSISSIPPI VALLEY DIVISION

PROPOSED

WORK

LEVEE AND FLOODWALL ITEMS

ALL PROJECT INFORMATION IS SUBJECT TO CHANGE AS DESIGNS ARE REFINED & IMPACTS ARE QUANTIFIED.

Length ; $

UNDER

CONSTRUCTION

NOTE:

+PROJECT INTENDED TO BE AWARDED UNDER A

MULTIPLE AWARD TASK ORDER CONTRACT.

0.6 MI ; >$10M

2.4 MI ; >$10M

1.3MI ; $5-10M

3.8 MI ; >$10M

N/A ; $0-5M

N/A ; $0-5M

3.25 MI ; $10-25M

3.0 MI ; >$10M

N/A ; $0-5M

1.1 MI ; $5-10M

3.2 MI ; >$10M

3.0 MI ; >$10M

2.7 MI ; >$10M

1 MI ; $0-5M

1 MI ; $0-5M

0.14 MI ; $0-5M

0.3 MI ; >$10M

12 miles ; $0-5M

0.5 MI ; $0-5M

Varies ; $0-5M

5.1 MI ; >$10M

2.5 MI ; >$10M

2.9 MI ; $5-10M

5.5 MI ; $5-10M

0.4 MI ; $5-10M

0.5 MI ; $0-5M

0.52 MI ; $5-10M

4.7 MI ; >$10M

2.9 MI ; $25-100M

1.1 MI ; $0-5M

1.6 MI ; $5-10M

3.3 MI ; >$10M

1.2MI ; >$10M

0.5 MI ; $1-$5M

0.82 MI ; $0-5M

2.6 MI ; >$10M

6.7 MI ; $5-10M

1.0 MI ; $0-5M

1.34 MI ; >$10M

3.7 MI ; >$10M

1.67 MI ; >$10M

0.5 MI ; $0-5M

0.5MI ; >$10M

0.5 MI ; $0-5M

0.7 MI ; $5-10M

2.5 MI ; >$10M

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2