L20_112880.pdf

PDF 16 MB Posted

Attached to
L20_2024 SGR - BRIDGE REPLACEMENT
Solicitation number
66701
Issued by
Mathews County, Virginia

About this file

This document is a project description for a bridge replacement project in Madison County, Virginia. The project scope involves replacing a bridge located 0.070 miles south of the Hughes River to 0.042 miles north of the Hughes River. Prequalification is required to bid on this contract. All questions must be submitted to the Virginia Department of Transportation (VDOT) using the Contractors Advertisement Bulletin Board. The project is part of VDOT's State of Good Repair (SGR) program.

The document does not provide any additional details on pricing, set asides, funding sources, or other salient contract information. It only outlines the project location, scope, and prequalification requirements.

View the file

Other files

File Type Posted
L20 Addendum C111 Forms 6.2024_signed.pdf PDF
L20_112880.pdf PDF
Programmatic Addendum Letter 2024.06.13_signed.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ORDER NO.: L20

CONTRACT ID. NO.: C0000112880B50

Form C-6a

Rev. 3-22-05

CNSP (F) 1-9-06

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

BID PROPOSAL AND CONTRACT

ROUTE NUMBER: 707

FHWA NUMBER: BROS-056-7(037)

PROJECT NUMBER: 0707-056-735, B650, B699

COUNTY: MADISON

DISTRICT: CULPEPER

DESCRIPTION: SGR - BRIDGE REPLACEMENT

FROM: 0.070 MILES SOUTH OF HUGHES RIVER

TO: 0.042 MILES NORTH OF HUGHES RIVER

DATE BID SUBMITTED: 10:00 A.M. WEDNESDAY, JUNE 26, 2024

Form C-118 Rev. 2-1-24

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

NOTICE TO BIDDERS

As a matter of information, the bidder’s attention is directed to the points noted herein. Every point enumerated below is fully covered by proposal documents that describe them in detail. Bidders should check their proposal against all requirements, as strict compliance with all provisions is mandatory.

1. Bids shall be filed electronically through Bidx (https://bidx.com/site/home) at the times designated in the Notice of Advertisement for Bids. For information see (https://cabb.virginiadot.org/)

2. Unless otherwise specified or permitted in the proposal, prices shall be submitted on all items shown in the proposal.

3. Proposals conditioned by proposed alternates, other than those specified or permitted, or by reserving the right to accept or reject an award or to enter into a contract pursuant to an award will not be considered.

4. A bid total shall be shown in each space provided.

5. Bid bonds shall conform to Section 102.07. The bid bond number shall be placed in the appropriate space in your electronic bid. As an alternative you may complete the bottom line of the Form C-24. This form may be mailed or faxed but must be received prior to the opening of the bids.

6. Joint venture proposals shall show the Firm Name of each party and shall be signed by an authorized representative of each Firm. A letter shall be filed with the prequalification office describing responsibility of each firm and the amount of maximum capacity pledge by each firm of a joint venture.

https://bidx.com/site/home http://cabb.virginiadot.org/

Form C-24 Rev. 7-6-05

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

PROPOSAL GUARANTY

KNOW ALL MEN BY THESE PRESENTS, THAT WE As principal, and Surety, are held and firmly bound unto the

Commonwealth of Virginia as obligee, in the amount of FIVE PERCENT OF THE DOLLAR VALUE OF THE

BID, lawful money of the United States of America, for the payment of which, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally and firmly by these presents.

SIGNED, sealed and dated this Day of , 20

WHEREAS, the above said principal is herewith submitting its proposal for:

PROJECT NUMBER: 0707-056-735, B650, B699

NOW, THEREFORE, the condition of the above obligee is such, that if the aforesaid principal shall be awarded the contract upon said proposal and shall within the time specified in the Specifications after the notice of such award enter into a contract and give bond for the faithful performance of the contract, then this obligation shall be null and void; otherwise to remain in full force and effect and the principal and surety will pay unto the obligee the difference in money between the amount of the bid of the said principal and the amount for which the obligee may legally contract with another party to perform the said work if the latter amount be in excess of the former; but in no event shall the liability exceed the penal sum hereof.

(Principal*) (Surety Company)

By: By:

(Officer, Partner or Owner) (Seal) (Attorney-in-Fact**) (Seal)

(Principal*) (Address)

By: By:

(Officer, Partner or Owner) (Seal) (Surety Company)

(Principal*) (Attorney-in-Fact**) (Seal)

By: By:

(Officer, Partner or Owner) (Seal) (Address)

*Note: If the principal is a joint venture, each party thereof must be named and execution made by same hereon. If there is more than one surety to the bid bond, each surety must be named and execution shall be made by same hereon.

Electronic Bid Only: In lieu of completing the above section of the Contract Performance Bond, the Principal shall file an Electronic Bid Bond when bidding electronically. By signing below the Principal is ensuring the identified electronic bid bond has been executed and the Principal and Surety are firmly bound unto the Commonwealth of Virginia under the same conditions of the bid bond as shown above.

Electronic Bid Bond ID# Company/Bidder Name Signature and Title

**Attach copy of Power of Attorney

Form C-48 Rev. 05-01-24

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

SUBCONTRACTOR/SUPPLIER SOLICITATION AND UTILIZATION,

AND VENDOR SURVEY FORM (ALL VENDORS)

PROJECT NO. CONTRACT I.D. NO.

FHWA NO. DATE SUBMITTED

All vendors submitting a bid as a Prime Contractor shall complete and submit with their bids the following information as requested for (1) Subcontractor/Supplier Solicitation, and (2) Utilization and for Vendor Survy.

The vendor certifies this form accurately represents its solicitation and utilization or non-utilization, as indicated, of the firms listed below for performance of work on this contract. The vendor also certifies he/she has had direct contact with the named firms regarding participation on this project.

VENDOR SIGNATURE:

VENDOR NO. TITLE:

VENDOR’S ADDRESS:

CITY: ____________________________________

STATE: __________________ ZIP CODE: _________

SUBCONTRACTOR/SUPPLIER SOLICITATION AND UTILIZATION (ALL)

VENDOR

NUMBER NAME OF SUBCONTRACTOR/SUPPLIER

TELEPHONE

NUMBER

DBE OR

NON-DBE

UTILIZED

(Y/N)

NOTE: ATTACH ADDITIONAL PAGES, IF NECESSARY.

BIDDER MUST SIGN EACH ADDITIONAL SHEET TO CERTIFY ITS CONTENT AND COMPLETION OF FORM.

FEDERAL LAW REQUIRES ALL VENDORS SUBMITTING BIDS OR OFFERS AS CONTRACTORS OR

SUBCONTRACTORS TO PROVIDE THE INFORMATION REQUESTED IN THIS FORM.

ORDER NO.: L20

CONTRACT ID. NO.: C0000112880B50

0707-056-735, B650, B699

BROS-056-7(037)

C0000112880B50

Form C-48 Rev. 05-01-24

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

VENDOR SURVEY

FEDERAL LAW REQUIRES THAT ALL VENDORS WHO SUBMIT BIDS OR OFFERS AS CONTRACTORS OR

SUBCONTRACTORS PROVIDE THE INFORMATION IN THIS FORM.

WHEN SUBMITTING A BID OR OFFER AS A PRIME CONTRACTOR, THE BIDDER MUST SUBMIT THEIR

VENDOR SURVEY AND A VENDOR SURVEY FOR EACH SUBCONTRACTOR LISTED ABOVE.

VENDOR’S FULL LEGAL NAME: ________________________________________

VENDOR ID NO.: __________________

ADDRESS: ____________________________________

CITY: ____________________________________

STATE: _______________ ZIP CODE: _________

VENDOR’S YEARS IN BUSINESS: _____________

VENDOR’S STATUS: _____ DBE _____ NON-DBE

[DBE means a small business that is certified as a Disadvantaged Business Enterprise by the Virginia Department of Small Business & Supplier Diversity or the Metropolitan Washington Airports Authority.]

GENDER OF VENDOR’S MAJORITY OWNER: ____ MALE ____ FEMALE ____ OTHER

ETHNICITY OF VENDOR’S MAJORITY OWNER: ____ White

(Defined in 49 CFR 26.5) ____ Black or African American

____ Hispanic American

____ Asian-Pacific American

____ Subcontinent Asian American

____ Native American, incl. Alaskan or Hawaiian

____ Other: ____________________________

VENDOR’S ANNUAL GROSS RECEIPTS: ____ Less than $1 million ____ $ 1 - 5 million ____ $ 5 - 10 million ____ $ 10 - 15 million ____ $ 15 - 20 million ____ $ 20 - 25 million ____ $ 25 - 30 million ____ $ 30 - 40 million ____ $ 40 - 50 million ____ $ 50 - 100 million ____ More than $100 million

THE VENDOR IDENTIFIED ABOVE ACKNOWLEDGES AND CERTIFIES THAT THIS FORM ACCURATELY STATES THE

INFORMATION CONTAINED HEREIN TO THE BEST OF VENDOR’S KNOWLEDGE.

Printed Full Legal Name of Vendor’s Authorized Officer (listed on page 2 of Form C-32)

Signature: ____________________________________________

Form C-7 Rev. 2-2-24

SHEET 1

TERMS OF THE PROPOSAL\CONTRACT

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

SUBMITTED: 10:00 A.M. WEDNESDAY, JUNE 26, 2024

PROJECT NUMBER: 0707-056-735, B650, B699

ROUTE NUMBER: 707

FHWA NUMBER: BROS-056-7(037)

DESCRIPTION: SGR - BRIDGE REPLACEMENT

FROM:

TO:

0.070 MILES SOUTH OF HUGHES RIVER

0.042 MILES NORTH OF HUGHES RIVER

DISTRICT: CULPEPER COUNTY: MADISON

I/we declare that no other person, firm or corporation is interested in this proposal; that I/we have carefully examined the plans, job specifications, current Road and Bridge specifications, and all other documents pertaining thereto and thoroughly understand the contents thereof; that I/we meet the prequalification requirements for bidding on this proposal;

that I/we understand that the plans and current Road and Bridge specifications, are a part of this proposal; that all of the quantities shown herewith are a part of this proposal; that all the quantities shown herewith are approximate only; that I/we have examined the location of the proposed work and source of supply of materials; and that I/we agree to bind myself/ourselves upon award by the Commonwealth under this proposal to a contract with necessary surety bond to start work according to project specifications, and to complete all work in accordance with the plans, job specifications and current Road and Bridge Specifications within the time limit set forth in the contract.

COMPLETION DATE: DECEMBER 23, 2025

BID TOTAL $

Attached is a bond conforming to the requirements of the current Road and Bridge Specifications, it being understood that such bond is to be forfeited as liquidated damages if, upon acceptance of the terms of this proposal, I/we fail to execute the contract and furnish bond as provided in the current Road and Bridge Specifications.

(Names of Individual(S),Firm(S) Or Corporation)

Street Address City State Zip Code Vendor#/Fin#

Print Name Signature Title

In consideration of the commitments made as shown herein, the Commonwealth of Virginia by The Commonwealth Transportation Commissioner agrees to pay for all items of work performed and materials furnished at the unit price(s) and under the conditions set forth in this proposal, in witnessed by the affixing of the name below.

Contract Execution Date By

CHIEF ENGINEER

VIRGINIA DEPARTMENT OF TRANSPORTATION

Virginia Department of Transportation 05/07/2024Date Printed:

Schedule of Items Page: 2

Proposal ID: C0000112880B50 0707-056-735, B650, B699

Order No.: L20

Oversight/State Project No.:

Federal Project No.: BROS-056-7(037)

Contractor:

0001 REGULAR BID ITEMSSECTION:

Cat Alt Set ID: Cat Alt Mbr ID:

Bid AmountUnit Price Approximate Quantity and

UnitsDescription

Item ID Proposal

Line Number Dollars Cents Dollars Cents

Spec No.

0010 301SD20-0001

CLEARING AND GRUBBING LUMP SUM _________._____LUMP SUM

0020 302SD20-0027

15" STORM SEWER PIPE LF

31.000

0030 302SD20-0072

48" STORM SEWER PIPE LF

138.000

0040 302SD20-0198

15" END SECTION ES-1 OR 2 EA

2.000

0050 303SD20-0001

REGULAR EXCAVATION CY

1,542.000

0060 303SD20-0007

BORROW EXCAVATION CY

1,228.000

0070 303SD20-0023

CHECK DAM ROCK TY. II EA

8.000

0080 303SD20-0028

DEWATERING BASIN EC-8 EA

4.000

0090 303SD20-0029

SILTATION CONTROL

EXCAVATION

CY

173.000

0100 303SD20-0033

TEMP. SILT FENCE TYPE B LF

72.000

0110 303SD20-0034

TEMP. SILT FENCE TYPE A LF

856.000

0120 303SD20-0037

TURBIDITY CURTAIN,

PERVIOUS TY. I

LF

263.000

0130 306SD20-0001

LIME TON

2.520

0140 308SD20-0012

AGGR. BASE MATL. TY. I NO.

21B

TON

499.000

Schedule of Items Page: 3

Proposal ID: C0000112880B50 0707-056-735, B650, B699

Order No.: L20

Oversight/State Project No.:

Federal Project No.: BROS-056-7(037)

Contractor:

0001 REGULAR BID ITEMSSECTION:

Cat Alt Set ID: Cat Alt Mbr ID:

Bid AmountUnit Price Approximate Quantity and

UnitsDescription

Item ID Proposal

Line Number Dollars Cents Dollars Cents

Spec No.

0150 308SX20-0003

CRUSHER RUN AGGR. NO. 25

OR 26

TON

10.000

ATTD

0160 315SD20-0008

ASPHALT CONCRETE TY. SM-

9.5D CONST

TON

155.000

0170 315SD20-0010

ASPHALT CONCRETE BM-25.0 TON

49.000

0180 315SX20-0011

SAW-CUT ASPH CONC FULL

DEPTH

LF

20.000

0190 401SD20-0001

STRUCTURE EXCAVATION

CONST.

CY

1,667.000

0200 401SD20-0002

SELECT BACKFILL

ABUTMENT ZONE

TON

2,174.000

0210 401SD20-0004

GEOCOMPOSITE WALL

DRAIN

SY

76.000

0220 401SD20-0007

COFFERDAM EA

2.000

0230 401SD20-0009

STRUCTURE EXCAVATION

MAINT.

CY

6.000

0240 401SX20-0011

BRIDGE SUBSTRUCTURE

TEMPORARY SHORING

LUMP SUM _________._____LUMP SUM

ATTD

0250 403SD20-0006

STEEL PILES 12" LF

990.000

0260 403SX20-0016

PREBORING PILE . LF

945.000

Schedule of Items Page: 4

Proposal ID: C0000112880B50 0707-056-735, B650, B699

Order No.: L20

Oversight/State Project No.:

Federal Project No.: BROS-056-7(037)

Contractor:

0001 REGULAR BID ITEMSSECTION:

Cat Alt Set ID: Cat Alt Mbr ID:

Bid AmountUnit Price Approximate Quantity and

UnitsDescription

Item ID Proposal

Line Number Dollars Cents Dollars Cents

Spec No.

0270 404SD20-0011

CONCRETE CLASS A3,

SUBSTRUCT. CONST.

CY

253.000

0280 404SD20-0021

CONCRETE CLASS A3

SUBSTRUCT. MAINT.

CY

2.000

0290 404SP20-0002

SHEAR KEYS CF

17.000

ATTD

0300 404SP20-0003

VA ADJACENT MEMBER

CONN. BLOCK-OUTS

CF

121.000

ATTD, 404

0310 405SD20-0029

PREST. CONCRETE BEAM 4' x 2'-3" x (+70'-75')

EA

2.000

0320 405SX20-0004

PRESTRESSED CONCRETE

SLAB 3' x 2'-3" x (+70'-75')

EA

5.000

ATTD

0330 406SD20-0003

CR REINF. STEEL CL. I SPR.

STRUCT. CONST.

LB

600.000

0340 406SD20-0006

REINFORCING STEEL

SUBSTRUCT. CONST.

LB

15,180.000

0350 406SD20-0008

CR REINF. STEEL CL. I

SUBSTRUCT. CONST.

LB

14,810.000

0360 406SD20-0016

CR REINF. STEEL CL. I

SUBSTRUCT. MAINT.

LB

120.000

0370 410SD20-0004

RAILING TEXAS T-6 CONST. LF

55.000

0380 410SX20-0006

BRIDGE SUPERSTRUCTURE

SLAB 3' x 15" x (+30'-35')

EA

5.000

ATTD

Schedule of Items Page: 5

Proposal ID: C0000112880B50 0707-056-735, B650, B699

Order No.: L20

Oversight/State Project No.:

Federal Project No.: BROS-056-7(037)

Contractor:

0001 REGULAR BID ITEMSSECTION:

Cat Alt Set ID: Cat Alt Mbr ID:

Bid AmountUnit Price Approximate Quantity and

UnitsDescription

Item ID Proposal

Line Number Dollars Cents Dollars Cents

Spec No.

0390 410SX20-0006

BRIDGE SUPERSTRUCTURE

SLAB 4' x 15" x (+30'-35')

EA

2.000

ATTD

0400 413SX20-0002

DISM.& REM. EX. STR.

NUMBER 6003

LUMP SUM _________._____LUMP SUM

0410 413SX20-0003

ENV.& WORKER PROTECT.

(STR. NO. 6003)

LUMP SUM _________._____LUMP SUM

0420 413SX20-0003

ENV.& WORKER PROTECT.

(STR. NO. 6053)

LUMP SUM _________._____LUMP SUM

0430 413SX20-0004

MATERIAL DISPOSAL (STR.

NO. 6003, TYPE B)

LUMP SUM _________._____LUMP SUM

0440 413SX20-0004

MATERIAL DISPOSAL (STR.

NO. 6053, TYPE B)

LUMP SUM _________._____LUMP SUM

0450 413SX20-0005

REM. PORT.OF EX.STR.

NUMBER 6053

LUMP SUM _________._____LUMP SUM

0460 414SD20-0056

DRY RIPRAP CL.II 38" SY

773.000

0470 505SD20-0073

REMOVE EXISTING

GUARDRAIL

LF

210.000

0480 505SD20-0074

GUARDRAIL, THRIE BEAM LF

300.000

0490 508SD20-0004

DEMO. OF PAVEMENT

FLEXIBLE

SY

100.000

0500 512SD20-0003

TRAFFIC BARRIER SERVICE

MB-11A

LF

650.000

Schedule of Items Page: 6

Proposal ID: C0000112880B50 0707-056-735, B650, B699

Order No.: L20

Oversight/State Project No.:

Federal Project No.: BROS-056-7(037)

Contractor:

0001 REGULAR BID ITEMSSECTION:

Cat Alt Set ID: Cat Alt Mbr ID:

Bid AmountUnit Price Approximate Quantity and

UnitsDescription

Item ID Proposal

Line Number Dollars Cents Dollars Cents

Spec No.

0510 512SD20-0013

TYPE 3 BARRICADE 8' EA

3.000

0520 512SD20-0014

TEMPORARY SIGN SF

539.000

0530 512SD20-0024

GROUP 2 CHANNELIZING

DEVICES

DAY

14,364.000

0540 512SD20-0025

PORT.CHANGEABLE MESS.

SIGN

HR

672.000

0550 512SD20-0027

FLAGGER SERVICE HR

104.000

0560 512SD20-0029

WARNING LIGHT TY. B DAY

1,204.000

0570 513SD20-0001

MOBILIZATION LUMP SUM _________._____LUMP SUM

0580 517SD20-0001

CONSTRUCTION SURVEYING

CONSTR.

LUMP SUM _________._____LUMP SUM

0590 603SD20-0002

TEMPORARY SEED LB

56.000

0600 603SD20-0003

REGULAR SEED LB

168.000

0610 603SD20-0004

OVERSEEDING LB

134.000

0620 603SD20-0009

HYDRAULIC EROSION

CONTROL PRODUCT TYPE 3

SY

6,098.000

0630 603SD20-0014

FERTILIZER NITROGEN - N LB

54.000

Schedule of Items Page: 7

Proposal ID: C0000112880B50 0707-056-735, B650, B699

Order No.: L20

Oversight/State Project No.:

Federal Project No.: BROS-056-7(037)

Contractor:

0001 REGULAR BID ITEMSSECTION:

Cat Alt Set ID: Cat Alt Mbr ID:

Bid AmountUnit Price Approximate Quantity and

UnitsDescription

Item ID Proposal

Line Number Dollars Cents Dollars Cents

Spec No.

0640 603SD20-0015

FERTILIZER PHOSPHOROUS

- P

LB

74.000

0650 603SD20-0016

FERTILIZER POTASSIUM - K LB

37.000

0660 606SD20-0001

ROLLED EROSION CTRL

PRODUCT EC-2 TYPE 1

SY

9.000

0670 606SD20-0004

ROLLED EROSION CTRL

PRODUCT EC-2 TYPE 4

SY

1.000

0680 606SD20-0005

ROLLED EROSION CTRL

PRODUCT EC-3 TYPE 1

SY

1.000

0690 700SD20-0003

REMOVE EXISTING 1 POST

SIGN STRUCTURE

EA

8.000

0700 700SD20-0012

RELOCATE EX. 1 POST GRND

MOUNT SGN PANEL

EA

1.000

0710 700SD20-0034

SIGN POST STP-1, 2", 14

GAUGE

LF

117.000

0720 700SD20-0038

CONC. FOUND. STP-1, TY. A EA

9.000

0730 701SD20-0001

SIGN PANEL SF

24.000

0740 703SD20-0045

REMOVE EXISTING

FOUNDATION

EA

4.000

Section: 0001 _________._____Total:

Total Bid: _________._____

Page

Bid Items Eligible For Fuel Adjustment

C0000112880B50

L20

Contract ID:

Order No.:

Instructions: This form shall be completed in accordance with the Special Provision for Optional Adjustment for Fuel. If you choose to have Fuel Adjustment applied to any of the items listed below, write the word "Yes" in the "OPTION" column beside the item. The form must be signed, dated, and submitted to the Contract Engineer within the timeframe required in the Special Provision.

FORM C-21B

Rev 12-21-05

0001 REGULAR BID ITEMSSECTION:

ltem Description Fuel Factor gal/unit Option Item

Number

_______REGULAR EXCAVATION 0.290303SD20-

_______BORROW EXCAVATION 0.290303SD20-

_______SILTATION CONTROL EXCAVATION 0.290303SD20-

_______AGGR. BASE MATL. TY. I NO. 21B 0.600308SD20-

_______CRUSHER RUN AGGR. NO. 25 OR 26 0.400308SX20-

_______ASPHALT CONCRETE TY. SM-9.5D CONST 3.500315SD20-

_______ASPHALT CONCRETE BM-25.0 3.500315SD20-

_______STRUCTURE EXCAVATION CONST. 0.290401SD20-

_______CONCRETE CLASS A3, SUBSTRUCT. CONST. 1.892404SD20-

_______CONCRETE CLASS A3 SUBSTRUCT. MAINT. 1.892404SD20-

_______DEMO. OF PAVEMENT FLEXIBLE 0.200508SD20-

Date:

Signature:

(Firm or Corporation)

(Vendor No.)

Bid Items Eligible For Steel Price Adjustment

C0000112880B50

L20

Contract ID:

Order No.:

Instructions: This form shall be completed in accordance with the Special Provision. If you choose to have Steel Price Adjustment applied to any of the items listed below, write the word "Yes" in the "OPTION" column beside the item. The form must be signed, dated, and submitted to the Contract Engineer within the timeframe required in the Special Provision.

Rev 12-21-08

FORM C-21C

0001 REGULAR BID ITEMSSECTION:

ltem Description Option Item

Number

_______STEEL PILES 12"403SD20-

_______CR REINF. STEEL CL. I SPR. STRUCT. CONST.406SD20-

_______REINFORCING STEEL SUBSTRUCT. CONST.406SD20-

_______CR REINF. STEEL CL. I SUBSTRUCT. CONST.406SD20-

_______CR REINF. STEEL CL. I SUBSTRUCT. MAINT.406SD20-

_______RAILING TEXAS T-6 CONST.410SD20-

_______SIGN POST STP-1, 2", 14 GAUGE700SD20-

Date:

Signature:

(Firm or Corporation)

(Vendor No.)

Bid Items Eligible For Asphalt Adjustment within this Project

C0000112880B50

L20

Contract ID:

Order No.:

0001 REGULAR BID ITEMSSECTION:

ltem Description Item

Number

ASPHALT CONCRETE TY. SM-9.5D CONST315SD20-0008

ASPHALT CONCRETE BM-25.0315SD20-0010

Determination of Major Items

1C0000112880B50Contract ID:

ltem Description Item

Number

PREBORING PILE .403SX20-0016

CONCRETE CLASS A3, SUBSTRUCT. CONST.404SD20-0011

Form C-110 Rev. 05-06-24

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

DBE REGULAR DEALER/DISTRIBUTOR AFFIRMATION FORM

Bidder / Contractor Name:

Project No.

FHWA No.:

Contract ID:

Date Submitted:

*** INSTRUCTIONS ***

Submit this DBE Regular Dealer / Distributor Affirmation Form for each DBE listed as a regular dealer or distributor, on the Bidder’s Form C-111 within 5 days after the bid opening, along with Form C-112 - Certification of Binding Agreement. In the questions below, “you and “your” refer to the DBE.

Section 26.53(c)(1) of Title 49 Code of Federal Regulations requires the Virginia Department of Transportation to make a preliminary counting determination for each DBE listed as a regular dealer or distributor to assess its eligibility for 60 or 40 percent credit, respectively, of the cost of materials and supplies based on its demonstrated capacity and intent to perform as a regular dealer or distributor, as defined in 49 CFR § 26.55(e)(2)(iv)(A),(B),(C), and (3) under the contract at issue. The preliminary determination will be based on the DBE’s written responses to relevant questions and its affirmation that its subsequent performance of a commercially useful function will be consistent with the preliminary counting of such participation.

DBE Name:

DBE Authorized Representative:

Total Amount of DBE Subcontract / Purchase Order:

NAICS Codes Applicable to Items Sold / Leased:

1. Will all items sold or leased be provided from the on-hand inventory at your establishment?

☐ YES (If "YES," you have indicated that your performance will satisfy the regular dealer requirements and may be counted at 60%. STOP here. Read and sign the affirmation below.)

☐ NO (If "NO" Continue.)

(a) Are you selling bulk items (e.g., petroleum products, steel, concrete, concrete products, sand, gravel, asphalt, etc.) or items not typically stocked due to their unique characteristics (aka specialty items)?

☐ YES (If "YES," Go to Question 2.)

☐ NO (If "NO" Continue.)

(b) Will at least 51% of the items you are selling be provided from the inventory maintained at your establishment, and will the minor quantities of items delivered from and by other sources be of the general character as those provided from your inventory?

☐ YES (If "YES," you have indicated that your performance will satisfy the regular dealer requirements and may be counted at 60%. STOP here. Read and sign the affirmation below.

☐ NO * (*If 1,1(a), and 1(b) above are "NO," your performance on the whole will not satisfy the regular dealer requirements; therefore, only the value of items to be sold or leased from inventory can be counted at 60%. Go to Question 3, below, to determine if the items delivered from and by other sources are eligible for Distributor credit.)

0707-056-735, B650, B699

BROS-056-7(037)

C0000112880B50

Form C-110 Rev. 05-06-24

2. Will you deliver all bulk or specialty items using distribution equipment you own (or under a long-term lease) and operate?

☐ YES (If "YES," you have indicated that your performance will satisfy the requirements for a regular dealer of bulk items and may be counted at 60%. STOP here. Read and sign the affirmation below.)

☐ NO (If "NO," your performance will not satisfy the requirements for a regular dealer of bulk items;

the value of items to be sold or leased cannot be counted at 60%. Go to Question 3.)

3. Will the written terms of your purchase order or bill of lading from a third party transfer responsibility, including risk for loss or damage, to your company at the point of origin (e.g. a manufacture's facility)?

☐ YES ☐ NO

(a) Will you be using sources other than the manufacturer (or other seller) to deliver or arrange delivery of the items sold or leased?

☐ YES ☐NO

(If you responded "YES" to both 3 and 3(a), you have indicated that your performance will satisfy the requirements of a Distributor; therefore, the value of items sold or leased may be counted at 40%.)

(If you responded "NO" to either 3 or 3(a), your performance will not satisfy the requirements for a regular dealer and counting of your participation is limited to the reasonable cost of fees or commissions charged, including transportation charges for the delivery of materials or supplies; the cost of materials or supplies may not be counted.)

For DBE:

I affirm that the information that I provided above is true and correct and that my company's subsequent performance of a commercially useful function will be consistent with the above responses. I further affirm that my company will independently negotiate price, order specified quantities, and pay for the items listed in the Bidder's Forms C-111 and C-112. This includes my company's responsibility for the quality of such items in terms of necessary repairs, exchanges, or processing of any warranty claims for damaged or defective materials.

Printed Name of DBE Owner/Authorized Representative Signature

For Bidder:

The Bidder acknowledges its responsibility for verifying the information provided by the DBE named above and ensuring that the counting of the DBE's participation is accurate. Any shortfall in DBE participation caused by errors in counting are the responsibility of the Bidder.

Printed Name of Bidder Owner/Authorized Representative Signature

Form C-111

Rev. 05-08-24

X

$ x ____ % =

$ x ____ % =

$ x ____ % =

$ x ____ % =

$ x ____ % =

$ x ____ % =

$ x ____ % =

$ x ____ % =

DBE PARTICIPATION ATTAINED PERCENT: %

BY:

DBE SUMMARY

* * * INSTRUCTIONS * * *

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

MINIMUM DBE REQUIREMENTS

Contract ID No.:

X $ = $

DBE GOAL TOTAL CONTRACT VALUE MINIMUM DBE PARTICIPATION

VENDOR ID NO.

DBE

CERTIFICATION

NO.

Subcontract

Value

SUBCONTR. (S) 100%

Fees/Com

DOLLAR AMT

DBE CREDIT

MNFR. (M) 100%

HAULER (H) 100%

REG. DLR. (R) 60%

DISTR. (D) 40%

BROKER (B)

DBE PARTICIPATION ATTAINED TOTAL: $

SIGNATURE DATE

I/WE CERTIFY THAT THE LISTED DBES WILL BE USED ON THIS CONTRACT AS STATED HEREIN AND THAT IN THE

PERFORMANCE OF THE CONTRACT I/WE WILL MAKE GOOD FAITH EFFORTS TO MEET OR EXCEED THE DBE GOAL

ESTABLISHED FOR THE CONTRACT.

BIDDER'S NAME

Project No.:

FHWA No.: Order No.:

LIST THE DBES WHO WILL PARTICIPATE IN THE CONTRACT, INDICATE THE WORK THEY WILL PERFORM, THE

NAICS CODE APPLICABLE TO THAT WORK (S, M, H, R, D, or B), AND THE DOLLAR AMOUNT OF PARTICIPATION, REDUCED AS NEEDED FOR REGULAR DEALERS (60%), DISTRIBUTORS (40%), AND BROKERS (FEES/COMMISSIONS).

COUNT 100% FOR SUBCONTRACTORS AND MANUFACTURERS, AND FOR HAULERS THAT DELIVER MATERIALS AND

SUPPLIES TO THE PROJECT SITE (EXCLUDING COST OF THE MATERIALS AND SUPPLIES ).

Title:

NAME OF DBE SUBCONTRACTOR

[ATTACH ADDITIONAL SHEETS AS NECESSARY, EACH OF WHICH MUST BE SIGNED AND DATED.]

0707-056-735, B650, B699

BROS-056-7(037)

C0000112880B50 L20

7.00

Form C-111

Rev. 05-08-24

Full DBE Name:

DBE Vendor ID: __________________________ (DBE's number can be found on VDOT's List of Prequalified Vedors)

DBE Cert. No.: __________________________(DBE's number can be found on DSBSD's DBE Directory)

Used As: Subcontractor (S) Eligible for 100% of Subcontract Value

Manufacturer (M) Eligible for 100% of Subcontract Value

Hauler (H) Eligible for 100% of Subcontract Value Excluding Materials

Regular Dealer (R) Eligible for 60%of Subcontract or PO Value

Distributor (D) Eligible for 40% of Subcontract or PO Value

Broker (B) Eligible for Fees / Commissions Only

Unit %

DBE Credit Total: $

DBE's PRICEDESCRIPTION

Instructions: For each DBE listed in the Summary on page 1, complete a DBE Item Entry form.

NOTE: To count toward the DBE goal, DBEs must be certified in NAICS codes applicable to kind of work they perform. A DBE's NAICS codes are shown in the DBE's listing in the DSBD DBE Directory at:

https://directory.sbsd.virginia.gov/#/executiveExport

DBE ITEMS ENTRY

WORK ASSIGNED TO DBE

CONTRACT BID

ITEMS

Dollar Amt

DBE CreditNAICS Code QTY

[ATTACH ADDITIONAL SHEETS AS NECESSARY, EACH OF WHICH MUST BE SIGNED AND DATED.]

Form C-112 Rev. 3-1-11

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

CERTIFICATION OF BINDING AGREEMENT WITH

DISADVANTAGED BUSINESS ENTERPRISE FIRMS

Project No.: 0707-056-735, B650, B699

FHWA NO: BROS-056-7(037)

This form is to be submitted in accordance with the Department’s Special Provision for Section 107.15.

It is hereby certified by the below signed Contractors that there exists a written quote, acceptable to the parties involved preliminary to a binding subcontract agreement stating the details concerning the work to be performed and the price which will be paid for the aforementioned work. This document is not intended to, nor should it be construed to, contain the entire text of the agreement between the contracting parties.

This document does not take the place of, nor may it be substituted for, an official subcontracting agreement in those situations that may require such an agreement. A copy of the fully executed subcontract agreement shall be submitted to the Engineer within fourteen (14) working days after contract execution.

It is further certified that the aforementioned mutually acceptable quote and fully executed subcontract agreement represent the entire agreement between the two parties involved and that no conversations, verbal agreements, or other forms of non-written representations shall serve to add to, delete, or modify the terms as stated.

The prime Contractor further represents that the aforementioned mutually acceptable quote and fully executed subcontract agreement shall remain on file for a period of not less than one year following completion of the prime's contract with the Department or for such longer period as provisions of governing Federal or State law or regulations may require. For purposes of this form, the term Prime Contractor shall refer to any Contractor utilizing a DBE subcontractor, regardless of tier, in which they are claiming DBE credit toward the contract goal.

Contractors further jointly and severally represent that said binding agreement is for the performance of a "commercially useful function" as that term is employed in 49 C.F.R. Part 26.55 (c), (d).

TO BE SIGNED BY THE SUBCONTRACTOR TO THE PRIME CONTRACTOR, AND ANY LOWER TIER

SUBCONTRACTORS HAVING A CONTRACT WITH THE BELOW NAMED DBE FIRM

Prime Contractor:

By:

Signature Title

Date:

First Tier Subcontractor If Applicable:

Form C-112 Rev. 3-1-11

Second Tier

If Applicable:

Third Tier

If Applicable

DBE Contractor

FORMS and SCHEDULE OF ITEMS PRECEDE SPCNs, SPs and SUPPLEMENTAL SPECS.

*CN100-000026-08 GEN. PROJ. REQUIRE., SSS/SPS/SPCNS 4-4-22 (SPCN) 1

CN315-000100-00 SEC. 315.05(C) PLACING AND FINISHING 1-18-17 (SPCN) 1

*DRUG-FREE WORKPLACE 7-3-19 (SPCN) 2

CN522-000300-00 PROTECT NESTING BIRDS DURING BRIDGE MAINT. 7-24-20 (SPCN) 2

CQ107-000150-00 EQUAL EMPLOYMENT OPPORTUNITY 5-11-22 2

PROTECTION OF BAT SPECIES 1-17-18 (SPCN) 3

CRUSHER RUN AGGREGATE NO. 25 OR 26 4-10-20 (SPCN) 3

CONCRETE SLABS 3-12-24 (SPCN) 4

TEMPORARY SHORING 2-2-24 (SPCN) 4

SP0F0-000100-00 PREDETERMINED MIN. WAGE RATES R-7-12-16 5

SP0F0-000130-02 FHWA 1273—REQ. PROVISIONS, FED-AID 10-3-23 11

SP0F0-000150-01 AFFIRMATIVE ACTION / EEO NOTICE 7-17-17 36

SP102-000120-00 NON-DISCRIMIN. EMPLOY. & CONTRACT. PRACTICES (EO-61) 1-10-17 42

*SP102-000510-02 USE OF DOMESTIC MATERIAL 12-19-18 43

SP105-000100-00 INFORMAL PARTNERING R-7-12-16 45

SP107-000110-00 C-45–SWPPP GEN. PERMIT–CONTRACTOR CERTIFICATION R-10-27-16 47

*SP107-000120-00 ELEC. SUBMISSION OF DBE AND PAYROLLS 1-21-20 48

SP107-001510-03 SEC. 107.15 (DBES) 5-8-24 50

*SP107-003000-01 BUILD AMERICA, BUY AMERICA ACT REQUIREMENTS 6-8-23 74

SP108-000100-01 PROG. SCHED. FOR CAT. I PROJECTS 3-21-22 76

*SP109-000100-04 ASPHALT MATERIAL PRICE ADJUSTMENT 6-29-23 91

SP109-000110-00 OPTIONAL ADJUSTMENT FOR FUEL R-7-12-16 92

SP109-000120-01* PRICE ADJUSTMENT FOR STEEL 7-2-19 94

SP217-000100-00 VERY HIGH PERFORMANCE CONCRETE (VHPC) 2-8-21 99

SP217-000110-00 ENGINEERED CEMENTITIOUS COMPOSITE (ECC) 3-16-21 103

SP401-000100-01 CLEAR & GRUB BRIDGE APPROACHES 2-28-18 106

SP404-000130-00 SHEAR KEYS AND BLOCK OUTS BETWEEN ADJACENT MEMBERS 3-25-21 108

SP407-000500-00 SUPERSTRUCTURE ERECTION STABILITY 6-10-22 110

SP522-000130-02 TREE REMOVAL TIME OF YEAR RESTRICTION 6-6-22 123

*SP700-000180-03 MODIFICATIONS TO AASHTO’S SIGN STRUCT. SPEC. 9-29-20 124

SP801-000100-01 LANE CLOSE COORD (LCC)/LANE CLOSE IMPLEMENT (LCI) 9-20-17 129

SEC. 105.06—SUBCONTRACTING (FEDERAL FUNDED PROJECTS) 2-9-17_(SP) 131

SQ107-001300-00 PREVAILING WAGE RATES 10-12-2023 132

SS109-002020-01 SEC. 109—MEASUREMENT AND PAYMENT 5-1-23 136

*SS211-002020-03 SECT 211 – ASPHALT CONCRETE 3-18-24 139

*SS220-002020-01 SEC. 220 – CONCRETE CURING MATERIALS 8-28-20 144

SECTION 223 – STEEL REINFORCEMENT 04/04/2023 145

*SS234-002020-01 SECTION 234 – GLASS BEADS AND RETROREFLECTIVE OPTICS 5-6-22 146

*SS235-002020-01 SECTION 235 – RETROREFLECTORS 5-6-22 147

SS236-002020-01 SECTION 236 – WOOD PRODUCTS 5-14-21 148

*SS246-002020-02 SECTION 246 – PAVEMENT MARKING 5-6-22 152

SS248-002020-02 SECTION 248 – STONE MATRIX ASPHALT CONCRETE 3-18-24 160

*SS305-002020-02 SECTION 305 – SUBGRADE AND SHOULDERS 12-20-23 162

SS308-002020-01 SECTION 308 -SUBBASE COURSE 7-13-21 164

SS309-002020-01 SECTION 309 - AGGREGATE BASE COURSE 7-13-21 165

SS315-002020-04 SECTION 315 – ASPHALT CONCRETE PLACEMENT 6-16-23 166

SS318-002020-01 SECTION 318—PAVEMENT INTERLAYERS 8-2-23 184

*SS319-002020-02 SECT 319 – THIN HOT MIX ASPHALT CONCRETE OVERLAY 3-18-24 185

TABLE OF CONTENTS FOR PROVISIONS

SS321-002020-02 SECTION 321 – TRENCH WIDENING 4-4-23 189

*SS407-002020-02 SEC. 407 – STEEL & METAL STRUCT 11-01-22 191

*SS411-002020-01 SEC. 411 – PROT. COAT. OF METAL 11-01-22 193

*SS512-002020-03 SECTION 512 – MAINTAINING TRAFFIC 7-1-22 194

*SS704-002020-02 SECTION 704 – PAVEMENT MARKINGS AND MARKERS 5-6-22 208

PERMIT PACKAGE 214

cn100-000026-08 GENERAL PROJECT REQUIREMENTS, SUPPLEMENTAL SPECIFICATIONS

(SSs), SPECIAL PROVISIONS (SPs) AND SPECIAL PROVISION COPIED NOTES (SPCNs)

This project shall be constructed according to: the plans; the Virginia Department of Transportation Road and Bridge Specifications, dated 2020 and the Supplement thereto, dated 2022; the Virginia Department of Transportation Road and Bridge Standards, dated 2016, with revisions issued online as of the advertisement date for this project incorporated; the 2011 edition of the Virginia Work Area Protection Manual with Revision Number 2.1 incorporated, dated November 1, 2020; the 2009 edition of the MUTCD with Revision Numbers 1 and 2 incorporated, dated May 2012; and the 2011 edition of the Virginia Supplement to the MUTCD with Revision Number 1 dated September 30, 2013; and the Supplemental Specifications, Special Provisions and Special Provision Copied Notes in this contract. The status in the Contract of each of these documents will be according to Section 105.12 of the Specifications.

Special Provision Copied Notes in this contract are designated with “(SPCN)” after the date.

The information at the top and left of each Special Provision Copied Note in this contract is file reference information for Department use only. The information in the upper left corner above the title of each Supplemental Specification and Special Provision in this contract is file reference information for Department use only.

4-4-22 (SPCN)

cn315-000100-00 SECTION 315.05(c) PLACING AND FINISHING is modified by replacing the third paragraph with the following:

The longitudinal joint in one layer shall offset that in the layer immediately below by approximately 6 inches or more. The joint in the wearing surface shall be offset 6 inches to 12 inches from the centerline of the pavement if the roadway comprises two traffic lanes. The joint shall be offset approximately 6 inches from the lane lines if the roadway is more than two lanes in width. The longitudinal joint shall be uniform in appearance. On all roads except secondary routes, if the offset for the longitudinal joint varies from a straight line more than 2 inches in 50 feet on tangent alignment, or from a true arc more than 2 inches in 50 feet on curved alignment, the Contractor shall seal the joint using a water-proof sealer at no cost to the Department. The Contractor shall recommend a sealant and installation procedure to the Engineer for approval before proceeding. On all roads except secondary routes, if the offset for the longitudinal joint varies from a straight line more than 3 inches in 50 feet on tangent alignment, or from a true arc more than 3 inches in 50 feet on curved alignment, the Engineer may reject the paving. The Engineer will not require offsetting layers when adjoining lanes are paved in echelon and the rolling of both lanes occurs within 15 minutes after laydown.

1-18-17 (SPCN)

https://outsidevdot.cov.virginia.gov/P0JQP/2016_Standard_Specifications/cn315-000100-00.docx

DRUG-FREE WORKPLACE– The Contractor shall:

• Provide a Drug-Free Workplace for the Contractor’s employees.

• Post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the Contractor’s workplace and specifying the actions that will be taken against employees for violations of such prohibition.

• State in all solicitations or advertisements for employees placed by or on behalf of the Contractor that the Contractor maintains a Drug-Free Workplace.

• Include the provisions of the foregoing clauses in every Subcontract or purchase order of over $10,000, so that the provisions will be binding upon each Subcontractor or vendor.

For the purposes of this provision, “Drug-Free Workplace” means a site for the performance of work done in connection with the Contract. The Contractors employees, and those of his Subcontractors, shall be prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession, or use of any controlled substance or marijuana during the performance of the Work.

7-3-19 (SPCN)

cn522-000300-00 PROTECTION OF NESTING BIRDS DURING BRIDGE MAINTENANCE — If bird nests are found on a bridge included in the Contract, the Contractor shall immediately notify the Engineer and suspend all work in the immediate vicinity of the nests until authorized to continue. The Contractor may proceed with other work activities that do not result in removal of nests or nest contents.

7-24-20 (SPCN)

cq107-000150-00 EQUAL EMPLOYMENT OPPORTUNITY

Section 107.14(a)1 – Required by §2.2-4201 and §2.2-4311 of the Code of Virginia is replaced with the following:

1. Required by §2.2-4201 and §2.2-4311 of the Code of Virginia: During the performance of this Contract, the Contractor agrees as follows:

a. The Contractor shall not discriminate against any employee or applicant for employment because of race, religion, color, sex, or national origin, age, disability, or other basis prohibited by state law relating to discrimination in employment, except where religion, sex, or national origin is a bona fide occupational qualification reasonably necessary to the normal operation of the Contractor. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause, including the names of all contracting agencies with which the Contractor has contracts of over $10,000.

b. The Contractor shall, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that such contractor is an equal opportunity employer. However, notices, advertisements and solicitations placed in accordance with federal https://outsidevdot.cov.virginia.gov/P0JQP/2020%20Standard%20Specifications/cn522-000300-00.docx law, rule or regulation shall be deemed sufficient for the purpose of meeting the requirements of this chapter.

c. If the Contractor employs more than five employees, the Contractor shall (i) provide annual training on the Contractor's sexual harassment policy to all supervisors and employees providing services in the Commonwealth, except such supervisors or employees that are required to complete sexual harassment training provided by the Department of Human Resource Management, and

(ii) post the Contractor's sexual harassment policy in (a) a conspicuous public place in each building located in the Commonwealth that the Contractor owns or leases for business purposes and (b) the Contractor's employee handbook.

The Contractor shall include the provisions of subdivisions a, b, and c in every subcontract or purchase order of over $10,000, so that such provisions shall be binding upon each subcontractor or vendor.

Nothing contained in this chapter shall be deemed to empower any agency to require any contractor to grant preferential treatment to, or discriminate against, any individual or any group because of race, color, religion, sex, or national origin on account of an imbalance that may exist with respect to the total number or percentage of persons of any race, color, religion, sex, or national origin employed by such contractor in comparison with the total number or percentage of persons of such race, color, religion, sex, or national origin in any community or in the Commonwealth.

5-11-22 (SPCN)

PROTECTION OF BAT SPECIES — If bats are observed roosting on a structure, the Contractor shall immediately notify the Engineer and suspend work in the immediate vicinity of the bats until authorized to continue.

1-17-18 (SPCN)

CRUSHER RUN AGGREGATE NO. 25 OR 26 shall conform to Section 205 of the Specifications and shall be placed in accordance with Section 302 of the Specifications. The aggregate shall be placed at locations shown on the Plans or as directed by the Engineer. Crusher run aggregate No. 25 or 26 will be measured in tons and will be paid for at the Contract ton price. This price shall include furnishing, placing, and compacting.

Payment will be made under:

Pay Item Pay Unit

Crusher Run Aggregate No. 25 or 26 Ton

4-10-20 (SPCN)

CONCRETE SLABS shall be fabricated in accordance with Section 405 of the Specifications, except prestressed strands are not included. Section 405.05(b) of the Specifications shall not be applicable to this Contract. Concrete curing and form removal shall be in accordance with Section 404 of the Specifications.

Concrete slabs, that are to be incorporated in the completed structure, will be measured in units of each for the size specified and will be paid for at the Contract each price. This price shall include manufacturing, fabricating, and furnishing units; reinforcing steel and rail post inserts embedded in units: anchor rods and bearing pads; post-tensioning fittings, strands, and rods, grouting, joint fillers and sealers, waterproofing applied to structural units at the prestressing plant; testing and documentation, hauling, handling, storage, and treatment.

Concrete slab (width, depth, and length) Each

3-12-24 (SPCN)

TEMPORARY SHORING utilized by the Contractor to support the existing and proposed structures and roadway while open to the traveling public shall be designed by a registered professional engineer holding a valid license to practice engineering in the Commonwealth of Virginia. Working drawings and design calculations of the shoring shall be submitted to the Engineer for review 30 days prior to installation of the shoring in accordance with Section 105.02 of the Specifications. The drawings shall include plan and profile views, details of sheet piling, walers, rakers, connections, welds, fasteners, all structural members, soldier piles, tiebacks or other means of support as determined by the Contractor and his engineer. The Contractor shall determine the methods and means of support required for the loads imposed by the roadway, traffic, the structure and any loads imposed by construction equipment during the construction of the project.

Approximate limits of temporary shoring shown on the plans are for informational purposes only. The Contractor shall be responsible for determining the actual limits and quantities of temporary shoring. The limits of temporary shoring shall be defined as that length necessary for structure excavation or minor structure excavation, and for maintaining minimum temporary slopes in accordance with OSHA requirements around the limits of structure excavation or minor structure excavation for each stage of construction. The cost of the design, installation, and removal of the temporary shoring, when no longer required, shall be included in the bid price for the temporary shoring. This price shall be full compensation for all labor, tools, materials, equipment, and incidentals required for the satisfactory completion of the work.

This price shall include all temporary shoring required for construction of the structure whether or not shown on the plans. Temporary shoring shall be paid for on a lump sum basis and shall include all construction phases.

Temporary shoring Lump sum

2-2-24 (SPCN)

SP0F0-000100-00

Reissued July 12, 2016

PREDETERMINED MINIMUM WAGE RATES

"General Decision Number: VA20240080 01/05/2024

Superseded General Decision Number: VA20230080

State: Virginia

Construction Type: Highway

County: Madison County in Virginia.

HIGHWAY CONSTRUCTION PROJECTS (excluding tunnels, building structures in rest area projects & railroad construction;

bascule, suspension & spandrel arch bridges designed for commercial navigation, bridges involving marine construction;

and other major bridges).

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |. Executive Order 14026 |

|into on or after January 30, | generally applies to the |

|2022, or the contract is | contract. |

|renewed or extended (e.g., an |. The contractor must pay |

|option is exercised) on or | all covered workers at |

|after January 30, 2022: | least $17.20 per hour (or |

| | the applicable wage rate |

| | listed on this wage |

| | determination, if it is |

| | higher) for all hours |

| | spent performing on the |

| | contract in 2024. |

|If the contract was awarded on|. Executive Order 13658 |

|or between January 1, 2015 and| generally applies to the |

|January 29, 2022, and the | contract. |

|contract is not renewed or |. The contractor must pay all|

|extended on or after January | covered workers at least | https://outsidevdot.cov.virginia.gov/P0JQP/2016_Standard_Specifications/SP0F0-000100-00.docx

|30, 2022: | $12.90 per hour (or the |

| | applicable wage rate listed|

| | on this wage determination,|

| | if it is higher) for all |

| | hours spent performing on |

| | that contract in 2024. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the

Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date

0 01/05/2024

SUVA2016-016 07/02/2018

Rates Fringes

CARPENTER, Includes Form Work....$ 17.73 1.48

CEMENT MASON/CONCRETE FINISHER...$ 19.35 0.00

IRONWORKER, REINFORCING..........$ 20.80 0.00

LABORER: Asphalt, Includes

Raker, Shoveler, Spreader and

Distributor......................$ 16.40 ** 0.00

LABORER: Common or General......$ 14.96 ** 0.00

LABORER: Pipelayer..............$ 16.75 ** 0.00

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 19.59 0.00

OPERATOR: Broom/Sweeper.........$ 12.25 ** 0.23

OPERATOR: Bulldozer.............$ 19.36 0.00

OPERATOR: Crane.................$ 26.68 0.00

OPERATOR: Grader/Blade, Includes Finishing...............$ 26.13 0.00

OPERATOR: Loader................$ 19.36 0.00

OPERATOR: Mechanic..............$ 19.13 0.00

OPERATOR: Milling Machine.......$ 21.13 0.00

OPERATOR: Paver (Asphalt, Aggregate, and Concrete).........$ 17.12 ** 0.00

OPERATOR: Roller (Finishing)....$ 18.96 0.00

OPERATOR: Roller................$ 18.11 0.00

OPERATOR: Asphalt Spreader and Distributor..................$ 18.90 0.00

TRAFFIC CONTROL: Flagger.......$ 11.82 ** 0.00

TRUCK DRIVER : HEAVY 7CY &

UNDER............................$ 16.69 ** 0.00

TRUCK DRIVER: HEAVY OVER 7

CY...............................$ 16.69 ** 0.00

TRUCK DRIVER: Single & Multi

Axle.............................$ 18.00 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.20) or 13658

($12.90). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the

Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate

(weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or

""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .