Lehman_Bid_Documents.pdf

PDF 7 MB Posted

Attached to
Lehman Rd Pump Station Improvements
Solicitation number
RFP-2026-076
Issued by
Hays County, La Casita CDP, Texas

About this file

This is a Project Manual and bid solicitation document for the City of Kyle, Texas, for the Lehman Road Pump Station Improvements (Project Number 2026-076). The project consists of construction of a new 3.0-million-gallon prestressed concrete ground storage tank, a high-service pump station with three horizontal split-case centrifugal pumps, a disinfection room with on-site sodium hypochlorite generation, rehabilitation of an existing 0.5-million-gallon steel ground storage tank, and associated infrastructure including yard piping, site work, electrical systems, emergency backup generator, SCADA controls, and security systems. The City will receive sealed proposals through the OpenGov procurement portal (https://procurement.opengov.com/portal/cityofkyle) until 2:00 PM on December 17, 2026, with a mandatory pre-bid virtual conference scheduled for November 19, 2026, at 2:00 PM. Proposers must submit written inquiries by 2:00 PM on December 2, 2026, with responses posted by 2:00 PM on December 9, 2026. The expected project duration is 540 days, with substantial completion required within 510 days and final completion within 30 days thereafter. Contract award will be made within 90 days after proposal opening to the highest-scoring responsible proposer based on evaluation criteria: 50 points for contract price, 30 points for contractor experience and qualifications, 20 points for proposed schedule, and an optional 10 points for interview performance.

Proposal security in the form of a bid bond equal to five percent of the total proposal amount is required and must be submitted electronically with the proposal. The Owner reserves the right to reject any or all proposals and has established evaluation procedures including potential interviews of qualified proposers. Proposers must submit comprehensive qualifications statements including current and past project experience, key personnel resumes, financial statements, safety records, surety information, and lists of critical subcontractors and suppliers for evaluation. Award criteria prioritize contractor experience with similar projects, financial stability, and ability to meet the aggressive timeline. The project is funded by the City of Kyle and is not subject to state sales and use taxes per Tax Code Section 151.309. Proposers are required to be authorized to do business in Texas and, if applicable, must hold valid contractor licenses. Prior to contract award, successful proposers must submit a Texas Ethics Commission Form 1295 (Certificate of Interested Parties) with an assigned certificate number and complete a Conflict of Interest Questionnaire. The Owner reserves broad authority to modify timelines, issue addenda, negotiate with proposers, conduct investigations, and take corrective actions as deemed in the City's best interest. Bid protests must be submitted in writing within five business days after award notification to the City of Kyle Procurement Division.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

FOR

LEHMAN RD PUMP STATION IMPROVEMENTS

Project Number: 2026-076 for the

CITY OF KYLE, TEXAS

Prepared for

CITY OF KYLE

100 W. CENTER ST.

P.O. BOX 40

KYLE, TEXAS 78640

“OWNER”

Prepared by

WGI, Inc.

755 East Mulberry Avenue, Suite 501, San Antonio, TX 78212

“ENGINEER”

TABLE OF CONTENTS

City of Kyle Kyle, Texas

LEHMAN RD PUMP STATION IMPROVEMENTS

Project Number: 2026-076

SECTION DESCRIPTION NO. OF PAGES

00100 Advertisement for Proposals 2

00200 Instructions to Proposers for Construction Contract 15

00400 Proposal Form for Construction Contract 15

Form of Bid Bond 2

Qualifications Statement 10

Qualifications Statement – Schedule A – Current Projects 1

Qualifications Statement – Schedule B – Previous Experience with Similar Projects

Qualifications Statement – Schedule C – Key Individuals 2

00500 Notice of Award 1

Agreement between Owner and Contractor for Construction 8 Contract (Stipulated Price)

Notice to Proceed 1

00600 Form of Performance Bond 3

Form of Payment Bond 3

00700 Standard General Conditions of the Construction Contract – Table of Contents

Standard General Conditions of the Construction Contract 77

00800 Supplementary Conditions of the Construction Contract 1

Wage Rates and Payroll Reporting 4

ADVERTISEMENT FOR PROPOSALS

City of Kyle Kyle, Texas

LEHMAN RD PUMP STATION IMPROVEMENTS

Project Number: 2026-076

The CITY OF KYLE (“Owner”) will receive COMPETITIVE SEALED PROPOSALS (“Proposals”) for the LEHMAN RD PUMP STATION IMPROVEMENTS (“Project”) until 2:00PM on December 17th, 2026 at the link identified below at which time they will be publicly opened and read aloud, for furnishing all labor, material, tools, and equipment and performing all work required for the Project.

The City will receive Proposals electronically through https://procurement.opengov.com/portal/cityofkyle under bid ID RFP-2026-076

Proposals are invited for the items and scope of work as follows:

FOR THE DEVELOPMENT OF A 3.0 MG CONCRETE GROUND STORAGE TANK, PUMP STATION, AND

DISINFECTION ROOM, ALONG WITH THE REHABILITATION OF AN EXISTING 0.5 MG GROUND STORAGE TANK. ASSOCIATED IMPROVEMENTS INCLUDE BASE AND PAVEMENT, GRADING, DRAINAGE, UTILITIES, SITE RESTORATION, AND RELATED APPURTENANCES.

Construction services for this project will be selected through competitive sealed proposals in accordance with Chapter 2269, of the Texas Government Code. The Owner will evaluate and rank the contractors based on the following selection criteria: [50 Points – Contract Price; 30 Points - Contractor’s Experience and Qualifications; 20 Points - Proposed Schedule; with an additional possible 10 Points for Optional Interview for certain qualified Proposers].

The Project has an expected duration of 540 days.

Proposals must be submitted on the Proposal Form provided and must be accompanied by Proposal security in a penal sum not less than five percent (5%) of the total amount of the Proposal. The security shall be in the form of a bid bond furnished by a reliable surety company having authority under the laws of Texas to write surety bonds in the amount required, with such security made payable without recourse to the City of Kyle.

Instructions to Proposers, Proposal Forms, Specifications, Contract Documents, and other information and Proposal Documents for the Project will be on file by November 9th, 2026 and may be examined at the City of Kyle website (www.cityofkyle.com).

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

Issued for Bid WGI, Inc.00100 - ADVERTISEMENT FOR

PROPOSALS - 1

https://procurement.opengov.com/portal/cityofkyle http://www.cityofkyle.com/ http://www.cityofkyle.com/

All such documents will also be provided on OpenGov for immediate download by such date. Please go to www.opengov.com. The Project ID is “2026-076”. Prospective Bidders shall address written inquiries through the Project’s OpenGov website. Hard copies of Contract Documents are not available.

A non-mandatory pre-Bid virtual conference will be held on November 19th, 2026 at 2:00pm. A link to attend the virtual conference will be posted on the City of Kyle OpenGov procurement portal (https://procurement.opengov.com/portal/cityofkyle).

The websites will be updated periodically with addenda, reports, and other information relevant to submitting a Proposal for the Project. All official notifications, addenda, and other Proposal Documents will be offered only through the designated website. Neither Owner nor Engineer will be responsible for Proposal Documents, including addenda, if any, obtained from sources other than the designated website.

For all further requirements regarding Proposal submittal, qualifications, procedures, and contract award, refer to the Instructions to Proposers that are included in the Proposal Documents.

Proposers should carefully examine the plans, specifications and other documents, visit the site of work, and fully inform themselves as to all conditions and matters which can in any way affect the work or the cost thereof. Should a Proposer find discrepancies in, or omissions from, the plans, specifications or other documents, or should be in doubt as to their meaning, Proposer should notify the Project Engineer via https://procurement.opengov.com/portal/cityofkyle. Obtain clarification prior to submitting any Proposal by posing questions via the OpenGov website, but no later than 2:00PM on December 2nd, 2026 . Answers to such questions pertaining to the Proposals will be posted on the OpenGov website no later than 2:00PM on December 9th, 2026. Proposer shall be responsible for checking the OpenGov website for the most up-to-date information before submitting a Proposal.

During the pendency of this RFP, Proposer shall not contact any City staff except those designated herein this RFP or subsequent addendums or correspondence.

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

Issued for Bid WGI, Inc.00100 - ADVERTISEMENT FOR

PROPOSALS - 2

https://procurement.opengov.com/portal/cityofkyle

INSTRUCTIONS TO

PROPOSERS FOR CONSTRUCTION CONTRACT

ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Proposers have the meanings indicated in the General Conditions and Supplementary Conditions.

ARTICLE 2—PROPOSAL DOCUMENTS

2.01 Complete Proposal Documents and Contract Documents have been uploaded to OpenGov for immediate download (https://procurement.opengov.com/portal/cityofkyle. The Project ID is “2026-076.” Prospective Proposers shall address written inquiries through the Project’s OpenGov website. Hard copies of Contract Documents are not available. It is Proposer’s responsibility to determine that it is using a complete set of documents in the preparation of its Proposal. Proposer assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Proposer itself or by its prospective Subcontractors and Suppliers.

2.02 Proposal Documents are made available for the sole purpose of obtaining Proposals for completion of the Project and permission to download or distribution of the Proposal Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for Proposers to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers. Printed documents may not be re-sold under any circumstances. Ownership of the Proposal Documents shall remain with Owner.

2.03 Owner has established a Proposal Documents Website on OpenGov, as stated in Paragraph

2.01 herein (“Proposal Website”) and as indicated in the Advertisement or Invitation to Proposers.

Owner recommends that Proposer obtain a complete set of the Proposal Documents from such website. Proposers may rely that sets of Proposal Documents obtained from the Proposal Website are complete, unless an omission is blatant. Addenda shall be posted on the Proposal Website or otherwise distributed to Proposers.

ARTICLE 3—QUALIFICATIONS OF PROPOSERS

3.01 To demonstrate Proposer’s qualifications to perform the Work, Proposer shall submit with its Proposal the following information:

A. The names and positions of the individuals authorized to bind Proposer’s company, including attesting or countersigning officers.

B. An organization chart showing the principals and management personnel who will be involved with the proposed Work.

C. The resumes of the superintendent and supervisors for the various disciplines and crafts required for the Project.

D. A proposed Progress Schedule estimating the completion of the major tasks of the project.

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

Issued for Bid WGI, Inc.00200 - INSTRUCTIONS TO PROPOSERS

FOR CONSTRUCTION CONTRACT - 1

E. Current insurance certificate(s) with limits consistent with requirements of these Contract Documents.

F. Such other information required under the Qualifications Statement or as required to evaluate Proposal or Proposer.

3.02 A Proposer’s failure to submit required qualification information within the times indicated may disqualify Proposer from receiving an award of the Contract.

ARTICLE 4—PRE-PROPOSAL CONFERENCE

4.01 A pre-Bid conference will be conducted for this Project.

Date: Thursday, November 19 , 2026

Time: 2:00pm

For additional information, please see Project ID “RFP-2026-076” at the OpenGov portal link below.

https://procurement.opengov.com/portal/cityofkyle

All proposers are highly encouraged to attend this online meeting to learn more about the requirements of this solicitation.

ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE

5.01 Site and Other Areas

A. The Site is identified in the Proposal Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions or Contract identify the following regarding existing conditions at or adjacent to the Site:

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

Issued for Bid WGI, Inc.00200 - INSTRUCTIONS TO PROPOSERS

FOR CONSTRUCTION CONTRACT - 2

https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fprocurement.opengov.com%2Fportal%2Fcityofkyle&data=05%7C02%7Callen.crozier%40hdrinc.com%7Cade4661606db4b00358c08ddf09cc9f0%7C3667e201cbdc48b39b425d2d3f16e2a9%7C0%7C0%7C638931278474689960%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=snDZqPp%2FZLJK1C5XBGjrAIZK64%2FXqbivdMsjfoXJ8KY%3D&reserved=0

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Proposers. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

C. Provisions concerning responsibilities for the adequacy of data furnished to prospective Proposers with respect to subsurface conditions, other physical conditions and Underground Facilities, and possible changes in the Proposal Documents due to differing or unanticipated conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Proposers with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work appear in Paragraph

5.06 of the General Conditions.

5.03 Other Site-related Documents

A. No other Site-related documents are available.

5.04 Site Visit and Testing by Proposers

A. Proposer is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas to become familiar with and satisfy Proposer as to the general, local, and Site conditions that may factor into its Proposal. During the visit the Proposer must not disturb any ongoing operations at the Site.

B. Proposer is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

C. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Proposer general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Proposer deems necessary for preparing and submitting a successful Proposal. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Proposer is responsible for establishing access needed to reach specific selected test sites.

D. Proposer must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

Issued for Bid WGI, Inc.00200 - INSTRUCTIONS TO PROPOSERS

FOR CONSTRUCTION CONTRACT - 3

by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

E. Proposer must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

5.05 Other Work at the Site

A. Reference is made to Article 8 of the General Conditions and the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Proposal Documents.

ARTICLE 6—PROPOSER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 The submission of a Proposal will constitute an incontrovertible representation by Proposer that Proposer has complied with the requirements of the RFP, that, without exception, other than any stated in Article 7 of the Proposal Form, the Proposal is premised upon performing and furnishing the Work required by the Contract Documents, and applying the specific means, methods, techniques, sequences, or procedures of construction (if any) that may be shown or indicated or expressly required by the Contract Documents, the Proposer has given Owner and Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Proposer has discovered in the Contract Documents, and written resolutions thereof by Owner and Engineer are acceptable to Proposer, that the Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work, that the Proposer has no questions regarding the Work, that the Proposer has all information necessary to make a fully informed Proposal, and that the Proposer has conducted all tests at the site it deems necessary.

6.02 Express Representations and Certifications in Proposal Form, Agreement

A. The Proposal Form that each Proposer will submit contains express representations regarding the Proposer’s examination of Project documentation, Site visit, and preparation of the Proposal, and certifications regarding lack of collusion or fraud in connection with the Proposal. Proposer should review these representations and certifications, and assure that Proposer can make the representations and certifications in good faith, before executing and submitting its Proposal.

B. If Proposer is awarded the Contract, Proposer (as Contractor) will make similar express representations and certifications when it executes the Agreement.

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

FOR CONSTRUCTION CONTRACT - 4

6.03 The requirements of Subchapter J, Chapter 552, Government Code, may apply to this bid and the Proposer agrees that the Agreement can be terminated if the Proposer knowingly or intentionally fails to comply with a requirement of that subchapter.

ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Proposer shall submit all questions about the meaning or intent of the Proposal Documents to Owner and Engineer in writing. Contact information and submittal procedures for such questions are as follows:

A. All inquiries or requests regarding this solicitation must be submitted in writing online via City of Kyle OpenGov procurement portal

(https://procurement.opengov.com/portal/cityofkyle) only using the electronic question submission feature specific to this solicitation. Such inquiries or requests must be submitted by the due date and time for clarifications provided in this solicitation.

B. Any attempt to question City employees regarding this solicitation outside of OpenGov may result in the City disqualifying that Bidder. Only written responses in OpenGov will be binding regarding inquiries requesting clarification or additional information. Written responses will be released in the form of an Addendum. Bidders must acknowledge receipt of all Addenda.

7.02 Interpretations or clarifications considered necessary by Owner in response to such questions will be issued by Addenda posted on the Proposal Website. Questions received less than seven (7) days prior to the date for opening of Proposals may not be answered.

7.03 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

ARTICLE 8—PROPOSAL SECURITY

8.01 A Proposal must be accompanied by Proposal security made payable to Owner in an amount of five percent (5%) of Proposer’s Proposal Price and in the form of a bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such bid bond must be electronically submitted with the Proposal and issued in the form included in the Proposal Documents.

8.02 The Proposal security of the apparent Successful Proposer will be retained until Owner awards the contract to such Proposer, and such Proposer has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Proposal security will be released. If the Successful Proposer fails to execute and deliver the Contract and furnish the required Contract security within fifteen (15) days after the Notice of Award, Owner may consider Proposer to be in default, annul the Notice of Award, and the Proposal security of that Proposer will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Proposer defaults.

8.03 The Proposal security of other Proposers that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven (7) days after the

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

Issued for Bid WGI, Inc.00200 - INSTRUCTIONS TO PROPOSERS

FOR CONSTRUCTION CONTRACT - 5

Effective Date of the Contract or sixty-one (61) days after the Proposal opening, whereupon Proposal security furnished by such Proposers will be released.

8.04 Proposal security of other Proposers that Owner believes do not have a reasonable chance of receiving the award will be released within seven (7) days after the Proposal opening.

ARTICLE 9—CONTRACT TIMES

9.01 The Contract Times are set forth in the Agreement.

9.02 Provisions for liquidated damages, are set forth in the Agreement.

ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS

10.01 The Contract for the Work, if awarded, will be on the basis of materials and equipment specified or described in the Proposal Documents without consideration during the Proposal and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.

ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 Proposer must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work with the submitted Proposal, with scoring evaluations for the following critical Suppliers and Subcontractors:

Critical Suppliers:

• Pumps

• Variable Frequency Drives (VFDs)

• Motor Control Center / Electrical Distribution Equipment

• Generator and Automatic Transfer Switch (ATS)

• Instrumentation and Control System Equipment (PLC, HMI, SCADA)

• Control Panels

• Sodium Hypochlorite Feed System

• Valves

• Pipe and Fittings

• Security System Equipment

Critical Subcontractors:

• Electrical Contractor

• Instrumentation and Controls Contractor

• Concrete Contractor

• Earthwork/Sitework Contractor

• HVAC Contractor

• Plumbing Contractor

• Site Fencing and Gates Contractor

• Security System Contractor

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

FOR CONSTRUCTION CONTRACT - 6

11.02 Proposer using subcontractors must comply with the terms of the contract documents. Proposer is responsible for all subcontractor acts and omissions to the same extent as if the subcontractor and its employees were employees of the proposer. All requirements set forth as part of the contract documents are applicable to all subcontractors and their employees to the same extent as if the proposer and its employees had performed the services.

11.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Proposer to submit an acceptable substitute, in which case apparent Successful Proposer will submit a substitute, Proposer’s Proposal price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Proposals and making the Contract award.

11.04 If apparent Successful Proposer declines to make any such substitution, Owner may award the Contract to the next highest scoring Proposer that proposes to use acceptable Subcontractors and Suppliers. Declining to make requested substitutions will constitute grounds for forfeiture of the Proposal security of any Proposer.

ARTICLE 12—PREPARATION OF PROPOSAL

12.01 The Proposal Form is included with the Proposal Documents.

A. All blanks on the Proposal Form must be completed by printing or typing in ink and the Proposal Form shall be signed digitally or by wet signature. Erasures or alterations must be initialed in ink by the person signing the Proposal Form. A Proposal price must be indicated for each section, Proposal item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Proposal Form expressly indicates that submitting pricing on a specific alternate item is optional, and Proposer elects to not furnish pricing for such optional alternate item, then Proposer may enter the words “No Proposal” or “Not Applicable.”

12.02 Each and every deviation or exception to the Proposal Documents shall be listed on the Proposal Form upon submission of your Proposal. Listing of deviations and exceptions is an integral and required part of your Proposal. Any deviations or exceptions not listed on the Proposal Form upon submission of your Proposal will not become part of the Contract awarded by the City pursuant to this RFP.

12.03 A Proposal by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

12.04 A Proposal by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.

12.05 A Proposal by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

12.06 A Proposal by an individual must show the Proposer’s name and official address.

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

FOR CONSTRUCTION CONTRACT - 7

12.07 A Proposal by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Proposal Form. The joint venture must have been formally established prior to submittal of a Proposal, and the official address of the joint venture must be shown.

12.08 All names must be printed or typed in ink below the signatures.

12.09 The Proposal must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Proposal Form.

12.10 Postal and e-mail addresses and telephone number for communications regarding the Proposal must be shown.

12.11 The Proposal must contain evidence of Proposer’s authority to do business in the state where the Project is located, or Proposer must certify in writing that it will obtain such authority within the time for acceptance of Proposals and attach such certification to the Proposal.

12.12 If Proposer is required to be licensed to submit a Proposal or perform the Work in the state where the Project is located, the Proposal must contain evidence of Proposer’s licensure, or Proposer must certify in writing that it will obtain such licensure within the time for acceptance of Proposals and attach such certification to the Proposal. Proposer’s state contractor license number, if any, must also be shown on the Proposal Form.

12.13 By submitting a Proposal, Proposer acknowledges and agrees that Owner reserves the right to:

A. Reject any and all Proposals received;

B. Modify the timeline in this RFP;

C. Issue a subsequent RFP;

D. Without prior notice, supplement, amend or otherwise modify this RFP, prior to the date of the submission of the Proposals;

E. Issue one or more Addendums to this RFP, including extending the due date for the Proposals;

F. Cancel, postpone, extend or withdraw the entire RFP, in whole or in part with or without substitution of another RFP if determined to be in the best interest of Owner;

G. Remedy or waive any defect or technical errors in the RFP process;

H. Negotiate with any, all, or none of the Proposers;

I. Accept the written Proposal as an offer;

J. Waive informalities, deficiencies and/or irregularities or accept and review a non-conforming Proposal;

K. Request additional information or clarification;

L. Conduct investigations with respect to the qualifications and experience of each Proposer;

M. Contact any Proposer for clarification after responses are opened and/or to further negotiate with any Proposer if such is deemed desirable by Owner;

N. Eliminate any Proposer which submits an incomplete or inadequate Proposal or is not responsive to the requirements of this RFP; and

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

FOR CONSTRUCTION CONTRACT - 8

O. Take any action affecting the process, the RFP process, or the Project subject to this RFP that would be in the best interest of Owner.

12.14 The Owner may choose not to accept an incomplete Proposal. A Proposal that has one or more of the deficiencies listed below is considered incomplete:

A. The Proposal Form was not signed;

B. All certifications were not acknowledged;

C. A regular item, additive alternative item or deductive alternate item is left blank;

D. A regular item and the corresponding replacement alternative items are left blank; or

E. All addenda were not acknowledged.

ARTICLE 13—BASIS OF PROPOSAL

13.01 Unit Price

A. Proposers must submit a Proposal on a unit price basis for each item of Work listed in the unit price section of the Proposal Form.

B. The total of all estimated prices will be the sum of the products of the estimated quantity of each item and the corresponding unit price. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

ARTICLE 14—SUBMITTAL OF PROPOSAL

14.01 The Proposal Documents include a copy of the Proposal Form, and the bid bond form. The copy of the Proposal Form is to be completed and submitted with the Proposal security and the other documents required to be submitted under the terms of the Proposal Form.

14.02 A Proposal must be received no later than the date and time prescribed and through the electronic procurement portal indicated in the Advertisement or Invitation to Proposers. The Proposal must be accompanied by the Proposal security and other required documents.

14.03 Proposals received after the date and time prescribed for the opening of Proposals, or not submitted at the correct location or in the designated manner, will not be accepted.

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

FOR CONSTRUCTION CONTRACT - 9

ARTICLE 15—MODIFICATION AND WITHDRAWAL OF PROPOSAL

15.01 An unopened Proposal may be withdrawn by an appropriate document duly executed in the same manner that a Proposal must be executed and delivered to the place where Proposals are to be submitted prior to the date and time for the opening of Proposals.

15.02 If a Proposer wishes to modify its Proposal prior to Proposal opening, Proposer must withdraw its initial Proposal in the manner specified in Paragraph 15.01 herein and submit a new Proposal prior to the date and time for the opening of Proposals.

15.03 If within twenty-four (24) hours after Proposals are opened any Proposer files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Proposal, the Proposer may withdraw its Proposal, and the Proposal security will be returned. Thereafter, if the Work is reissued for Proposal, the Proposer will be disqualified from further Proposal on the Work.

ARTICLE 16— PROTEST PROCEDURES

16.01 These protest procedures apply to procurement of goods, services, or public works by the City of Kyle, including those where federal funds are used in whole or part. These procedures are also applicable to recipients of grants awarded by the City of Kyle who intend to provide such funds to subrecipients. This protest process does not create due process rights but provides an avenue for bidders/proposers to raise concerns about actions related to a bid or competitive solicitation process.

16.02 The City’s Procurement Division of Administrative Services has the authority to settle or resolve any alleged deficiencies or protests. Protests must follow the specific procedures outlined below.

Failure to comply with these requirements may result in the dismissal of the protest by the Procurement Officer.

16.03 The City of Kyle will only consider protests related to the following issues:

A. Violation of local, state, or federal regulations.

B. Issues with the solicitation document that result in an unfair advantage or an unlevel playing field.

C. Errors in the tabulation or evaluation of bids or proposals.

16.04 Protest Process

A. Timeframe: A protest must be submitted in writing to the City of Kyle's Procurement Division within five (5) business days after the date the protestor was notified of the award decision or non-award notice. If the protestor fails to submit the protest within this timeframe, the protest will be considered waived.

B. Method: Protests must be submitted in writing to:

City of Kyle Procurement Division

100 W. Center Street

Kyle, Tx 78640

C. Protest Contents: The protest must include:

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

FOR CONSTRUCTION CONTRACT - 10

1. Name, address, and contact information of the protestor

2. Solicitation number and name of the solicitation

3. A clear statement of the grounds for the protest, including facts, legal theory, and specific references to relevant solicitation provisions.

4. A detailed explanation of the relief or remedy sought.

5. Signature of the protestor or their representative, including evidence of authority to sign

D. Acknowledgement of Protest: Upon receipt of the protest, the Procurement Division will acknowledge the receipt within three (3) business days and will provide the protestor with timeline of the internal review schedule.

E. Review of Protest

1. The Purchasing Department, along with legal counsel or other designated City officials, will review the protest.

2. The City may request additional information from the protestor, the awarded vendor, or any other parties involved in the procurement process.

3. The review process is intended to determine if the protest has merit and if any procedural errors, legal violations, or issues occurred during the procurement process.

F. Resolution of Protest

1. Protest Decision: The Procurement Division will issue a written decision within fifteen

(15) business days of receiving the protest. This decision will include:

a. A summary of the protest.

b. The analysis of the protest’s grounds.

c. A determination as to whether the protest is upheld or denied.

2. Possible Outcomes:

a. If the protest is upheld, the City may:

1) Re-evaluate the bid or proposals.

2) Re-open the procurement process if necessary.

3) Modify the award decision or take corrective action.

b. If the protest is denied, the original award decision will stand, and no changes will be made to the procurement process.

G. Impact on Award of Contract

1. The City reserves the right to delay the contract award until the protest is resolved.

2. If the City determines that the protest is valid and that the award decision was incorrect, the City may cancel the contract award, re-evaluate bids, or take any necessary corrective actions.

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

FOR CONSTRUCTION CONTRACT - 11

3. While a protest is pending, the City generally will not make an award until the protest has been resolved. However, the City may proceed with an award if the City Manager or Procurement Officer determines that:

a. The City urgently needs the supplies or services, or

b. Delay in making an award would unduly impact the delivery or performance of services.

H. Federal Agency Review: If federal funds are involved, the protestor must exhaust all administrative remedies within the City’s protest process before appealing to the appropriate federal agency. The federal agency review will be limited to:

1. Violations of applicable federal law or regulations; and

2. Violations of the City’s protest procedures, including failure to review the protest.

I. Finality of Decision: The decision by the City of Kyle, through the Procurement Division or its designated representative, is final and binding.

ARTICLE 17—OPENING OF PROPOSALS

17.01 Proposals will be opened at the time and place indicated in the advertisement or invitation to Proposers and, unless obviously non-responsive, read aloud publicly.

ARTICLE 18—PROPOSALS TO REMAIN SUBJECT TO ACCEPTANCE

18.01 All Proposals will remain subject to acceptance for the period of time stated in the Proposal Form, but Owner may, in its sole discretion, release any Proposal and return the Proposal security prior to the end of this period.

ARTICLE 19—EVALUATION OF PROPOSALS AND AWARD OF CONTRACT

19.01 Owner reserves the right to reject any or all Proposals, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Proposals and to reject the Proposal of any Proposer if Owner believes that it would not be in the best interest of the Project to make an award to that Proposer, whether because the Proposal is not responsive or the Proposer is unqualified or of doubtful financial ability. Owner also reserves the right to waive all minor Proposal informalities not involving price, time, or changes in the Work.

A. More than one Proposal for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Proposer has an interest in more than one Proposal for the Work may be cause for disqualification of that Proposer and the rejection of all Proposals in which that Proposer has an interest.

19.02 Owner reserves the right to reject the Proposal of any Proposer that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

19.03 If Proposer purports to add terms or conditions to its Proposal, takes exception to any provision of the Proposal Documents, or attempts to alter the contents of the Contract Documents for

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

FOR CONSTRUCTION CONTRACT - 12

purposes of the Proposal, whether in the Proposal itself or in a separate communication to Owner or Engineer, then Owner may reject the Proposal as nonresponsive.

19.04 If Owner awards the contract for the Work, such award will be to the responsible Proposer submitting the highest scoring Proposal.

19.05 Evaluation of Proposals

A. In evaluating Proposals, Owner will consider whether the Proposals comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Proposal Form or prior to the Notice of Award.

19.06 In evaluating whether a Proposer is responsible, Owner will consider the qualifications of the Proposer and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Proposal Documents.

The Selection Criteria shall total One Hundred (100) Points for the base score, with an additional Ten (10) Points available through the optional interview. Only Proposers considered qualified to perform the work, on the basis of their written Proposal, may be invited for interviews. The Selection Criteria consist of the items described below. Some of the requirements listed below expand information requested in these Proposal Documents. The Owner reserves the right to verify all information by contacting parties from current or past projects listed.

A. Values of Selection Criteria

1. Contract Price – 50 Points

2. Contractor’s Experience and Qualifications – 30 Points

3. Proposed Schedule – 20 Points

4. Interview (Optional) – 10 Points

B. Selection Criteria Information

1. Contract Price (50 Points)

Proposer must submit the proposed Contract Price, as required in Section 00400 – Proposal Form for Construction Contract. The Contract Price shall be considered but shall not be the sole determining factor. The Owner shall have the right to accept alternates in any order or combination unless otherwise specifically provided in the Proposal Documents. The Owner shall have the right to consider Proposer’s capacity to perform the Work required for the Project at the proposed Contract Price based upon Contractor’s financial stability, current and past projects, and other information submitted per Section 00400 – Qualifications Statement.

2. Contractor’s Experience and Qualifications (30 Points)

Proposer’s experience and qualifications as a general contractor with specific experience in construction projects of the same or similar type, size, nature and class as the Project being proposed shall be considered. Consideration may be given to the number of years of experience, number of projects performed of similar type, safety record, and other information submitted per Section 00400 – Qualifications Statement.

The Owner will evaluate the projects submitted by the Proposer to determine relevancy to the specified scope of Work of this Project and review the Proposer’s performance on such projects. The Owner may contact listed references, owners of previously

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

FOR CONSTRUCTION CONTRACT - 13

completed or ongoing projects, and other relevant parties to verify information and performance. Subcontractors’ and Suppliers’ safety records and specific experience in construction projects of the same or similar type, size, nature and class as the Project being proposed may also be considered in Owner’s evaluation.

3. Proposed Schedule (20 Points)

Time is of essence to the Owner. The amount of time proposed for construction in Section 00400 – Proposal Form for Construction Contract will influence the number of points awarded to the Proposer for this category. Proposed strategies that can be used to minimize delays, maximize value of Project, avoid unknowns, and proposed areas for possible time savings may also be considered in the scoring process.

4. Interview (Optional) (10 Points)

The Owner may determine that it is necessary to interview Proposers prior to selecting a Successful Proposer. Only Proposers considered qualified to perform the work, on the basis of their written Proposal, may be invited for interviews. The Owner reserves the right to determine whether interviews will be conducted for this RFP, and the number of Proposers to be interviewed. The Owner may consider significant gaps in point separation between the top ranked Proposers in determining the number of Proposers to be interviewed. Owner reserves the right to conduct interviews in other cases where Owner believes it is in the best interest of the Owner.

19.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Proposer and any proposed Subcontractors or Suppliers.

19.08 If the contract is to be awarded, Owner will give Successful Proposer a Notice of Award within ninety (90) days after the day of the Proposal opening.

19.09 The Texas Ethics Commission adopted the attached Conflict of Interest Questionnaire (Form CIQ) pursuant to Texas Local Government Code Chapter 176, as amended. Proposer shall complete Form CIQ, attached to the Proposal Form, as part of its Proposal.

19.10 Provision of Texas Ethics Commission Form 1295 (“TEC Form 1295”) by Proposers: Effective January 1, 2016, pursuant to Texas Government Code § 2252.908 (the “Interested Party Disclosure Act” or the “Act”), the Owner may not award the contract to a Proposer unless the Proposer has provided to the Owner a completed, signed TEC Form 1295 which has been assigned a certificate number by the Texas Ethics Commission (the “TEC”). Pursuant to the rules prescribed by the TEC, the TEC Form 1295 must be completed online through the TEC’s website, assigned a certificate number, printed, signed, and provided to the Owner. The TEC Form 1295 may accompany the Proposal or may be submitted separately but must be provided to the Owner prior to the award of the contract. For purposes of completing the TEC Form 1295, the entity’s name is the City of Kyle; the contract ID number is RFP-2026-076; and the description of goods and services is FOR THE DEVELOPMENT OF A 3.0 MG CONCRETE GROUND STORAGE TANK, PUMP

STATION, AND DISINFECTION ROOM, ALONG WITH THE REHABILITATION OF AN EXISTING 0.5

MG GROUND STORAGE TANK. ASSOCIATED IMPROVEMENTS INCLUDE BASE AND PAVEMENT,

GRADING, DRAINAGE, UTILITIES, SITE RESTORATION, AND RELATED APPURTENANCES. Neither the Owner nor its consultants have the ability to verify the information included in a TEC Form 1295, and

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

FOR CONSTRUCTION CONTRACT - 14

neither have an obligation nor undertake responsibility for advising any Proposer with respect to the proper completion of the TEC Form 1295.

ARTICLE 20—BONDS AND INSURANCE

20.01 Article 6 of the General Conditions, as modified, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Proposer delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

20.02 Article 8, Proposal Security, of these Instructions, addresses any requirements for providing bid bonds as part of the Proposal process.

ARTICLE 21—SIGNING OF AGREEMENT

21.01 When Owner issues a Notice of Award to the Successful Proposer, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within ten (10) days thereafter, Successful Proposer must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner.

ARTICLE 22—SALES AND USE TAXES

22.01 The Owner is tax exempt under Tax code, Subtitle E. SALES, EXCISE, AND USE TAXES, Section 151.309.

ARTICLE 23—RETAINAGE

23.01 Retainage shall be withheld as set forth in the Contract Documents.

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

FOR CONSTRUCTION CONTRACT - 15

FORM OF BID BOND

Surety Bond No.

STATE OF TEXAS §

COUNTY OF §

KNOW ALL MEN BY THESE PRESENTS:

That we, ______________________________________________________, as Principal, and ______________________________, as Surety, are hereby held and firmly bound unto ___________, as Obligee, and its successors and assigns, in the Penal Sum of five percent (5%) of_____________ and __/100 Dollars ($________), the Total Proposal Price, a total Penal Sum of _____________________ and __/100 Dollars ($________), for the Project defined herein below, for payment whereof the said Principal and Surety bind themselves, their heirs, executors, administrators, and successors, jointly and severally, firmly by these presents.

THE CONDITIONS OF THIS OBLIGATION ARE SUCH THAT:

WHEREAS the Principal has submitted to the Obligee a certain Proposal in response to a Request for Proposals, attached hereto and hereby made a part hereof to enter into a contract in writing, for the construction of the _________________ to be located in Kyle, Texas (the “Project”).

NOW THEREFORE, the condition of this obligation is such that, if said Proposal shall be accepted by Obligee and if the Principal fails to execute and deliver a contract in the form of Contract specified in the Proposal Documents (properly completed in accordance with said contract as such contract may be modified by Principal and Obligee during contract negotiations) or fails to deliver Performance and Payment Bonds within the time required by the Contract, to secure the performance of the terms and conditions of the Contract, the Principal and Surety will pay the Obligee (i) the difference in money between the amount of the Principal’s Proposal and the amount of the proposal of the offeror next selected by Obligee, and (ii) the amount of the costs Obligee incurs to reselect a contractor for the Project, but in no event shall the Surety’s aggregate liability hereunder exceed the Penal Sum hereof.

PROVIDED, FURTHER, that this Bid Bond is effective for the term of six (6) months from the time of its execution and will be deemed to be automatically extended without amendment for six (6) months from the expiry date hereof, or any future expiration date, unless at least sixty (60) days prior to any expiration date Surety notifies Obligee by registered mail, at the address for notices to oblige set forth in the Contract, that it elects not to extend the term of this Bid Bond for any additional period.

[Signature Page Follows]

City of Kyle LEHMAN RD PUMP STATION

IMPROVEMENTS

November 9th, 2026

Issued for Bid WGI, Inc.00400 - FORM OF BID BOND - 1

IN WITNESS WHEREOF, the above bounden parties have executed this instrument under their several seals this ___________ day of ____________________________ in the year ______, the name and corporate seal of each corporate party being hereto affixed, and these presents duly signed by its undersigned representative pursuant to authority of its governing body.

(SEAL)

Principal

ATTEST:

By: By:

(Typed Name and Title) (Typed Name and Title)

(SEAL)

Surety

ATTEST:

By: By:

(Typed Name and Title) (Typed Name and Title)

November 9th, 2026

Issued for Bid WGI, Inc.00400 - FORM OF BID BOND - 2

QUALIFICATIONS STATEMENT

ARTICLE 1 - GENERAL INFORMATION

1.01 By signing and submitting this proposal, Proposer acknowledges that they have inspected the Specifications, Drawings, and other Contract Documents, are capable and willing to perform and provide the required services and products, and…