This document appears to be a government file related to a special notice for upcoming levee requirements along the Mississippi River system within the U.S. Army Corps of Engineers Mississippi Valley Division (MVD). The work will primarily involve construction, repair, and maintenance of earthen levee embankments, seepage berms and cutoffs, and groundwater relief wells across the Memphis, Vicksburg, and New Orleans Districts. The work will also include floodwall construction. Estimated project lengths range from 0.05 to 6.7 miles, with costs between $0-5 million to over $10 million. The work is expected to be awarded under multiple award task order contracts. The notice provides contact information for small business professionals and contracting chiefs in each district. No specific response dates or award timelines are provided, as this appears to be a general forecast of upcoming requirements for Fiscal Year 2025.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Island 8: MVM
Item 528.0-R: MVK+
Item 380.0-R: MVK+
Item 385.0-R: MVK+
Item 388.0-R: MVK+
Caruthersville, MO Floodwall Replacement: MVM
MRL Item 368-R: MVK+
MRL Item 460-L: MVK+
MRL Item 525-R :MVK+
St. Thomas, AR Berm Re-Eval: MVM
Plaquemines Point Seepage: MVN+
Item 465-L: MVK
Wilson, AR Slope Flattening: MVM
North Mound City, IL Sump: MVM+
MRL Item 345-R: MVK+
MRL Item 189/217.6/181-R: MVK+
Harvey Forebay Lock - Levee: MVN
Dugas to Celotex: MVN+
MRL Item 409-R: MVK+
MRL Item 411-R: MVK+
MRL Item 393-R: MVK+
MRL Item 366-R: MVK+
Fish Market Gate/Highway 51, IL: MVM
Helena, AR Floodwall Replacement: MVM
Item 611-L: MVK
Item 614/615/616-L: MVK
Barfield, AR: MVM
Pecan Point, AR: MVM
MRL Item 367-R: MVK+
Item 370-R: MVK+
Item 206.7-R - Plaquemines/Reveille: MVK
Item 340-R: MVK
Bayou Sale East West Tie In: MVN
Item 228-R - Port Allen Levee: MVK
Items 240.3/246-R - Thomas Point/Smithfield: MVK
Item 178-R - Smoke Bend: MVK
Phillippy, TN: MVM
Item 555-R: MVK
Item 110.4-R - Waggaman: MVK
Item 520-R: MVK
Item 194.5-R - Bayou Goula to Alhambra: MVK
E73.3 - E74 Levee Lift: MVN
Item 154-L - Welham Plantation: MVK
Items 152/156.8/163-L - Bel/Rome-Coll/Rome: MVK
Item 92.6-L - IHNC Lock Forebay: MVK
W121 Levee Lift: MVN
Cairo, IL Floodwall: MVM
Bayou Alabama Levee Lift: MVN
Algiers Lock - Levee: MVN+
ABLD-1 180R: MVN+
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
U.S. Army Corps of Engineers 1400 Walnut Street, Vicksburg, MS 39180 www.mvd.usace.army.mil
MVD Levee Items
NOTE:
+PROJECT INTENDED TO BE AWARDED UNDER A
MULTIPLE AWARD TASK ORDER CONTRACT.
OCTOBER 2024
CONSTRUCTION DURATION
ONGOING AWARDED PROPOSED WORK
U.S. ARMY CORPS OF ENGINEERS MISSISSIPPI VALLEY DIVISION
PROPOSED
WORK
LEVEE AND FLOODWALL ITEMS
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
ALL PROJECT INFORMATION IS SUBJECT TO CHANGE AS DESIGNS ARE REFINED & IMPACTS ARE QUANTIFIED.
Length ; $
UNDER
CONSTRUCTION
1.6 MI ; >$10M
3.0MI ; $5-10M
3.8MI ; $5-10M
4.4MI ; $5-10M
4.4MI ; $5-10M
0.6 MI ; >$10M
3.8 MI ; >$10M
2.4 MI ; >$10M
3.0 MI ; >$10M
6 MI ; $5-10M
0.9 MI ; $5-10M
0.4 MI ; $5-10M
0.8 MI ; $0-5M
0.05 MI ; $0-5M
6.1 MI ; >$10M
0.82 MI ; $0-5M
0.3 MI ; >$10M
1.1 MI ; $5-10M
3.2 MI ; >$10M
3.0 MI ; >$10M
5.1 MI ; >$10M
4.8 MI ; >$10M
0.7 MI ; $0-5M
0.3 MI ; >$10M
2.9 MI ; $5-10M
5.5 MI ; $5-10M
0.5 MI ; $0-5M
1.0 MI ; $0-5M
4.7 MI ; >$10M
3.7 MI ; >$10M
2.7 MI ; >$10M
3.0 MI ; $5-10M
0.6 MI ; $5-10M
2.5 MI ; >$10M
1.6 MI ; $5-10M
3.3 MI ; >$10M
0.5 MI ; $0-5M
0.5 MI ; $1-$5M
1.1 MI ; $0-5M
2.6 MI ; >$10M
6.7 MI ; $5-10M
1.34 MI ; >$10M
0.5 MI ; $0-5M
0.5 MI ; $0-5M
3.2 MI ; $5-10M
2.9 MI ; $0-5M
2.5 MI ; >$10M
1.67 MI ; >$10M
0.5 MI ; $0-5M
0.7 MI ; $5-10M