This is a construction proposal document issued by the Louisiana Department of Transportation and Development (LA DOTD) for State Project No. 4400036338, a cross drain replacement project located on LA 39, approximately 1,800 feet north of LA 46 in St. Bernard Parish. The project involves removal and replacement of a cross drain and asphalt patching within a 0.003-mile section between control station line marks 10.723 and 10.726. Electronic bids will be accepted through www.bidx.com until 10:00 a.m. on Tuesday, September 15, 2026, with results posted online immediately thereafter. Contractors must be licensed under LA R.S. 37:2150-2192 for Highway, Streets, and Bridge Construction and must complete online bidder registration prior to submission; registration closes 24 hours before the bid opening. The contract requires completion within 30 working days following a 30-calendar-day assembly period from the Notice to Proceed. Key project personnel include ADA Construction contact Mr. Corbett Hollier (504-376-0210), Project Engineer Mr. Mahmoud Hamide (504-253-6131), and Project Manager Ms. Brittany Rooney (504-376-0250).
The estimated cost range is $50,000 to $100,000, provided for informational purposes only, with actual award determination based on the published estimate value at bid opening. Contractors must maintain comprehensive insurance coverage including Workers Compensation with minimum $1,000,000 employer liability, Commercial General Liability with combined single limits specified in Table 107.2-1 based on contract amount, Owner's and Contractor's Protective liability, and Business Automobile Liability. All insurance must be placed with companies holding A.M. Best ratings of A-: VI or higher. The project is designated for payment adjustments for asphalt cements, fuels, and steel in accordance with Section 109.9, with base price indices established at bid opening. Work must comply with the 2026 Louisiana Standard Specifications for Roads and Bridges and all special provisions, including traffic maintenance requirements mandating one-lane paving operations with specific restrictions during holiday periods and weather events. No lane closures are permitted during specified holiday periods including Mardi Gras, Independence Day, and Thanksgiving, and all such periods are considered excusable, non-compensable delays.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ELECTRONIC COPY - NOT FOR BID SUBMITTAL
STATE PROJCET NO. 4400036338
TABLE OF CONTENTS
Page No.
Title Sheet A-1
Table of Contents B-1
Notice to Contractors C-1 thru C-3
Special Provisions D-1 thru D-108
Plans (9 sheets) E-1 thru E-9
Construction Proposal Information:
Title Sheet F-1
Bid Bond G-1
Schedule of Items H-1 thru H-3
Construction Proposal Signature and Execution Form I-1 thru I-2
B-1
NOTICE TO CONTRACTORS (01/26)
Electronic bids and electronic bid bonds for the following project will be downloaded by the
Louisiana Department of Transportation and Development (LA DOTD) on Tuesday, September
15, 2026 at 10:00 a.m. Paper bids and paper bid bonds will not be accepted. Electronic bids and electronic bid bonds must be submitted through www.bidx.com prior to the electronic bidding deadline. Beginning at 10:00 a.m., all bids will be downloaded and posted online at http://www.dotd.la.gov/cgi-bin/construction.asp. No bids are accepted after 10:00 a.m.
STATE PROJECT NO.4400036338
CONTROL SECTION NO. 046-32
DESCRIPTION: LA 39: CROSS DRAIN REP’L 1800’ N LA 46
ROUTE: LA 39
PARISH: ST. BERNARD
LENGTH: 0.003 miles.
TYPE: REMOVAL AND REPLACEMENT OF CROSS DRAIN AND ASPHALT PATCHING
LIMITS: C.S.L.M 10.723 – C.S.L.M. 10.726
ESTIMATED COST RANGE: $50,000-$100,000
The estimated cost range is for informational purposes only and may be subject to change. The bid prices received from bidders will be evaluated based on the actual estimate value, which will be published at bid opening, for award determination.
ADA CONSTRUCTION: Mr. Corbett Hollier, P.E.; Phone: (504) 376-0210
PROJECT ENGINEER: Mr. Mahmoud Hamide, P.E.; Phone: (504) 253-6131
DOTD COORDINATOR: Ms. Irinia Kourilova, Phone: (504) 376 0254
PROJECT MANAGER: Ms. Brittany Rooney, P.E.; Phone: (504) 376-025
PROJECT CLASSIFICATION
Bids shall be accepted from Contractors who are licensed under LA R.S. 37:2150-2192 for the classification of Highway, Streets, Bridge Construction.
Bids must be prepared and submitted in accordance with Section 102 of the 2026 Louisiana
Standard Specifications for Roads and Bridges as amended by the project specifications, and must include all information required by the proposal.
ONLINE BIDDER REGISTRATION IS FOR ALL PROSPECTIVE BIDDERS AND FOR
OTHERS INTERESTED IN INFORMATION ONLY. Prior to the electronic bid submission deadline, ONLINE BIDDER REGISTRATION for each project bid is REQUIRED. Online Bidder
Registration may be accessed via the Internet at wwwsp.dotd.la.gov. Select the following options:
DOING BUSINESS, then Construction Services, then Bidder Registration.
C-1
When completed, a registration confirmation notice will be displayed and may be printed by the bidder. When approved for bidding, the bidder’s name will be placed on the “List of Prospective
Bidders” located on the LA DOTD Internet website. It is the bidder’s responsibility to review the “List of Prospective Bidders” to ensure approval to bid. If a bidder does not register for a project, the bid will not be accepted by LA DOTD. As per 102.4 e) of the 2026 edition of the
Louisiana Standard Specifications for Roads and Bridges, no bidders will be approved for bid registration within 24 hours before the bid opening. All bidders must register to bid before that deadline. If further information is required, please contact Mr. Alfonzo Simon, email:
Alfonzo.Simon@la.gov, (225) 379-1111, fax: (225) 379-1857.
Plans and bid proposals are available in electronic format ONLY. All Plans, Proposals, Addenda, Amendments, Letters of Clarification, and Withdrawal Notices will be posted online. Paper notices will not be distributed.
Construction bid proposals (includes specifications) and plans may be accessed via the Internet at wwwsp.dotd.la.gov. To receive update notifications on specific projects, ONLINE BIDDER
REGISTRATION is required. From the LA DOTD home page, select the following options:
DOING BUSINESS, then Construction Services, then Construction Letting Info. Once the
Construction Letting Information page appears, find the Notice to Contractors box. From the drop down menu, select the appropriate letting date and press the “Go To” button to open the page, which provides a listing of all projects to be let and a Construction Proposal Documents link for each project. All project specific notices are found here. It will be the responsibility of the bidder to check for updates. Additionally, plans and specifications may be seen at the Project Engineer's office. Upon request, the Project Engineer will show the project site.
All questions concerning the plans shall be submitted via the Electronic Plans Distribution
Center known as Falcon. All submitted questions will be forwarded by email to the Project
Manager and the Project Engineer. Questions submitted within a period of 96 hours prior to the advertised time for the opening of bids, excluding Saturdays, Sundays, and any other legal holidays, may not be answered prior to bidding. Falcon may be accessed via the Internet at wwwsp.dotd.la.gov. From the home page, select DOING BUSINESS, then Construction
Services, then select Construction Letting Info. On the Construction Letting Information page, select the link, DOTD Plans Room (Falcon); Login to Falcon (or request an ID if a first-time user). Once logged in, you will have access to view Project Information, submit a question concerning the project, and view the plans. To avoid any suggestion that a potential bidder is using the Falcon system to communicate with other potential bidders, DOTD will not post any question or any statement of fact or opinion not made for the purpose of seeking clarification of plans and/or project specifications. Any non-questions posted on falcon will be limited to the statement of an issue considered unresolved by a previous DOTD response.
Bidders assume the responsibility for accessing the Apparent Bid Results and final Bid Results on the Construction Letting Information web page located at http://wwwapps.dotd.la.gov/engineering/lettings/ to confirm whether they are the apparent low bidder for any given project and the specific due date of Form CS-6AAA for SBE Goal Projects.
Apparent Low Bidders on Small Business Element (SBE) Goal Projects shall comply fully with the “Required Contract Provisions for SBE Participation in Federal Aid Construction
Contracts (SBE Goal Project)” contained in Section “E” of the Proposal; and, in accordance
C-2 therewith, Apparent Low Bidders shall submit the completed Form CS-6AAA for SBE
Goal Projects and Attachments to the LA DOTD Compliance Programs Office utilizing the list of SBE Certified Contractors as posted for this letting at:
http://wwwapps.dotd.la.gov/engineering/lettings.
The award of the contract will be electronically submitted to the successful low bidder on each project.
The U. S. Department of Transportation (DOT) operates a toll free "Hotline" Monday through
Friday, 8:00 a.m. to 5:00 p.m., Eastern Time. Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should call 1-800-424-9071. All information will be treated confidentially and caller anonymity will be respected.
C-3
STATE PROJECT NO. 4400036338
SPECIAL PROVISIONS
S.P. CONTRACT TIME (01-26):
The entire contract shall be completed in all details and ready for final acceptance in accordance with 105.17.020 within THIRTY (30) working days.
Prior to assessment of contract time, the contractor will be allowed 30 calendar days from the date stipulated in the Notice to Proceed to commence with portions of the contract work including but not limited to assembly periods, preparatory work for materials fabrications such as test piles, or other activities which hinder progress in the beginning stages of construction.
Prior to issuance of the Notice to Proceed, the Department will consider extending the assembly period upon written request from the contractor justifying the need for additional time.
The contractor shall be responsible for maintenance of traffic from the beginning of the assembly period. During the assembly period, the contractor will be allowed to do patching and other maintenance work necessary to maintain the roadway with no time charges when approved by the engineer.
If the contractor begins regular construction operations prior to expiration of the assembly period, the assessment of contract time will commence at the time construction operations are begun.
S.P. GENERAL BIDDING REQUIREMENTS (01-26):
The specifications, contract and bonds governing the construction of the work are the 2026
Edition of the Louisiana Standard Specifications for Roads and Bridges, together with any supplementary specifications and special provisions attached to this proposal.
Bids shall be prepared and submitted in accordance with Section 102 of the Standard
Specifications.
The plans herein referred to are the plans approved and marked with the project number, route and Parish, together with all standard or special designs that may be included in such plans.
The bidder declares that the only parties interested in this proposal as principals are those named herein; that this proposal is made without collusion or combination of any kind with any other person, firm, association, or corporation, or any member or officer thereof; that careful examination has been made of the site of the proposed work, the plans, Standard
Specifications, supplementary specifications and special provisions above mentioned, and the form of contract and payment, performance, and retainage bond; that the bidder agrees, if this proposal is accepted, to provide all necessary machinery, tools, apparatus and other means of construction and will do all work and furnish all material specified in the contract, in the manner and time therein prescribed and in accordance with the requirements therein set forth; and agrees to accept as full compensation therefore, the amount of the summation of the products of the quantities of work and material incorporated in the completed project, as determined by the engineer, multiplied by the respective unit prices herein bid.
D-1
It is understood by the bidder that the quantities given in this proposal are a fair approximation of the amount of work to be done and that the sum of the products of the approximate quantities multiplied by the respective unit prices bid shall constitute gross sum bid, which sum shall be used in comparison of bids and awarding of the contract.
The bidder further agrees to perform all extra and force account work that may be required on the basis provided in the specifications.
The bidder further agrees that within 15 calendar days after the contract has been transmitted to him, he will execute the contract and furnish the Department satisfactory surety bonds.
If this proposal is accepted and the bidder fails to execute the contract and furnish bonds as above provided, the proposal guaranty shall become the property of the Department; otherwise, said proposal guaranty will be returned to the bidder; all in accordance with 103.4.
S.P. MAINTENANCE OF TRAFFIC (01-26)
Section 104.3 of the 2026 Louisiana Standard Specifications for Roads and Bridges is amended to include the following:
Conduct paving operations on one side of the roadway at a time. The side of the roadway, including shoulder, that is open to traffic shall be clear at all times.
When pavement layers are 2 inches or less, paving will be permitted in one lane for a full day;
the adjacent lane shall be paved the following workday.
When pavement layers are greater than 2 inches thickness, a wedged joint shall be used.
Paving will be permitted in one lane for a full day; the adjacent lane shall be paved the following day or place approximately 1/2 of each day's production in one lane and the remainder in the adjacent lane.
When asphalt concrete pavement is milled 2 inches or less, milling is permitted in one lane for a full day; the adjacent lane shall be milled no later than the following workday. When asphalt concrete pavement is milled more than 2 inches, milling shall be limited to approximately 1/2 of each day's production in one lane and the remainder in the adjacent lane.
All asphalt concrete pavement new construction, overlays, and shoulder surfacing operations open to traffic shall be conducted in accordance with the following requirements:
Shoulder Subgrade Preparation: Any required embankment widening shall be completed before placement of the asphalt concrete overlay. All vegetation shall be removed from existing shoulders before beginning temporary or final shoulder construction. When a shoulder wedge is required, the contractor shall blade and shape existing material to form a uniform surface for the placement of the wedge prior to placement of the asphalt concrete overlay.
Blading and Shaping of Material Adjacent to Pavement: Blading and shaping material adjacent to pavement described herein shall be completed at the end of each day's operations for all asphalt concrete courses. There shall be no drop-off from the pavement edge to the adjacent shoulder or foreslope. The contractor shall blade and shape existing material against, and
D-2 approximately level with, the top of the pavement surfacing to form a uniform slope from the pavement edge to the adjacent existing shoulder, or to a point 10 feet from the pavement edge.
If existing materials are insufficient, the contractor shall furnish, place, and shape additional materials to form the required tie-in or temporary shoulder. Permanent materials and procedures shall be in accordance with contract documents. Existing and/or additional materials placed temporarily shall be to the satisfaction of the Engineer. Compaction shall be by approved methods.
No direct payment will be made for temporary work; payment for permanent materials will be made using the appropriate pay items when additional materials are needed.
Lane closure and work hour restrictions shall be as follows:
All lanes shall remain open to traffic and no work shall be performed except during times when lane closures are allowed. The contractor shall maintain through traffic at all times during construction. All lane closures shall be approved by the Project Engineer. The Project Engineer shall be allowed to stop work and order the opening of any lane closures for special or unforeseen circumstances.
There are no daytime lane closure restrictions aside from the following holiday periods.
No work shall be allowed and all lanes shall be open during New Year’s, Mardi Gras, Easter, Memorial Day, Independence Day, Labor Day, Thanksgiving, Christmas holiday periods, and other events as directed by the Engineer. No work shall be allowed and all lanes shall be open in preparation for weather events such as hurricanes, ice storms, etc, as deemed necessary, or during hurricane evacuation and contra flow operations. These periods shall be considered excusable, non-compensable.
S.P. Plans and Submittals (06-26)
Section 105.2 of the 2026 Louisiana Standard Specifications for Roads and Bridges has been amended to delete and replace the first paragraph as follows:
105.2 PLANS AND SUBMITTALS
Conform to 801.3.010 for format of plans and submittals.
S.P. PERMITS, LICENSES, TAXES AND INSURANCE (01-26)
Section 107 of the 2026 Louisiana Standard Specifications for Roads is Bridges is amended as follows:
107.2 is deleted and replaced with the following:
D-3
107.2 PERMITS, LICENSES, TAXES AND INSURANCE.
Contractors shall procure temporary permits and licenses for the work, pay charges, fees, and taxes, and give notices necessary for lawful prosecution of the work. Contractor, and its subcontractors, shall maintain all licenses and certifications necessary to accomplish the work in accordance with contract requirements and applicable law.
The contractor shall maintain, at a minimum, the following insurance coverage until final acceptance of the contract:
a) Workers Compensation in compliance with state law, with the exception that the contractor’s
Employer liability is to be at least $1,000,000 when work is to be over water and involves maritime exposures. For the coverage provided in this subpart the contractor’s Insurer will have no right of recovery or subrogation against the State of Louisiana or the Louisiana
Department of Transportation and Development.
b) For Commercial General Liability Insurance with a combined single limit per occurrence for bodily injury and property damage, the aggregate loss limit must be on a per project basis.
This insurance shall include coverage for bodily injury and property damage, and include coverage for Premises-Operation; Broad form Contractual Liability; Products and Completed
Operation; Use of Contractors and Subcontractors; Personal Injury; Broad form Property
Damage; and Explosion, Collapse and Underground (XCU) coverage. The required combined single limit amount of insurance shall be as provided in Table 107.2-1.
When a railroad is within the project limits, the combined single limit amount of Commercial
General Liability Insurance shall be as required by the railroad or as provided in Table 107-
1, whichever is greater.
c) A separate Owner’s and Contractor’s Protective Liability (OCP) Policy shall be furnished by the contractor naming the Louisiana Department of Transportation and Development as the named insured. The policy period of the OCP insurance shall extend through final acceptance of the project. The required combined single OCP limit amount shall be as provided in Table 107.2-1.
d) For Business Automobile Liability Insurance with a combined single limit per occurrence for bodily injury and property damage, this insurance shall include bodily injury and property damage coverage for owned automobiles, hired automobiles and non-owned automobiles.
The required combined single limit amount of insurance shall be as provided in Table 107.2-
1 below.
Table 107.2-1
Insurance Requirements1
Initial Contract
Amount
Occurrence
Minimum Aggregate
Ultrahazardous
Aggregate
Up to $1 $1 $2 $3
From >$1 to $2 $2 $4 $6
D-4
Over $2 $5 $10 $15 1 $ in millions.
Aggregate coverage for projects with ultrahazardous activities shall be triple the occurrence minimum. Ultrahazardous activities include pile driving; transportation, use, storage, or removal of explosives, radioactive materials, or particularly hazardous or volatile chemicals; and asbestos or lead paint abatement; but does not include vibratory installation of sheet piles.
Each policy shall include provisions stipulating that the insurance company(ies) shall have no recourse against the State of Louisiana and the Department for payment of any premiums or for assessments under any form of the policy and that any and all deductibles in the above described insurance policy(ies) shall be assumed by and be at the sole risk of the contractor.
Insurance is to be placed with insurance companies authorized in the State of Louisiana with an
A. M. Best’s rating of A-: VI or higher. This rating requirement may be waived for Workers
Compensation coverage only.
Should any policies be canceled, the contractor shall immediately notify the Department.
Upon failure of the contractor to furnish, deliver and maintain such insurance for itself as required, this contract, at the election of the Department, may be immediately declared suspended, discontinued or terminated. Upon failure of the contractor to maintain OCP insurance at any time prior to final acceptance of the project, work on this contract shall be immediately suspended until proof of such insurance is presented to and accepted by the
Department’s Project Control unit. During a suspension caused by the lack of any required insurance, contractual time charges will continue to be assessed against contract time, as will any assessment of stipulated damages, without interruption.
Failure of the contractor to maintain any required insurance shall not relieve the contractor from any liability under the contract, nor shall the insurance requirements be construed to conflict with the obligations of the contractor concerning indemnification under 107.17.
The contractor is responsible for requiring and verifying that all subcontractors working on the project maintain appropriate types and levels of insurance coverage.
Purchases related to work performed for this Project are exempt from sales and use taxes.
Prior to claiming the exemption, the general contractor or its subcontractor shall obtain a certificate of exemption from the secretary of the Department of Revenue at Louisiana
Department of Revenue, Taxpayer Compliance - SES Division, Phone: (855) 307-3893, Email:
LDRSales.ExemptionApplications@la.gov.
107.2.010 REIMBURSEMENT OF OCP INSURANCE:
Contractor may submit the direct cost of OCP insurance (only) to the Department for reimbursement. The provisions of 109.4 shall not apply to this reimbursement. The cost of all other required insurance must be included in contractor’s overhead applied to all other bid items.
D-5
The Department will reimburse the actual cost of OCP coverage as shown on an invoice produced by the insurance company or broker issuing the invoice in the amount of the premium due for the OCP policy: a) without a markup for profit or indirect costs including indirect costs associated with procurement of the OCP insurance; and b) less charges in the amount of a tax from which the Department is exempt and other related incidental fees.
Contractor will be responsible for submitting a written request for reimbursement of the amount of the OCP policy premium invoice less all such charges including surplus lines taxes and other incidental fees. The Contractor shall contact the Louisiana Department of
Insurance, ldi.la.gov, to receive additional guidance.
Contractor must also submit an original sworn affidavit from the insurance producer/agent in which that person attests that the submitted invoice is for the required OCP coverage only, and that the invoice accurately reports the cost to contractor of that coverage. The invoice and affidavit may be submitted at the preconstruction conference or thereafter for inclusion with a partial estimate.
There will be no reimbursement for any purchase of OCP insurance policy extensions necessitated by concurrent; non-excusable; or excusable, non-compensable delays in completion of the project, whenever such delays occur, or for claimed utility delays where such days were not added to Contract Time by change order. Any policy extensions necessitated by excusable, compensable delays will be reimbursed on a pro-rata monthly basis.
S.P. COMPENSATION FOR
ALTERATIONS OF THE CONTRACT (07-26)
109.4 of the 2026 Louisiana Standard Specifications for Roads and Bridges is amended as follows:
109.4.030.B. is deleted and replaced with the following:
B. Direct Materials
For materials accepted by the engineer and used, the contractor shall receive the actual cost of such materials delivered to the work, including transportation charges if applicable and sales taxes subject to the requirements of 107.2.
109.4.030.C.3. is deleted and replaced with the following:
3. Operating Cost
When internal rates are used for cost recovery, equipment operating cost will be reimbursed for the actual hours used in work. Intermittent breaks throughout the day will not be deducted while the equipment is dedicated solely to the force account work. When using guide book rental rates, only the operating cost will be
D-6 reimbursed at an hourly rate over 8-hours per day. Reimbursement will stop when the equipment is no longer needed.
Pickups for superintendents and employee transport are non-compensable; when directly used in performance of the work, pickups will be reimbursed at $150/day with no markup.
The cost of service trucks and other support equipment will be considered compensable.
Standby will be reimbursed as follows, with a maximum reimbursement of 8-hours per day, 40-hours per week, and 22-days per month:
∗ (𝑎𝑔𝑟𝑒𝑒𝑑 𝑟𝑎𝑡𝑒 − 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑐𝑜𝑠𝑡𝑠)
Standby will not be reimbursed for periods when the equipment would ordinarily be idle (weekends, holidays, adverse weather, periods of repair and maintenance)
S.P. PAYMENT FOR STOCKPILED
OR STORED MATERIAL (01-26)
Section 109 of the 2026 Louisiana Standard Specifications for Roads and Bridges is amended as follows:
109.6.010 is deleted and replaced with the following:
109.6.010 GENERAL
Payment for stockpiled or stored material will be considered only for materials anticipated to be stored for periods in excess of 30 calendar days. When approved, advance payments may be made for fabricated or natural materials that are to be incorporated in the project when stockpiled materials are stored on the project or in a dedicated stockpile at an approved site outside the limits of the project within the State of Louisiana. Payments shall be limited to durable materials described herein and shall represent a significant portion of the project cost. Perishable articles and small warehouse items are not included. These materials shall meet the requirements of the specifications. Payment for stockpiled or stored materials will not constitute acceptance. It shall be the contractor's responsibility to protect the material from damage while in storage.
Payment for materials stored outside the State of Louisiana will be considered, subject to approval of the Chief Engineer. This will generally be limited to adjacent states, except in cases where it will be in the best interest of the Department to pay for these materials. If payment for stockpiled materials outside the State will affect the bid price for an item, the contractor shall submit a written request to the Chief Engineer prior to bidding.
Payment may be made for the invoice price for the materials, which shall not exceed 85 percent of the contract price for the items where the materials are to be incorporated. For fabricated materials purchased from commercial sources and delivered to approved storage, D-7 partial payment may be the invoice price plus freight and taxes subject to the requirements of
107.2. The quantity of material for payment will not exceed the total estimated quantity required to complete the project.
The amounts advanced on stockpiled or stored materials will be recovered by the
Department through deductions made on payments as the materials are incorporated in the work.
Partial payment for stockpiled materials shall be requested by the contractor in writing and the following documents shall be furnished:
a) A copy of the invoices from supplier or manufacturer verifying the cost and quantity of material.
b) If storage is on private property, a copy of the lease or agreement granting the
Department right of entry to property.
Within 30 calendar days after payment by the Department, the contractor shall submit a certified copy of invoices from the supplier for each item for which payment has been made.
All such invoices submitted shall state the amount received by the supplier as payment in full for the materials. If this certification of payment is not presented within the 30 day period, the advanced payment will be deducted from future progress payments.
Title and ownership of materials for which advancements have been made by the
Department shall not vest in the Department until such materials are incorporated in the work and the work accepted by the Department. The making of advancements by the Department shall not release the contractor from the responsibility for any portion thereof.
S.P. PAYMENT ADJUSTMENTS (01-26):
Section 109 of the 2026 Louisiana Standard Specifications for Roads and Bridges is amended to add the following:
This project is designated for payment adjustments for asphalt cements, fuels, and steel in accordance with Subsection 109.9 as follows:
109.9 PAYMENT ADJUSTMENTS
109.9.010 GENERAL
Payment for contract items indicated herein will be adjusted to compensate for cost differentials of Performance Graded (PG) asphalt cements, gasoline, diesel fuel, and steel when such costs increase or decrease more than 5 percent from the Department's established base prices for these items. The base price indices for asphalt cements, gasoline, diesel fuel, and steel will be the monthly price indices in effect at the time bids are opened for the project. The base price indices for asphalt cements will be as stated in
109.9.020. The base price index for gasoline and diesel fuel will be as stated in 109.9.030.
The base price index for steel will be as stated in 109.9.040.
D-8
Payment adjustments will be made each monthly estimate period when a price index for this period varies more than 5 percent from its respective base price index. The monthly price indices to be used with each monthly estimate will be the price indices for the month in which the estimate period begins. No payment adjustment will be made for new pay items created by change order.
If the project is placed in default, payment adjustments will be based on the monthly price indices used for the last monthly estimate period prior to the project being placed in default, unless a monthly price index decreases in which case the lower monthly price index will be used.
If it is determined after completion of work on any eligible item that the total quantity paid to date must be adjusted to reflect more accurate quantity determinations, the Department will prorate the additional quantity to be added or subtracted over all previous estimate periods in which the item of work was performed in order to determine additional payment adjustments.
If payment adjustments were made during any of these partial estimate periods, the prorated quantity added or subtracted will likewise have payment adjustments calculated and included.
109.9.020 PERFORMANCE GRADED (PG) ASPHALT CEMENTS
The base price index will be the monthly price index in effect at the time of bid opening as shown elsewhere herein. The monthly price indices will be the average, excluding the extreme outliers, of the unit prices for PG67-22, the average, excluding the extreme outliers, of the unit prices for PG70-22m, and the average, excluding the extreme outliers, of the unit prices for PG76-22m. The monthly prices for each of these asphalt materials will be F.O.B.
refinery or terminal as determined from the quoted prices effective on the first calendar day of each month from suppliers of these materials. Suppliers considered are those who have requested to participate in the liquid asphalt index determination and have supplied materials on DOTD projects within the past twelve months. These suppliers and materials shall be listed on the Department's Approved Materials List (AML) and must be marketed in
Louisiana. For Asphalt Cements not listed above, the following shall be considered equivalent for payment adjustments:
Table 109.9.020-1 Pay Item Equivalents Eligible for Asphalt Payment Adjustment
Performance Graded Asphalt Cement Equivalent PG Asphalt Cement for
Payment Adjustment
PG58-28 PG67-22
PG67-22 PG67-22
PG70-22m PG70-22m
PG76-22m PG76-22m
PG76-22rm PG67-22
Payment adjustments will be made in accordance with the following formulas:
D-9
If Monthly Price Index exceeds Base Price Index, Pa = (A - 1.05B) x C x D x (1.00 + T)
If Base Price Index exceeds Monthly Price Index, Pa = (0.95B - A) x C x D x (1.00 + T)
Where:
Pa = Price adjustment (increase or decrease) for asphalt cement.
A = Monthly Price Index for respective PG67-22 PG70-22m, or PG76-
22m in dollars per ton.
B = Base Price Index for respective PG67-22 PG70-22m, or PG76-
22m in dollars per ton.
C = Tons of asphaltic concrete.
D = Percent of respective asphalt cement, per job mix formula, in decimals.
T = Louisiana sales tax percentage, in decimals.
(Note: Local tax is not considered)
The engineer will furnish the weights of asphalt concrete placed during the monthly estimate period with the respective asphalt cement content, excluding the asphalt content in reclaimed asphalt pavement (RAP) as per job mix formula. If the asphalt cement content changes during the estimate period, the respective weight of asphalt concrete produced at each cement content will be reported.
All contract pay items using PG58-28, PG67-22 PG70-22m, PG76-22m, and PG76-22rm shall be eligible for payment adjustments of asphalt materials; except no payment adjustment will be made for contract pay items under Section 510-01 series “Pavement Patching”, Section 510-03 series “Pavement Joint Repair”, Section 510-04 series “Pavement Patching”, Section 507 “Asphalt Surface Treatment”, Section 707 Asphalt Concrete Curbs, and Section
725 Temporary Detour Roads, nor for any emulsions or cutbacks.
Item 510-02, Pavement Widening, and all contract pay items under Sections 501 (excluding tack coat), and 502, will be eligible for payment adjustments of asphalt materials. No payment adjustment will be made for other asphalt materials, including emulsions and cutbacks.
The base price indices for asphalt cements, gasoline, and diesel fuel will be posted on the
DOTD internet website before the 3rd calendar day of each month, excluding Saturdays, Sundays, and legal holidays at the following URL:
http://wwwapps.dotd.la.gov/engineering/lettings/lac_price_index/priceindices.aspx.
D-10
109.9.030 GASOLINE AND DIESEL FUEL
The base price index for this project will be the monthly price index in effect when bids are opened for the project. The monthly price index will be the closing price for unleaded gasoline and No. 2 diesel fuel provided for the U.S. Gulf Coast area as posted on the U.S.
Energy Information Administration Web Site effective on the first working day of each month or as determined by Louisiana Department of Transportation and Development.
Payment adjustment will be made in accordance with the following formulas:
If Monthly Price Index exceeds Base Price Index, Pa = (A - 1.05B) x Q x F
If Base Price Index exceeds Monthly Price Index, Pa = (0.95B - A) x Q x F)
Where:
Pa = Price adjustment.
A = Monthly Price Index in dollars per gallon.
B = Base Price Index in dollars per gallon.
Q = Pay Item Quantity (Pay Units).
F = Fuel Usage Factor Gal /Pay Unit.
The following is a listing of contract pay items that are eligible for payment adjustment and the fuel usage factors that will be used in making such adjustment. Contract items that expand the items listed herein by use of letter or number designations are also eligible for gasoline and diesel fuel price adjustments; for example:
Item 601-01-00100, Portland Cement Concrete Pavement 8 inches thick.
Table 109.9.030-1
ELIGIBLE CONTRACT PAY ITEMS & FUEL USAGE FACTORS FOR
FUEL PAYMENT ADJUSTMENT7
Item No. Pay Item Units
Min. Original
Contract Quantity
For Pay
Adjustment
Fuel Usage
Factors
Diesel2 Gasoline
203-011 General Excavation gal/cu yd 10,000 cu yd 0.29 0.15
203-02 Drainage Excavation gal/cu yd 10,000 cu yd 0.29 0.15
203-031 Embankment gal/cu yd 10,000 cu yd 0.29 0.15
D-11
203-04 Nonplastic Embankment gal/cu yd 10,000 cu yd 0.29 0.15
203-07 Borrow (Vehicular
Measurement) gal/cu yd 10,000 cu yd 0.29 0.15
301-01 Class I Base Course gal/cu yd 3,000 cu yd 0.88 0.57
301-02 Class I Base Course ( " Thick) gal/sq yd 50,000 sq yd 0.04 0.03
302-01 Class II Base Course gal/cu yd 3,000 cu yd 0.88 0.57
302-02 Class II Base Course ( " Thick) gal/sq yd 50,000 sq yd 0.04 0.03
303-01 In-Place Cement Stabilized
Base Course ( “Thick) gal/sq yd 50,000 sq yd 0.04 0.03
303-03 In-Place Cement Treated Base
Course ( “ Thick) gal/sq yd 50,000 sq yd 0.04 0.03
304-02 Lime Treatment (Type B) gal/sq yd 50,000 sq yd 0.04 0.03
304-03 Lime Treatment (Type C) gal/sq yd 50,000 sq yd 0.04 0.03
304-04 Lime Treatment (Type D) gal/sq yd 50,000 sq yd 0.04 0.03
305-01 Subgrade Layer ( " Thick) gal/sq yd 50,000 sq yd 0.04 0.03
401-01 Aggregate Surface Course (Net
Section) gal/cu yd 3,000 cu yd 0.88 0.57
401-02 Aggregate Surface Course
(Adjusted Vehicular
Measurement) gal/cu yd 3,000 cu yd 0.88 0.57
501-01 Thin Asphalt Concrete (Dense
Mix) gal/ton 1000 ton 2.403 0.2
501-02 Thin Asphalt Concrete (Coarse
Mix) gal/ton 1000 ton 2.403 0.2
501-03 Thin Asphalt Concrete (OGFC) gal/ton 1000 tons 2.403 0.2
502-01 Asphalt Concrete gal/ton 1000 ton 2.403 0.2
502-02 Asphalt Concrete gal/cu yd 500 cu yd 4.804 0.4
502-03 Asphalt Concrete ( " Thick) gal/sq yd 10,000 sq yd 0.135,6 0.016
502-04 Asphalt Concrete (SMA)
Wearing Course gal/ton 1000 ton 2.403 0.2
510-02 Pavement Widening gal/sq yd 3,000 sq yd 0.86 0.24
601-01 Portland Cement Concrete
Pavement ( " Thick) gal/sq yd 15,000 sq yd 0.11 0.15
1 If project has both 203-01 & 203-03, only the item with larger quantity is eligible.
2 For fuel adjustment purposes, the term "diesel" shall represent No. 2 or No. 4 fuel oils or any of the liquefied petroleum gases, such as propane or butane.
3 If natural gas or coal is used instead of diesel for aggregate drying and heating the fuel usage factor shall be 1.67 gal/ton.
4 If natural gas or coal is used instead of diesel for aggregate drying and heating the fuel usage factor shall be 3.34 gal/cu yd.
5 If natural gas or coal is used instead of diesel for aggregate drying and heating the fuel usage factor shall be 0.09 gal/sq yd.
D-12
6 Per inch of thickness.
7 No fuel adjustment will be allowed for waste oil.
109.9.040 STEEL
The base price index will be the monthly price index in effect at the time of bid opening as shown elsewhere herein. The monthly price indices will be the US Bureau of Labor Statistics
Series Report WPU101702. The monthly prices for each of these steel materials will be the final accepted published number per the link on the DOTD website. The payment adjustment will be based on the monthly price index at the time of stockpile payment or the date of installation if no stockpile payment is made. Price Adjustment for steel items will only be eligible for projects with an original contract time of more than 120 calendar days.
Payment adjustments will be made in accordance with the following formulas:
If Monthly Price Index exceeds Base Price Index, Pa = (A - 1.05B) x F x (1.00 + T)
If Base Price Index exceeds Monthly Price Index, Pa = (0.95B - A) x F x (1.00 + T)
Where:
Pa = Price adjustment (increase or decrease) for steel.
A = Monthly Price Index for respective WPU101702.
B = Base Price Index for respective WPU101702.
F = Material Factor
T = Louisiana sales tax percentage, in decimals.
(Note: Local tax is not considered)
A line-item adjustment will be made on the last progress estimate prior to the final estimate for each applicable pay item.
The following is a listing of contract pay items that are eligible for payment adjustment and the material factors that will be used in making such adjustment.
D-13
Table 109.9.040-1
ELIGIBLE CONTRACT PAY ITEMS & MATERIAL FACTORS FOR
STEEL PAYMENT ADJUSTMENTS
Item No. Pay Item Units Lbs/Quantity Material Factor
601-01 Portland Cement Concrete
Pavement _____in. Thick
SQYD
704-01 Guard Rail LNFT 11.44 lbs/LF (11.44 x LF)/2000
704-02 Guard Rail (Double Faced) LNFT 22.88 lbs/LF (22.88 x LF)/2000
704-03 Blocked Out Guard Rail LNFT 7.84 lbs/LF (7.84 x LF)/2000
704-04 Blocked Out Guard Rail (Double
Faced) LNFT 15.68 lbs/LF (15.68 x LF)/2000
704-05 Guard Rail Anchor Sections
(Trailing End) LNFT 7.84 lbs/LF (7.84 x LF)/2000
704-06 Guard Rail Bridge Attachments LNFT 11.44 lbs/LF (11.44 x LF)/2000
704-07 Guard Rail Transitions LNFT 9.64 lbs/LF (9.64 x LF)/2000
729-09 Mounting (Overhead Truss)
(Ground Mounted) 1 EACH X lbs X/2000
736-04 Signal Pole (Size and Type)1 EACH X lbs X/2000
803-01 Drilled Shaft (Diameter)2 LNFT X lbs X/2000
804-01 Precast Concrete Piles (Size) LNFT Various
-00200 14” LNFT 5.53 lbs/LF (5.53 x LF)/2000
-00300 16” LNFT 7.57 lbs/LF (7.57 x LF)/2000
-00400 18” LNFT 7.80 lbs/LF (7.80 x LF)/2000
-00600 24” LNFT 14.72 lbs/LF (14.72 x LF)/2000
-00600 24” Voided LNFT 12.64 lbs/LF (12.64 x LF)/2000
-00700 30” Voided LNFT 18.59 lbs/LF (18.59 x LF)/2000
-00800 36” Voided LNFT 23.76 lbs/LF (23.76 x LF)/2000
804-03 Steel Piles (Type and Size)3 LNFT X lbs/LF
10.68t(D-t)xLF X/2000
805-08 Precast-Prestressed Concrete
Girders (Type)1
LNFT
X lbs
X lbs/LF
X/2000
(X x LF)/2000
806-01 Deformed Reinforcing Steel LB X lbs X/2000
807-01 Structural Metalwork (Grade)2 LB X lbs X/2000
810-01 Concrete Bridge Railing (Type) LNFT 27.87 lbs/LF (27.87 x LF)/2000
813-01 Concrete Approach Slabs (Cast-in-Place) SQFT 26.25 lbs/SQFT (26.25 x SF)/2000
822-05 Light Pole (Type)1 EACH X lbs X/2000
822-06 High Mast Pole (Type)1 EACH X lbs X/2000 1 Pounds of steel based on shop drawings. Shop drawings must include total weight of all steel items in each pay item.
2 Pounds of steel based on plan sheet theoretical weight or as shown in the Summary of Quantity Table.
D-14
3 Pounds of steel for H-pile is based on the lbs/LF of the specified type. Pounds of steel for cylinder pile is based on the outside diameter (D in inches) and thickness (t in inches).
S.P. (SEC 203.3.060) SETTLEMENT PLATE INSTALLATION
AND SETTLEMENT MONITORING (02-26):
Section 203.3.060.D. of the 2026 Louisiana Standard Specification for Highway Roads and Bridges is deleted and replaced with the following:
D. Settlement Plate Installation and Settlement Monitoring
Install settlement plates prior to placement of fill. Unless specified otherwise, install settlement plate on natural ground on a level surface.
Maintain a vertical, accessible, and undamaged riser pipe during embankment placement and compaction. Replace any settlement plates damaged during construction at no cost to the Department.
Provide all elevations to have a precision of ±0.01 feet. Document the date and time of all survey readings.
Survey and document riser pipe elevations immediately before and immediately after riser pipe extension.
Survey and document settlement plate elevation readings immediately after installation of the plate, just prior to fill placement, and weekly during fill placement.
Survey immediately after the final lift is placed and compacted, twice weekly for the first month of the settlement monitoring period, and weekly for five months thereafter.
Restart settlement monitoring period if any additional fill placement or surcharge is required.
Unless specified otherwise, the settlement monitoring period begins after all fill has been placed and compacted. All surveying during fill placement does not count as part of the settlement monitoring period.
Record the embankment elevation and surcharge height for each settlement plate reading. Submit settlement plate readings to the Project Engineer. The Project Engineer and Geotechnical Engineer will verify the initial and final elevations for acceptance. Do not install foundations through, upon, or beneath new fill within 100 feet of a settlement plate prior to acceptance of the fill elevations.
Remove riser pipe and casing three feet below base course upon acceptance.
D-15
S.P. (SEC 502) Asphalt Concrete Mixtures (06-26)
Section 502 of the 2026 Louisiana Standard Specification for Highway Roads and Bridges is revised as follows:
Section 502.3.100.D. is deleted and replaced with the following:
D. Correction of Deficient Areas
Correct areas as required in 502.3.100.B. and 502.3.100.C. and those not meeting Table 502.3-4. Correct wearing and binder courses as defined in this subsection at no direct pay. In lieu of grinding, the Project Engineer may penalize the contractor $1,000.00 per individual bump specified in Table 502.3-4 or per “Ripple” as defined in 502.3.100.B.
1. Deficiencies in Mainline Wearing Course
Correct deficiencies in the final wearing course by:
a) by diamond grinding and applying a light tack coat; or
b) by furnishing and placing a supplemental layer of wearing course mixture at least 1½ inches compacted thickness for the full width of the roadway meeting specification requirements; or
c) by removing and replacing mixture.
If the supplemental layer does not meet specification requirements of Table 502.3-4, remove and replace or correct it by other methods approved by the Project Engineer.
For areas that will not be improved by grinding such as minor dips, extreme vertical curves, or other areas that are not exempt as measured with a 10 feet metal static straight edge, the Project Engineer may waive the requirement to grind as specified in 502.3.100.D.
2. Deficiencies in Mainline Binder Courses
Correct deficiencies in binder course: longitudinal, transverse, cross slope, and grade to meet specification requirements by diamond grinding, by milling, or by removing and replacing mixture. Make corrections before subsequent courses are constructed.
3. Deficiencies in Minor Mixes
Correct deficiencies in minor mixes by diamond grinding or approved method at the Project Engineer’s direction.
D-16
S.P. Milling Asphalt Pavement (03-26)
Section 509 of the 2026 Louisiana Standard Specifications for Roads and Bridges is amended as follows:
The last two paragraphs of 509.3 are deleted and replaced with the following:
A specified percentage or quantity of the reclaimed asphalt pavement (RAP) generated by the project may be required to be retained. After the specified amount of contractor RAP has been retained, immediately haul, or as agreed upon by the Engineer, all RAP material to be retained by the Department for its recycling program, or by other government entities to the storage facility indicated on the plans and stockpile as directed.
Make required joint repairs prior to milling. Complete pavement patching before milling, unless additional areas requiring patching are exposed by the milling. Perform pavement patching and joint repair in accordance with Section 510. A clean, vertical face the depth of the required milling is to be left at all tie-in locations of roadway, side-streets, turnouts, and drives. Removal of existing materials and any sawcuts necessary to leave the clean, vertical face will not be measured for payment.
S.P. (SEC 601) PORTLAND CEMENT
CONCRETE PAVEMENT (09-26)
Section 601 of the 2026 Louisiana Standard Specification for Highway Roads and Bridges is revised as follows:
Section 601.2 is deleted and replaced with the following:
601.2 Materials
Provide materials as specified in the following sections and subsections.
Portland Cement Concrete 901, 1001
Aggregates 1003
Joint Materials 1005
Reinforcing Steel 1009.1
Dowel Bars 1009.3
Curing Materials 1011.1
Admixtures 1011.2
Epoxy Resin Systems 1017
Water 1018.1
Hydrated Lime 1018.2
Non-Shrink Grout 1018.4
D-17
Geotextile Fabric 1019
Furnish PCCP concrete. Use the same type of concrete throughout the project, unless otherwise authorized in writing.
Account for delayed and fluctuating set times and strength gain characteristics when utilizing supplemental cementitious materials in PCCP.
601.2.010 HIGH FLEXURAL STRENGTH CONCRETE
Use the maturity method for flexural strength determination according to ASTM C1074. If any of the mix components change (material sources or mix proportions change by more than ±5%; admixture dosages change by more than ±20%), a new maturity curve must be developed and verified. Submit the mix design, trial batch results, and maturity curves to the
District Laboratory Engineer for review.
Verify by trial batch that the proposed mixture achieves the flexural strength specified in
Table 601.3.140-1, and the appropriate early opening strength specified in 601.3.130 within the time frame specified in the contract documents.
Trial batch requirements may be waived, with written approval from the District Laboratory
Engineer, for previously approved mix designs when all materials and proportions of the proposed design exactly match the previously approved mix design materials.
Section 601.3.060 is deleted and replaced with the following:
601.3.060 PLACING AND CONSOLIDATING CONCRETE
Deposit concrete on a surface-moist base or subgrade with a minimum of handling. Base course must be less than 120°F immediately prior to concrete placement. Place concrete continuously between transverse joints. Use appropriate tools for necessary hand spreading.
Place concrete as close to joints as possible without disturbing them. Ensure workers wear footwear clean of foreign matter.
Except for concrete sawing equipment, restrict operation of mechanical equipment on the pavement until obtaining a minimum compressive strength of 3,000 psi in accordance with
DOTD TR-230. When high flexural strength is specified, restrict operation of mechanical equipment, except for concrete sawing equipment, on the pavement until obtaining a minimum flexural strength of 480 psi in accordance with ASTM C1074.
Pave adjacent lanes only after a minimum elapse of 1-day with no observable marring of the surface.
Rain protection along with hot and cold weather limitations of 901.3.090 shall apply.
Complete the surface finish as specified in 601.3.090.G. Texture the surface as specified in
601.3.090.H.
Cure the surface and edges as specified in 601.3.100.
D-18
A. Slip-Form Method
At the option of the contractor, the slip-form paving method may be used.
Place concrete with an acceptable slip-form paver designed to spread, consolidate, screed and float finish freshly placed concrete in one pass of the machine with only a minimum amount of hand finishing necessary to provide a dense, homogeneous pavement in conformance with plans and specifications. Equip the machine with vibrators conforming to 601.3.010.F.1. Vibrate concrete for the full pavement width and depth for complete consolidation. Hold sliding forms rigidly together laterally to prevent spreading of forms.
Provide concrete of a uniform consistency exhibiting minimal bleed water and laitance. Operate the slip-form paver with as nearly a continuous uniform forward movement as possible. Coordinate mixing, delivering and placing of concrete to provide uniform progress. Concrete plants shall have sufficient mixing capacity to provide such continuous delivery of concrete to enable the paver to advance at a minimum rate of 1.5 feet per minute. If it is necessary to stop forward movement of the paver, also immediately stop the vibrator and tamping elements. If forward movement of the paver is delayed for a period, the engineer may direct fogging of fresh concrete. See 601.3.080 for construction joint requirements. Apply no outside tractive force to the machine except as controlled from the machine.
B. Stationary Side-Form Method
Deposit concrete as near as possible to forms and joints assemblies without disturbing…