This is a construction proposal document issued by the Louisiana Department of Transportation and Development (DOTD), District 58, for State Project No. H.972538, the Ferriday Maintenance Unit Office Replacement in Concordia Parish, Louisiana. The project involves selective demolition of an existing structure and construction of a new municipal utility office building with related work. Sealed bids will be received until 10:30 a.m. on October 29, 2026, at the District 58 Design Section, 6217 Highway 15 South, Chase, Louisiana, with public opening and reading of bids occurring between 10:30 a.m. and 11:00 a.m. Bids must be submitted in accordance with Section 102 of the 2026 Louisiana Standard Specifications for Roads and Bridges and must include all information required by the proposal. The project engineer is Andrew Moon, and the project manager is Callie Harrell. The entire contract must be completed within 120 calendar days from the Notice to Proceed, with an additional 120-calendar-day assembly period allowed prior to assessment of contract time for preparatory work and material fabrication.

The estimated cost range for this project is $250,000 to $500,000, with the actual estimate value to be published at bid opening for award determination. A bid bond equal to five percent (5%) of the total bid amount is required for bids exceeding $100,000. The contractor must maintain minimum insurance coverage including Workers Compensation with at least $1,000,000 employer liability, Commercial General Liability Insurance, Owner's and Contractor's Protective (OCP) Liability Insurance, and Business Automobile Liability Insurance as specified in Table 107.2-1, with coverage amounts based on the initial contract amount. The contractor may submit the direct cost of OCP insurance for reimbursement without markup, with other required insurance costs included in overhead. Sales and use taxes on purchases related to project work are exempt, pending contractor procurement of a certificate of exemption from the Louisiana Department of Revenue. Bidders must be registered with the Department and in good standing with the Louisiana Secretary of State to be eligible for award.

View the file

Other files

File Type Posted
ladot h.972538 proposal-watermark.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR IN

FORMATIO

NAL PURPOSES O

NLY

B-1

STATE PROJECT NO. H.972538

TABLE OF CONTENTS

Section Page No.

Title Sheet ......................................................................................................................... A-1 Table of Contents .............................................................................................................. B-1 Notice to Contractors ........................................................................................................ C-1/C-2 Special Provisions ............................................................................................................. D-1/ D-5

Technical Specifications .................................................................................................. E-1/E-240

Plans (24 sheets) .............................................................................................................. F-1/F-24 Bid Bond .................................................................................................................... G-1 Schedule of Items ...................................................................................................... H-1 Construction Proposal Signature and Execution Form .............................................. I-1/I-2

C-1

NOTICE TO CONTRACTORS

Sealed bids for construction of the following project will be received by the Louisiana

Department of Transportation and Development (DOTD), District 58 Design Section, 6217

Highway 15 South, Chase, Louisiana 71324 until 10:30 a.m. on October 29, 2026. After

10:30 a.m., bids will be received in the Conference Room, District 58 Administration

Building, 6217 Highway 15 South, Chase, Louisiana 71324 until 11:00 a.m., at which time and place bids will be publicly opened and read. No bids will be received after 11:00 a.m. Any person requiring special accommodations shall notify the Department of Transportation and

Development (DOTD) at (318) 412-3100 not less than 3 business days before bid opening.

CONTROL SECTION NO: 658-30

DESCRIPTION: FERRIDAY MU OFFICE REPLACEMENT

PARISH: CONCORDIA

TYPE: SELECTIVE DEMOLITION AND CONSTRUCTION OF NEW BUILDING AND

RELATED WORK

LIMITS: State Project No. H.972538: FERRIDAY MAINTENANCE UNIT, FERRIDAY, CONCORDIA PARISH, LOUISIANA

ESTIMATED COST RANGE: $250,000-$500,000

The estimated cost range is for informational purposes only and may be subject to change. The bid prices received from bidders will be evaluated based on the actual estimate value, which will be published at bid opening, for award determination.

PROJECT ENGINEER: MOON, ANDREW, 2215 E.E. WALLACE BLVD, FERRIDAY,

LOUISIANA; (318) 727-3832

PROJECT MANAGER: HARRELL, CALLIE; (318) 412-3100

Bids must be submitted in accordance with Section 102 of the 2026 Louisiana Standard

Specifications for Roads and Bridges as amended by the project specifications, and must include all information required by the proposal. Please be advised if your business establishment is the low bidder for this job, you will not be awarded the project if it is found to be “Not in Good

Standing” in the Louisiana Secretary of State database.

Bid Registration and proposals for bidding purposes shall be obtained at District 58 Design

Section, 6217 Highway 15 South, Chase, La. 71324, or by contacting the DOTD; Phone

318-412-3207, FAX (318) 412-3260, or by written requests sent to the Louisiana Department of

Transportation and Development, District 58 Design Section, P. O. Box 110, Chase, LA 71324.

As per Subsection 102.04(e) of the 2016 edition of the Louisiana Standard Specifications for

Roads and Bridges, no bidders will be approved for bid registration within 24 hours before the bid opening. All bidders must register to bid and receive department printed proposals before that deadline. If further information is required, please contact Ms. Victoria Floyd, email:

Victoria.Floyd@la.gov, (318) 412-3207, fax : (318) 412-3260.

FOR IN

FORMATIO

C-2

NOTICE TO CONTRACTORS (CONTINUED)

Construction proposal information may be accessed via the Internet at www.dotd.la.gov. From the LA DOTD home page, select the following options: Doing Business with DOTD, then

Construction Letting Information. Once the Construction Letting Information page appears, find the Notice to Contractors box. From the drop down menu, select the appropriate letting date and press the “Go To button to open the page, which provides a listing of all projects to be let and a Construction Proposal Documents link for each project. Paper copies of the plans are included in the proposal (no additional charge). Plans and specifications may be seen at the

Project Engineer's office. Upon request, the Project Engineer will show the work.

All questions concerning the plans shall be submitted via the Electronic Plans Distribution

Center known as Falcon. All submitted questions will be forwarded by email to the Project

Manager and the Project Engineer. Questions submitted within 96 hours of the bid deadline may not be answered prior to bidding. Falcon may be accessed via the Internet at www.dotd.la.gov.

From the home page, select Doing Business with DOTD from the left-hand menu, then select

Construction Letting Information on the pop-up menu. On the Construction Letting

Information page, select the link, DOTD’s Plan Room; Login to Falcon (or request an ID if a first-time user). Once logged in, you will have access to view Project Information, submit a question concerning the project, and view the plans. To avoid any suggestion that a potential bidder is using the Falcon system to communicate with other potential bidders, DOTD will not post any question or any statement of fact or opinion not made for the purpose of seeking clarification of plans and/or specifications. Any non-questions posted on falcon will be limited to the statement of an issue considered unresolved by a previous DOTD response.

Bidders assume the responsibility for accessing the Apparent Bid Results and final Bid Results on the Construction Letting Information web page located at www.dotd.la.gov/cgi-bin/construction.asp to confirm whether they are the apparent low bidder for any given project.

The award of the contract will be electronically submitted to the successful low bidder on each project.

The Engineer may suspend operations in accordance with 713.08(f).

The U. S. Department of Transportation (DOT) operates a toll free "Hotline" Monday through

Friday, 8:00 a.m. to 5:00 p.m., Eastern Time. Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should call 1-800-424-9071. All information will be treated confidentially and caller anonymity will be respected.

SPECIAL PROVISIONS

D-1

S.P. CONTRACT TIME (01-26):

The entire contract shall be completed in all details and ready for final acceptance in accordance with 105.17.020 within (120) calendar days.

Prior to assessment of contract time, the contractor will be allowed 120 calendar days from the date stipulated in the Notice to Proceed to commence with portions of the contract work including but not limited to assembly periods, preparatory work for materials fabrications such as test piles, or other activities which hinder progress in the beginning stages of construction.

Prior to issuance of the Notice to Proceed, the Department will consider extending the assembly period upon written request from the contractor justifying the need for additional time.

The contractor shall be responsible for maintenance of traffic from the beginning of the assembly period. During the assembly period, the contractor will be allowed to do patching and other maintenance work necessary to maintain the roadway with no time charges when approved by the engineer.

If the contractor begins regular construction operations prior to expiration of the assembly period, the assessment of contract time will commence at the time construction operations are begun.

S.P. GENERAL BIDDING REQUIREMENTS (01-26):

The specifications, contract and bonds governing the construction of the work are the 2026

Edition of the Louisiana Standard Specifications for Roads and Bridges, together with any supplementary specifications and special provisions attached to this proposal.

Bids shall be prepared and submitted in accordance with Section 102 of the Standard

Specifications.

The plans herein referred to are the plans approved and marked with the project number, route and Parish, together with all standard or special designs that may be included in such plans.

The bidder declares that the only parties interested in this proposal as principals are those named herein; that this proposal is made without collusion or combination of any kind with any other person, firm, association, or corporation, or any member or officer thereof; that careful examination has been made of the site of the proposed work, the plans, Standard

Specifications, supplementary specifications and special provisions above mentioned, and the form of contract and payment, performance, and retainage bond; that the bidder agrees, if this proposal is accepted, to provide all necessary machinery, tools, apparatus and other means of construction and will do all work and furnish all material specified in the contract, in the manner and time therein prescribed and in accordance with the requirements therein set forth; and agrees to accept as full compensation therefore, the amount of the summation of the products of the quantities of work and material incorporated in the completed project, as determined by the engineer, multiplied by the respective unit prices herein bid.

FOR IN

FORMATIO

D-2

It is understood by the bidder that the quantities given in this proposal are a fair approximation of the amount of work to be done and that the sum of the products of the approximate quantities multiplied by the respective unit prices bid shall constitute gross sum bid, which sum shall be used in comparison of bids and awarding of the contract.

The bidder further agrees to perform all extra and force account work that may be required on the basis provided in the specifications.

The bidder further agrees that within 15 calendar days after the contract has been transmitted to him, he will execute the contract and furnish the Department satisfactory surety bonds.

If this proposal is accepted and the bidder fails to execute the contract and furnish bonds as above provided, the proposal guaranty shall become the property of the Department; otherwise, said proposal guaranty will be returned to the bidder; all in accordance with 103.4.

S.P. Plans and Submittals (06-26)

Section 105.2 of the 2026 Louisiana Standard Specifications for Roads and Bridges has been amended to delete and replace the first paragraph as follows:

105.2 PLANS AND SUBMITTALS

Conform to 801.3.010 for format of plans and submittals.

S.P. PERMITS, LICENSES, TAXES AND INSURANCE (01-26)

Section 107 of the 2026 Louisiana Standard Specifications for Roads is Bridges is amended as follows:

107.2 is deleted and replaced with the following:

107.2 PERMITS, LICENSES, TAXES AND INSURANCE.

Contractors shall procure temporary permits and licenses for the work, pay charges, fees, and taxes, and give notices necessary for lawful prosecution of the work. Contractor, and its subcontractors, shall maintain all licenses and certifications necessary to accomplish the work in accordance with contract requirements and applicable law.

The contractor shall maintain, at a minimum, the following insurance coverage until final acceptance of the contract:

a) Workers Compensation in compliance with state law, with the exception that the contractor’s

Employer liability is to be at least $1,000,000 when work is to be over water and involves maritime exposures. For the coverage provided in this subpart the contractor’s Insurer will have no right of recovery or subrogation against the State of Louisiana or the Louisiana

Department of Transportation and Development.

FOR IN

FORMATIO

D-3

b) For Commercial General Liability Insurance with a combined single limit per occurrence for bodily injury and property damage, the aggregate loss limit must be on a per project basis.

This insurance shall include coverage for bodily injury and property damage, and include coverage for Premises-Operation; Broad form Contractual Liability; Products and Completed

Operation; Use of Contractors and Subcontractors; Personal Injury; Broad form Property

Damage; and Explosion, Collapse and Underground (XCU) coverage. The required combined single limit amount of insurance shall be as provided in Table 107.2-1.

When a railroad is within the project limits, the combined single limit amount of Commercial

General Liability Insurance shall be as required by the railroad or as provided in Table 107-

1, whichever is greater.

c) A separate Owner’s and Contractor’s Protective Liability (OCP) Policy shall be furnished by the contractor naming the Louisiana Department of Transportation and Development as the named insured. The policy period of the OCP insurance shall extend through final acceptance of the project. The required combined single OCP limit amount shall be as provided in Table 107.2-1.

d) For Business Automobile Liability Insurance with a combined single limit per occurrence for bodily injury and property damage, this insurance shall include bodily injury and property damage coverage for owned automobiles, hired automobiles and non-owned automobiles.

The required combined single limit amount of insurance shall be as provided in Table 107.2-

1 below.

Table 107.2-1

Insurance Requirements1

Initial Contract

Amount

Occurrence

Minimum Aggregate

Ultrahazardous

Aggregate

Up to $1 $1 $2 $3

From >$1 to $2 $2 $4 $6

Over $2 $5 $10 $15 1 $ in millions.

Aggregate coverage for projects with ultrahazardous activities shall be triple the occurrence minimum. Ultrahazardous activities include pile driving; transportation, use, storage, or removal of explosives, radioactive materials, or particularly hazardous or volatile chemicals; and asbestos or lead paint abatement; but does not include vibratory installation of sheet piles.

Each policy shall include provisions stipulating that the insurance company(ies) shall have no recourse against the State of Louisiana and the Department for payment of any premiums or for assessments under any form of the policy and that any and all deductibles in the above described insurance policy(ies) shall be assumed by and be at the sole risk of the contractor.

Insurance is to be placed with insurance companies authorized in the State of Louisiana with an

A. M. Best’s rating of A-: VI or higher. This rating requirement may be waived for Workers

Compensation coverage only.

Should any policies be canceled, the contractor shall immediately notify the Department.

FOR IN

FORMATIO

D-4

Upon failure of the contractor to furnish, deliver and maintain such insurance for itself as required, this contract, at the election of the Department, may be immediately declared suspended, discontinued or terminated. Upon failure of the contractor to maintain OCP insurance at any time prior to final acceptance of the project, work on this contract shall be immediately suspended until proof of such insurance is presented to and accepted by the

Department’s Project Control unit. During a suspension caused by the lack of any required insurance, contractual time charges will continue to be assessed against contract time, as will any assessment of stipulated damages, without interruption.

Failure of the contractor to maintain any required insurance shall not relieve the contractor from any liability under the contract, nor shall the insurance requirements be construed to conflict with the obligations of the contractor concerning indemnification under 107.17.

The contractor is responsible for requiring and verifying that all subcontractors working on the project maintain appropriate types and levels of insurance coverage.

Purchases related to work performed for this Project are exempt from sales and use taxes.

Prior to claiming the exemption, the general contractor or its subcontractor shall obtain a certificate of exemption from the secretary of the Department of Revenue at Louisiana

Department of Revenue, Taxpayer Compliance - SES Division, Phone: (855) 307-3893, Email:

LDRSales.ExemptionApplications@la.gov.

107.2.010 REIMBURSEMENT OF OCP INSURANCE:

Contractor may submit the direct cost of OCP insurance (only) to the Department for reimbursement. The provisions of 109.4 shall not apply to this reimbursement. The cost of all other required insurance must be included in contractor’s overhead applied to all other bid items.

The Department will reimburse the actual cost of OCP coverage as shown on an invoice produced by the insurance company or broker issuing the invoice in the amount of the premium due for the OCP policy: a) without a markup for profit or indirect costs including indirect costs associated with procurement of the OCP insurance; and b) less charges in the amount of a tax from which the Department is exempt and other related incidental fees.

Contractor will be responsible for submitting a written request for reimbursement of the amount of the OCP policy premium invoice less all such charges including surplus lines taxes and other incidental fees. The Contractor shall contact the Louisiana Department of

Insurance, ldi.la.gov, to receive additional guidance.

Contractor must also submit an original sworn affidavit from the insurance producer/agent in which that person attests that the submitted invoice is for the required OCP coverage only, and that the invoice accurately reports the cost to contractor of that coverage. The invoice and affidavit may be submitted at the preconstruction conference or thereafter for inclusion with a partial estimate.

There will be no reimbursement for any purchase of OCP insurance policy extensions necessitated by concurrent; non-excusable; or excusable, non-compensable delays in completion of the project, whenever such delays occur, or for claimed utility delays where such days were not added to Contract Time by change order. Any policy extensions necessitated by excusable, compensable delays will be reimbursed on a pro-rata monthly basis.

FOR IN

FORMATIO

D-5

S.P. COMPENSATION FOR

ALTERATIONS OF THE CONTRACT (07-26)

109.4 of the 2026 Louisiana Standard Specifications for Roads and Bridges is amended as follows:

109.4.030.B. is deleted and replaced with the following:

B. Direct Materials

For materials accepted by the engineer and used, the contractor shall receive the actual cost of such materials delivered to the work, including transportation charges if applicable and sales taxes subject to the requirements of 107.2.

109.4.030.C.3. is deleted and replaced with the following:

3. Operating Cost

When internal rates are used for cost recovery, equipment operating cost will be reimbursed for the actual hours used in work. Intermittent breaks throughout the day will not be deducted while the equipment is dedicated solely to the force account work. When using guide book rental rates, only the operating cost will be reimbursed at an hourly rate over 8-hours per day. Reimbursement will stop when the equipment is no longer needed.

Pickups for superintendents and employee transport are non-compensable; when directly used in performance of the work, pickups will be reimbursed at $150/day with no markup.

The cost of service trucks and other support equipment will be considered compensable.

Standby will be reimbursed as follows, with a maximum reimbursement of 8-hours per day, 40-hours per week, and 22-days per month:

Standby will not be reimbursed for periods when the equipment would ordinarily be idle (weekends, holidays, adverse weather, periods of repair and maintenance)

E-1

E-2

G-1

BID BOND

______________________________________________________________________, as Principal

(Bidder) and

___________________________________________________________________________, as Surety, are bound unto the State of Louisiana, Department of Transportation and Development, (hereinafter called the Department) in the sum of five percent (5%) of the bidder’s total bid amount as calculated by the Department for payment, of which the Principal and Surety bind themselves, their heirs, executors, administrators, successors and assigns, as solidary obligors.

Signed and sealed this ___________ day of ____________________________, 20_____.

The condition of this obligation is such that, whereas the Principal has submitted a bid to the

Department on a contract for the construction of STATE PROJECT NO. H.972538, FERRIDAY

MU OFFICE REPLACEMENT, FERRIDAY, CONCORDIA PARISH, LOUISIANA, if the bid is accepted and the Principal, within the specified time, enters into the contract in writing and gives bond with Surety acceptable to the Department for payment and performance of said contract, this obligation shall be void; otherwise to remain in effect.

Principal (Bidder or First Partner to Joint Venture)

If a Joint Venture, Second Partner

By

By

Authorized Officer-Owner-Partner

Authorized Officer-Owner-Partner

Typed or Printed Name

Surety

By (Seal)

Agent or Attorney-in-Fact

To receive a copy of the contract and subsequent correspondence / communication from LA DOTD, with respect to the bid bonds, the following information must be provided:

Bonding Agency or Company Name Address

Agent or Representative Phone Number / Fax Number

Form CS-2A

01/26

A Bid Bond is required when the bidder’s total bid amount as calculated by the Department in accordance with Subsection 103.01 is greater than $100,000. (See Section 102 of the

Specifications.)

FOR IN

FORMATIO

H-1

I-1

CONSTRUCTION PROPOSAL SIGNATURE AND EXECUTION FORM

THIS FORM, THE SCHEDULE OF ITEMS, AND THE PROPOSAL GUARANTY MUST BE COMPLETED AS INDICATED AND SUBMITTED

TO THE LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT (DOTD) TO CONSTITUTE A VALID BID

STATE PROJECT NO.

H.972538

FEDERAL AID PROJECT NO.

NAME OF PROJECT

FERRIDAY MU OFFICE REPLACEMENT

I (WE) HEREBY CERTIFY THAT I (WE) HAVE CAREFULLY EXAMINED THE PROPOSAL, PLANS AND SPECIFICATIONS, INCLUDING ANY AND ALL ADDENDA, AND THE SITE OF THE ABOVE PROJECT AND AM (ARE) FULLY COGNIZANT OF ALL PROPOSAL

DOCUMENTS, THE MASTER COPY OF WHICH IS ON FILE AT DOTD HEADQUARTERS IN BATON ROUGE, LA., AND ALL WORK, MATERIALS AND LABOR REQUIRED THEREIN, AND AGREE TO PERFORM ALL WORK, AND SUPPLY ALL NECESSARY MATERIALS

AND LABOR REQUIRED FOR SUCCESSFUL AND TIMELY COMPLETION OF THE ABOVE PROJECT AND TO ACCEPT THE SUMMATION

OF THE PRODUCTS OF THE UNIT PRICES BID ON THE SCHEDULE OF ITEMS ATTACHED HERETO AND MADE A PART HEREOF

MULTIPLIED BY THE ACTUAL QUANTITY OF UNIT OF MEASURE PERFORMED FOR EACH ITEM, AS AUDITED BY DOTD, AS FULL

AND FINAL PAYMENT FOR ALL WORK, LABOR AND MATERIALS NECESSARY TO COMPLETE THE ABOVE PROJECT, SUBJECT TO

INCREASE ONLY FOR PLAN CHANGES (CHANGE ORDERS) APPROVED BY THE DOTD CHIEF ENGINEER OR HIS DESIGNEE. THIS BID IS SUBMITTED IN ACCORDANCE WITH THE GENERAL BIDDING REQUIREMENTS IN THE CONSTRUCTION PROPOSAL AND ALL

SPECIAL PROVISIONS, PLANS, SUPPLEMENTAL SPECIFICATIONS, AND THE LOUISIANA STANDARD SPECIFICATIONS FOR ROADS

AND BRIDGES (2016 EDITION). I (WE) UNDERSTAND THAT THE SUMMATION OF THE PRODUCTS OF THE UNIT PRICES BID ON THE

SCHEDULE OF ITEMS MULTIPLIED BY THE ESTIMATED QUANTITY OF UNIT OF MEASURE FOR EACH ITEM, ALONG WITH ANY

OTHER FACTORS SPECIFIED TO BE APPLICABLE SUCH AS CONSTRUCTION TIME AND/OR LANE RENTAL, SHALL BE THE BASIS FOR

THE COMPARISON OF BIDS. I (WE) UNDERSTAND THAT THE SCHEDULE OF ITEMS MUST CONTAIN UNIT PRICES WRITTEN OUT IN

WORDS AND THAT THE SCHEDULE OF ITEMS SUBMITTED AS PART OF THIS BID IS ON THE FORM SUPPLIED BY DOTD IN THE BID PROPOSAL. MY (OUR) PROPOSAL GUARANTY IN THE AMOUNT SPECIFIED FOR THE PROJECT IS ATTACHED HERETO AS EVIDENCE

OF MY (OUR) GOOD FAITH TO BE FORFEITED IF THIS BID IS ACCEPTED BY DOTD AND I (WE) FAIL TO COMPLY WITH ANY

REQUIREMENT NECESSARY FOR AWARD AND EXECUTION OF THE CONTRACT, AS WELL AS, SIGN AND DELIVER THE CONTRACT

AND PAYMENT/PERFORMANCE/RETAINAGE BOND AS REQUIRED IN THE SPECIFICATIONS.

NONCOLLUSION DECLARATION (APPLICABLE TO FEDERAL-AID PROJECTS)

I (WE) DECLARE UNDER PENALTY OF PERJURY UNDER THE LAWS OF THE UNITED STATES AND THE STATE OF LOUISIANA THAT I (WE) HAVE

NOT DIRECTLY OR INDIRECTLY, ENTERED INTO ANY AGREEMENT, PARTICIPATED IN ANY COLLUSION, OR OTHERWISE TAKEN ANY ACTION IN

RESTRAINT OF FREE COMPETITIVE BIDDING IN CONNECTION WITH THE CONTRACT FOR THIS PROJECT NOR VIOLATED LA. R.S. 48:254.

BIDDER'S DBE GOAL STATEMENT (APPLICABLE TO DBE GOAL PROJECTS)

IF THIS PROJECT IS DESIGNATED BY SPECIAL PROVISION AS A DISADVANTAGED BUSINESS ENTERPRISE (DBE) GOAL PROJECT IN ACCORDANCE

WITH THE DBE PROVISIONS OF THIS CONTRACT, THE BIDDER ASSURES DOTD THAT HE/SHE WILL MEET OR EXCEED THE DBE CONTRACT GOAL, OR IF THE BIDDER CANNOT MEET THE REQUIRED DBE GOAL, THE BIDDER ASSURES DOTD THAT HE/SHE HAS MADE AND CAN DOCUMENT GOOD

FAITH EFFORTS MADE TOWARDS MEETING THE GOAL REQUIREMENT IN ACCORDANCE WITH THE CONTRACT AND DBE PROGRAM MANUAL

INCORPORATED HEREIN BY REFERENCE.

THE APPARENT LOW BIDDER SHALL COMPLETE AND SUBMIT TO THE DOTD COMPLIANCE PROGRAMS OFFICE, FORM CS-6AAA AND

ATTACHMENT(S) AND, IF NECESSARY, DOCUMENTATION OF GOOD FAITH EFFORTS MADE BY THE BIDDER TOWARD MEETING THE GOAL, WITHIN SEVEN CALENDAR DAYS AFTER THE OPENING OF BIDS FOR THIS PROJECT. RESPONSIVENESS OF INFORMATION SUPPLIED IN THIS

SECTION OF THIS CONSTRUCTION PROPOSAL SIGNATURE AND EXECUTION FORM IS GOVERNED BY THE DBE REQUIREMENTS INCLUDED WITHIN

THE SPECIFICATIONS AND DBE PROGRAM MANUAL.

CERTIFICATION OF EMPLOYMENT OF LOUISIANA RESIDENTS TRANSPORTATION INFRASTRUCTURE MODEL

FOR ECONOMIC DEVELOPMENT (TIME) PROJECTS (APPLICABLE TO TIME PROJECTS)

IF THIS PROJECT IS DESIGNATED BY SPECIAL PROVISION AS A TRANSPORTATION INFRASTRUCTURE MODEL FOR ECONOMIC DEVELOPMENT

(TIME) PROJECT AS DEFINED IN ACT NO. 16 OF THE 1989 FIRST EXTRAORDINARY SESSION OF THE LEGISLATURE WHICH ENACTED PART V OF

CHAPTER 7 OF SUBTITLE II OF TITLE 47 OF THE LOUISIANA REVISED STATUTES OF 1950, COMPRISED OF R.S. 47:820.1 THROUGH 820.6.

THE BIDDER CERTIFIES THAT AT LEAST 80 PERCENT OF THE EMPLOYEES EMPLOYED ON THIS TIME PROJECT WILL BE LOUISIANA RESIDENTS IN

ACCORDANCE WITH LOUISIANA R.S. 47:820.3.

NON PARTICIPATION IN PAYMENT ADJUSTMENT (ASPHALT CEMENT AND FUELS) STATEMENT

IF THIS PROJECT IS DESIGNATED BY SPECIAL PROVISION AS BEING SUBJECT TO PAYMENT ADJUSTMENT FOR ASPHALT CEMENT AND/OR FUELS, THE BIDDER HAS THE OPTION OF REQUESTING EXCLUSION FROM SAID PAYMENT ADJUSTMENT PROVISIONS THAT ARE ESTABLISHED BY

SPECIAL PROVISION ELSEWHERE HEREIN.

IF THE BIDDER DESIRES TO BE EXCLUDED FROM THESE PAYMENT ADJUSTMENT PROVISIONS,

THE BIDDER IS REQUIRED TO MARK HERE

FAILURE TO MARK THIS BOX PRIOR TO BID OPENING WILL CONSTITUTE FORFEITURE OF THE BIDDER'S OPTION TO REQUEST EXCLUSION.

CS-14A

FOR IN

FORMATIO

I-2

BIDDER SIGNATURE REQUIREMENTS (APPLICABLE TO ALL PROJECTS)

THIS BID FOR THE CAPTIONED PROJECT IS SUBMITTED BY:

Name of Principal (Individual, Firm, Corporation, or Joint Venture)

If Joint Venture, Name of First Partner

(Louisiana Contractor's License Number of Bidder or First Partner to

Joint Venture)

(Business Street Address)

(Business Mailing Address, if different)

(Area Code and Telephone Number of Business)

(Telephone Number and Name of Contact Person)

(Telecopier Number, if any)

If Joint Venture, Name of Second Partner

(Louisiana Contractor's License Number of Second Partner to Joint

Venture)

(Business Street Address)

(Business Mailing Address, if different)

(Area Code and Telephone Number of Business)

(Telephone Number and Name of Contact Person)

(Telecopier Number, if any)

ACTING ON BEHALF OF THE BIDDER, THIS IS TO ATTEST THAT THE UNDERSIGNED DULY AUTHORIZED REPRESENTATIVE OF THE

ABOVE CAPTIONED FIRM, CORPORATION OR BUSINESS, BY SUBMISSION OF THIS BID, AGREES AND CERTIFIES THE TRUTH AND

ACCURACY OF ALL PROVISIONS OF THIS PROPOSAL, INCLUSIVE OF THE REQUIREMENTS, STATEMENTS, DECLARATIONS AND

CERTIFICATIONS ABOVE AND IN THE SCHEDULE OF ITEMS AND PROPOSAL GUARANTY. EXECUTION AND SIGNATURE OF THIS

FORM AND SUBMISSION OF THE SCHEDULE OF ITEMS AND PROPOSAL GUARANTY SHALL CONSTITUTE AN IRREVOCABLE AND

LEGALLY BINDING OFFER BY THE BIDDER.

(Signature)

(Printed Name)

(Title)

(Date of Signature)

(Signature)

(Printed Name)

(Title)

(Date of Signature)

CONTRACTOR'S TOTAL BASE BID $ _____________________________________________

IT IS AGREED THAT THIS TOTAL, DETERMINED BY THE BIDDER, IS FOR

PURPOSES OF OPENING AND READING BIDS ONLY, AND THAT THE LOW BID FOR THIS

PROJECT WILL BE DETERMINED FROM THE EXTENSION AND TOTAL OF THE BID ITEMS BY DOTD.