C2-Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_L15PS00555.pdf | ||
| P2-Experience PastPerformanceQuestion.pdf | ||
| C3-Maps Drawings.pdf | ||
| C4-DavisBaconPhillipsHeavy.pdf | ||
| P3-SubContractorInfoRequest.pdf | ||
| P1-ValueScheduleQuoteSheet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2015 RESERVOIR SPILLWAY REPAIR
BUREAU OF LAND MANAGEMENT
PHILLIPS COUNTY, MONTANA
NID – MTM01000
TECHNICAL SPECIFICATIONS
PREPARED FOR
BUREAU OF LAND MANAGEMENT
MALTA FIELD OFFICE
501 SOUTH 2ND
STREET EAST
MALTA, MT 59538
MAY 2015
2015 Reservoir Spillway Repair Table of Contents
05/05/2015
2015 RESERVOIRS SPILLWAY REPAIR
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
BID SCHEDULE
DIVISION 1 - GENERAL REQUIREMENTS
01010 Summary of Work
01050 Field Engineering
01060 Permits
01150 Measurement and Payment
01200 Project Meetings
01300 Submittals
01400 Quality Control
01600 Material and Equipment
01700 Contract Closeout
DIVISION 2 - SITEWORK
02110 Clearing
02275 Riprap
02300 Earth Dam
02370 Geosynthetics
02910 Restoration and Topsoiling
DRAWINGS – Bound Separately
2015 Reservoirs SUMMARY OF WORK
05/05/2015 01010-1
DIVISION 1 - GENERAL REQUIREMENTS SECTION 01010 - SUMMARY
OF WORK
PART 1 - GENERAL
1.19 WORK INCLUDED:
This project will repair the spillways at Rebate Reservoir, Rotator Cup Reservoir, and Spanky
Reservoir located in Phillips County, Montana approximately 55 miles south of Malta, Montana.
Major items of work for each reservoir include:
Rebate:
If necessary, dewater reservoir and construction area.
Excavate the spillway cut, and fill and compact the cut.
Realign the spillway by adding a 3+25 foot extension that diverts the spillway further north. Between stations 2+00 and 3+25 include riprap protection and Geosynthetics
(02370).
Reconstruct the road traveling along the spillway, providing access to the top of the reservoir.
Reclaim all disturbed areas including staging areas and temporary roads. Reclamation consists of preparation of the soil for seeding but does not include seeding. Seeding will be completed by Others.
Rotator Cup:
If necessary, dewater reservoir and construction area.
Excavate the spillway cut, and fill and compact the cut.
Realign the spillway by adding a 1+06 foot extension that diverts the spillway further north into the next drainage. Between stations 0+55 and 1+06 include riprap protection and Geosynthetics (02370). Include riprap protection and blanket drain system in two 75 foot sections below spillway in the natural channel.
Reclaim all disturbed areas including staging areas and temporary roads. Reclamation consists of preparation of the soil for seeding but does not include seeding. Seeding will be completed by Others.
Spanky:
If necessary, dewater reservoir and construction area.
Excavate the spillway cut, and fill and compact the cut.
Extend the spillway to the north by cutting away the north bank and using it to fill in the existing cut. Construct a berm along the existing cut. The new spillway will run parallel to the existing spillway.
Between stations 0+80 and 1+50 include riprap protection and Geosynthetics (02370).
Reclaim all disturbed areas including staging areas and temporary roads. Reclamation consists of preparation of the soil for seeding but does not include seeding. Seeding will be completed by Others.
05/05/2015 01010-2
1.20 CONTRACTOR USE OF PREMISES:
Confine operations to the site of the proposed Work or within the right-of-way or construction easements provided and shown on the drawings. Construction camps and staging areas outside the construction area must be approved by the Contracting Officer (CO). Obtain advance approval from the CO of all staging areas, excavated soil stockpile and waste areas and camp areas.
It shall be understood that the responsibility for protection and safekeeping of equipment and materials on or near the site will be entirely that of the CONTRACTOR and that no claim shall be made against the GOVERNMENT by reason of any act of an employee or trespasser whether
GOVERNMENT has paid CONTRACTOR for equipment or materials in storage or not. It shall be further understood that should any occasion arise necessitating access by the GOVERNMENT to the sites occupied by these stored materials and equipment, the CONTRACTOR owning or responsible for the stored materials or equipment shall immediately remove same. No materials or equipment may be placed upon the property of the GOVERNMENT until the CO has agreed to the location contemplated by the CONTRACTOR to be used for storage. CONTRACTOR is solely responsible for obtaining and shall pay all costs in connection with any additional work area, storage sites, access to the site, or temporary right-of-way, which may be required for proper completion of the Work.
No waste fluids from equipment (such as fuel, oil, grease or antifreeze) shall be drained or spilled on the ground. All waste fluids shall be captured and disposed of properly offsite. Of a waste fluid is accidentally spilled on the ground, the Contractor shall excavate the spill area to a depth 12 inches below contaminated material, remove excavated material from the worksite and dispose of it properly offsite, at the Contractor’s expense.
1.21 PROTECTION OF EXISTING UTILITIES:
Utility service connections are generally shown on the drawings, but the CONTRACTOR is solely responsible for locating all existing underground installations, including service connections, in advance of excavating or trenching, by contacting 1-800-424-5555 or the owners thereof and prospecting. The CONTRACTOR shall use his own information and shall not rely solely upon information shown on the drawings concerning existing underground installations. Repair all damage to existing utilities or property at CONTRACTOR's expense.
1.22 PROTECTION OF EXISTING STRUCTURES:
Where excavation will be required adjacent to existing structures, the CONTRACTOR is solely responsible to maintain the structural integrity of the existing structures. Take whatever means necessary to insure that the existing structures are not damaged. Repair all damage to the existing structures at CONTRACTOR's expense. Repair any fences destroyed or damaged during construction to the satisfaction of the government. Unless otherwise noted on the Construction
Drawings, restore all existing ditches disturbed by construction to their original size, line, and grade.
Structures located downstream of the dam shall also be protected during reservoir dewatering
05/05/2015 01010-3 activities. Restore or repair to original condition roads, culverts, bridges, cattleguards and fences or any other structures damaged by the CONTRACTOR’s activities and access to the sites at no additional cost to the project.
1.23 FIELD CHECK OF EXISTING STRUCTURES:
Dimensions and elevations of existing structures and locations of existing fences, pipelines, conduits, cables, and equipment shown on the drawings were taken for the most part from available records and survey data and are not guaranteed for accuracy.
Check all dimensions and elevations of existing structures, pipelines, conduits, cables, equipment, or other existing items, both above and below ground, affected by or affecting the Work under this contract, prior to the start of construction or ordering materials and equipment affected thereby.
1.24 SITE ACCESS:
Determine the adequacy of all roads, culverts, cattleguards, and bridges used in moving or gaining access for equipment and materials to the construction site. Provide alternative methods of access, such as a temporary crossing for any equipment that exceeds the structural limits of existing facilities. Improvements for road access including fill, culverts, and fencing to remain after project completion as approved by CO.
Access to the Work:
1. Access to the Work: Access to the work area shall be on existing public roads.
Any public or private roads including cattle guards, gates and culverts, or any off road travel areas damaged in an way by the Contractor’s operations shall be restored by the
Contractor, at the Contractor’s expense, to the same condition existing prior to the commencement of work.
2. Access to the work shall be provided by and at the Contractor's expense. Prior to the building of access routes across lands under the jurisdiction of the Bureau of Land
Management, the Contractor shall obtain approval of the Contracting Officer.
3. Public or private access roads damaged by the Contractor shall be restored, at the
Contractor's expense, to the same condition they were in at the commencement of work.
4. Access to construction shall be accomplished with regard for environmental considerations.
05/05/2015 01010-4
1.14 SEQUENCING AND SCHEDULING:
Permitted Work Period: Work on this project can only occur between July 15th and November
30th during any calendar year to accommodate wildlife concerns in the vicinity.
Work Schedule: The schedule shall be submitted at the pre work conference. When requested, submit an updated schedule within 3 calendar days. As a minimum, the estimated start and completion dates shall be shown in the schedule.
1.08 QUALITY ASSURANCE:
Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference, with the same force and effect as when they were given in full text.
Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.
1.15 DELIVERY, STORAGE, AND HANDLING:
Delivery: Protect products incorporated into the work from damage while in transit to the site.
Storage: Provide temporary storage facilities for products. Storage shall comply with the manufacturer's instructions. The storage area shall permit access for inspection and handling.
Handling: The Contractor shall replace, at his expense, any products damaged by loading, hauling and unloading.
1.16 LIVESTOCK:
The CONTRACTOR shall provide temporary fencing for excluding livestock from construction areas, excavations, trenches, etc.
CONTRACTOR shall be solely responsible for any livestock injuries or losses as a result of
CONTRACTOR’s activities.
1.17 FIELD OFFICES AND SHEDS:
Provide field offices and storage sheds required for completion of the work. Locate these temporary structures in areas approved by the CO. All expenses for telephone, utilities, security and waste disposal are the responsibility of the CONTRACTOR. Provide the name and telephone number of a representative who may be contacted after hours in case of emergency.
05/05/2015 01010-5
1.18 SOILS:
The following design criteria would be included with this action:
1. Construction activities shall not be performed during periods when the soil is too wet to adequately support equipment/vehicles. If equipment/vehicles create ruts in excess of 3 inches deep, operations must cease as the soil will be deemed too wet to adequately support equipment/vehicles.
2. Erosion control and sediment containment BMPs (i.e., straw wattles, silt fence, erosion control blankets, Mats, etc.) shall be installed, where necessary and required by the MTDEQ Permit, to aid in stabilization and capture of sediment until vegetation reestablishes to effectively control erosion and sediment.
3. Where soils are disturbed and topsoil is present, topsoil shall be stripped, separated from subsoil/parent material, and stockpiled for use in reclamation.
1.19 WILDLIFE:
Surface disturbing activities will not be permitted between March 15- July 15 to mitigate impacts to Great sage-grouse breeding and nesting activities.
1.20 INVASIVE VEGETATION:
Vehicles and equipment shall be cleaned prior to entering the project area to prevent the introduction of invasive plants/seeds.
An inventory and possible treatment of the sites should be done prior to the commencement of the project so that the presence / absence of invaders can be identified and dealt with.
1.21 PREPARATION:
Work Layout: The Government will set survey stakes and monuments to give the Contractor measurements, lines and grades necessary for the work executed under the Contract. Survey stakes, monuments or benchmarks disturbed or removed during construction shall be reset by the
Contractor at the Contractor's expense.
Work Limits and Control Points: Will be staked and established by the Contracting Officer.
1.22 PROJECT MONUMENT:
Requirements: None
05/05/2015 01010-6
1.23 SALVAGEABLE ITEMS:
Requirements: Salvageable items to be removed from the site shall become the property of the
Contractor. All materials salvaged off the individual sites will be removed from government property and legally disposed of, all fees associated with the removal and disposal shall be paid for by the contractor. Burning or burying of removed materials is not permitted on government property.
1.24 DISPOSAL OF DEBRIS:
Requirements: Items or debris to be removed from the site, but not designated as salvageable items for the Government, shall become the property of the Contractor. Disposal of materials offsite in a legal manner and payment of disposal fees required is the Contractor's responsibility.
Burning or burying of removed materials is not permitted on government property.
1.25 REFERENCES:
References to documents, such as ASTM, shall be for the current printing.
1.26 ABBREVIATIONS:
AASHTO - American Association of State Highway and Transportation Officials
ACI - American Concrete Institute
ASTM - American Society for Testing and Materials
AWWA – American Water Works Association
CO - Contracting Officer
OSHA - Occupational Safety and Health Act
PVC - Polyvinyl Chloride
RCP – Reinforced concrete pipe
PART 2 - PRODUCTS – NONE
PART 3 - EXECUTION – NONE
05/05/2015 01010-7
PART 4 - PAYMENT – NONE
PART 4: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT
A. UNITS: THE WORK DISCRIBED IN THIS SECITON WILL NOT BE
MEASURED FOR PAYMENT
4.2 BASIS OF PAYMENT
A. PAYMENT: NO DIRECT PAYMENT FORTHE WORK DISCRIBED UNDER
THIS SECTION WILL BE MADE. CONSIDERATION FOR THIS ITEM SHALL BE
INCLUDED IN THE BID PRICE FOR OTHER ITEMS IN THE CONTRACT.
END OF SECTION 01010
2015 Reservoir Spillway Repairs FIELD ENGINEERING
05/05/2015 01050-1
DIVISION 1 - GENERAL REQUIREMENTS SECTION 01050 - FIELD ENGINEERING
1.01 WORK INCLUDED:
GOVERNMENT will established primary control with control points adjacent to the Work site.
GOVERNMENT will develop and provide any necessary surveys, grade stakes, and benchmark.
CONTRACTOR is responsible to perform measurements and maintain controls to complete the construction as staked by the government in the field. If the initial staking completed by the
GOVERNMENT is destroyed in the construction process the CONTRACTOR is responsible for the cost of any re-staking that is required.
1.02 PRESERVATION OF REFERENCE POINTS:
Carefully preserve bench marks, reference points, section corners, and stakes and, in case of destruction, the CONTRACTOR is responsible for the resetting of such points and responsible for any mistakes that may be caused by their loss or disturbance.
1.03 COMPACTION TESTS:
The Government will perform proctors for the soils and use their equipment to test compaction and moisture.
PART 4 - MEASUREMENT AND PAYMENT:
4.1 METHOD OF MEASUREMENT:
Units: The work described in this section will not be measured for payment.
4.2 BASIS OF PAYMENT:
Payment: No direct payment for the work described under this section will be made.
The Contractor shall include consideration for this item in the bid price for other items of the contract.
END OF SECTION 01050
2015 Reservoir Spillway Repair PERMITS
05/05/2015 1060-1
DIVISION 1 - GENERAL REQUIREMENTS SECTION 01060 – PERMITS
Prepare, maintain, and proceed in conformity with Storm Water Discharge Permit/Storm Water
Pollution Prevention Plan as required by the Montana Department of Environmental Quality. Once the contractor prepares and submits the final permit to the Government, the Government will obtain this permit and pay all fees associated with the Storm Water Discharge Permit. During the construction of the reservoir the Contractor is responsible for all maintenance to the pollution prevention plan. When the Contractor has completed work on the project and has been issued the final payment, the Government will continue maintenance on the pollution prevention plan. When all criteria have been met, the Government will file the Notice of Termination for the permit.
Except as otherwise noted, identify, obtain, maintain, and proceed in conformity with any and all additional required permits necessary for completion of the Work.
Any costs associated with these Permits are included as part of the Contract Price as incidental costs.
The Contractor shall have an licensed administrator associated with this project during the time he is responsible for the controls
1.02 SUBMITTALS:
The Contractor shall supply to the Government a draft Storm Water Discharge Permit within 10 days after issuance of the Notice to Proceed. The Government will have 10 days to review and provide comments back to the Contractor. The Contractor then has 10 additional days to submit the final Storm Water Discharge Permit to the Government. Work may proceed after the final Storm
Water Discharge Permit has been returned to the Contractor with an acceptance letter from the
MTDEQ. The Contractor shall perform all compliance testing required by all permits. Submit results of compliance testing directly to the appropriate review agency. Provide copies of all results to the Government. Submit copies of any additional required permits to the Government when they are acquired.
PART 2 - PRODUCTS - NONE
The Contractor shall be responsible for the purchase, and installation of all materials required by the avoce note permit.
2015 Reservoir Spillway Repair PERMITS
05/05/2015 1060-2
PART 3 - EXECUTION - NONE
Units: The work described in this section will not be measured for payment.
END OF SECTION 01060
2015 Reservoir Spillway Repair MEASUREMENT AND PAYMENT
05/05/2015 01150-1
DIVISION 1 - GENERAL REQUIREMENTS SECTION 01150 - MEASUREMENT AND PAYMENT
1.01 SCOPE:
The method of measurement and basis of payment is described in this section.
1.02 GENERAL:
A. Bid price for each item of the Contract covers all Work shown on the Drawings and required by the specifications and other Contract Documents.
B. All costs are included in the unit and lump-sum prices bid including all materials, equipment, supplies and appurtenances; all construction plant, equipment, and tools; and all labor and supervision necessary to fully complete the Work.
C. No item that is required by the Contract Documents, for the proper and successful completion of the Work, will be paid for outside of or in addition to the prices submitted in the Bid.
D. All work not specifically set forth as a pay item in the Bid Form is considered an incidental obligation of the CONTRACTOR, and all costs in connection therewith shall be included in the unit prices bid.
1.03 ESTIMATED QUANTITIES:
A. All quantities in the Price Schedule of the Bid Form or other Contract Documents, which are to be paid per field measurement, are approximate only, and are to be used only as:
1. A basis for estimating the probable cost of the Work, and
2. For the purpose of comparing Bids submitted for the Work.
B. Actual work performed, and materials furnished under the unit-price items for those items to be field measured may differ from the estimated quantities.
C. Basis of payment for work and materials will be the actual amount of work done and materials furnished to the pay lines defined in this section.
D. Payment will be paid at the unit price bid for listed items successfully completed according to
Contract requirements.
05/05/2015 01150-2
E. Lump-sum items and those based on neat-line plan dimensions are not field-measured. They will be paid at neat-line or the lump-sum price bid for the items listed.
1.04 AUTHORITY:
A. Contracting Officer will perform all measurements and compute quantities for payment.
B. Contracting Officer will verify measurements and quantities provided by CONTRACTOR.
C. CONTRACTOR provides access to work areas for survey measurements, as required.
1.05 MEASURED QUANTITIES:
A. Measurement by Volume: Measured by cubic dimension using mean length, width, and height or thickness.
1. Fill quantities will be computed using the average-end-area method or other computation method approved of by the Contracting Officer.
B. Measurement by Area: Measured by square dimension using mean length and width. Items that are measured by area will be measured parallel to the ground surface.
C. Linear Measurement: Measured by linear dimension at the item centerline or mean chord.
Items that are measured by the lineal foot will be measured parallel to the ground surface, unless otherwise specified.
D. Stipulated Sum/Price Items: Measured by weight, volume, area, or linear means, or combination, as appropriate, as completed items or units of the work.
E. Lump-Sum Items: Will not be measured for payment. Interim measurements may be made to monitor work progress.
1.06 SCHEDULE OF VALUES:
A. A schedule of values or “allocation of contract price” is required for all lump sum items.
B. The schedule of values is used only to help assess the intermediate value of work completed for the purpose of making progress payments. The schedule of values is not considered as a commitment to prices in the event of later negotiations.
05/05/2015 01150-3
1.07 MEASUREMENT AND PAYMENT ITEMS:
Item 101 – Mobilization & Preparatory Work: Consists of preparatory work and operations performed by the CONTRACTOR, including but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for the establishment of facilities necessary for all work on the project; for premium on bonds and insurance for the
Contract; and for other work and operations that must be performed or costs incurred before beginning work on the various items on the project site.
Mobilization costs for subcontracted work are also considered included.
Demolition and disposal of all existing structures designated for removal in the Contract Documents but not specifically included in other payment items are included in this payment item.
Measurement and payment for mobilization and preparatory work will be made at the Contract lump sum price. Progress payments for mobilization and preparatory work will be as follows:
When 5 percent of the total original Contract amount is earned from other Contract items, 50 percent of the amount bid for mobilization will be included in the progress payment estimate.
When 40 percent of the total original Contract amount is earned from other schedule items, the balance of the amount bid for mobilization and preparatory work will be included in the progress payment estimate.
Item 102 – Topsoil Stripping & Replacement: Consists of stripping, stockpiling and replacing topsoil from all staging, borrow, excavation, embankment, and waste areas. Topsoil stripping and replacement will be measured and paid at the Contract lump sum price evenly spread under excavation and embankment.
Item 103 –Excavation: Consists of excavation and stockpiling or wasting as necessary to construct work in accordance with the Contract Documents. The combined excavation of approximately 6800 CY. The quantity measured for payment will be to the defined neat-lines or as otherwise directed by the CO. Unauthorized over-excavation will not be included in measurement for this item. Payment for this work will be made at the Contract unit price per cubic yard.
Item 105 – Compacted Embankment: Consists of loading from stockpiles or excavating from borrow areas, hauling, placing and compacting embankment in accordance with the Contract
Documents. The quantity measured for payment will be to the defined neat-lines or as otherwise directed by the CO. Embankment placed to compensate for unauthorized over-excavation will not be included in measurement for this item. Payment will be made at the Contract unit price per cubic yard.
05/05/2015 01150-4
Item 106 – Riprap Slope Protection: Consists of supplying from government stockpiles and placing riprap on the designated spillway sections in accordance with the Contract Documents.
Measurement will be computed using the neat line dimensions shown on the Drawings. Payment for this work will be made at the Contract unit price per cubic yard.
Item 107 – Stabilization Fabric: (Field Measured). Consists of furnishing and installing geotextile stabilization fabric in accordance with the Contract Documents in areas directed by the CO.
Payment for this work will be made in conjunction with the placement of the riprap. The placement of the stabilization fabric should be factored in the cost of the installation of the riprap.
Units: The work described in this section will be paid for under RIPRAP section 02275
END OF SECTION 01150
2015 Reservoir Spillway Repair PROJECT MEETINGS
05/05/2015 01200-1
DIVISION 1 - GENERAL REQUIREMENTS SECTION 01200 - PROJECT MEETINGS
1.01 PRE-CONSTRUCTION CONFERENCE:
A. A pre-construction conference will be held prior to the start of work. CONTRACTOR will be notified in advance of meeting time, date, and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
B. CONTRACTOR, subcontractors and the persons responsible for coordination of the work are required to be present at the meeting.
C. CONTRACTOR, if contractor chooses to use materials not specifically outlines in the contract they are required to provide submittals details those materials or methods used in construction.
1.02 MID-CONSTRUCTION CONFERENCE:
A. Mid-construction conferences may be held during construction. CONTRACTOR will be notified in advance of meeting time, date, and place. The purpose will be to review required and completed work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
1.03 CLOSEOUT CONSTRUCTION CONFERENCE:
A. A closeout construction conferences will be held after all construction has been completed.
CONTRACTOR will be notified in advance of the meeting time, date, and place. The purpose will be to review completed work, payroll, cleanup, and final payments.
05/05/2015 01200-2
3.01 PROJECT MEETINGS
A. Pre Work Conference:
1. Will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date, and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
2. The Contractor, subcontractors and the persons responsible for coordination of the work shall be present at the meeting.
3. Be prepared to summarize and explain procedures planned for the project and present the submittals requested in the specifications.
B. Progress Meetings:
1. To be held at the project site, or as determined by the Contracting Officer.
2. May be called by either the Contracting Officer or the Contractor. Request shall state who should attend and include an agenda.
C. Final Inspection:
1. To be held at the project site, or as determined by the Contracting Officer.
2. Notify the Contracting Officer in writing at least 5 working days before the completion date so the Government can schedule final inspection.
3. The superintendent shall be present during this inspection.
05/05/2015 01200-3
END OF SECTION 01200
2015 Reservoir Spillway Repair SUBMITTALS
05/05/2015 01300 - 1
DIVISION 1 - GENERAL REQUIREMENTS SECTION 01300 – SUBMITTALS
1.01 DESCRIPTION:
This section includes the procedures for submittals. Items that need to be reviewed by the
GOVERNMENT are included.
PART 3 - EXECUTION
3.01 SUBMITTAL PROCEDURE:
A. Coordinate all submittals and review them for accuracy, completeness, and compliance with contract requirements; and indicate CONTRACTOR's approval thereon as evidence of such coordination and review. Items submitted without evidence of the CONTRACTOR's approval will be returned for resubmission.
B. Date and Number: Forward to GOVERNMENT at least 30 days prior to needing approval or delivery to the site, all items required by the individual sections of the specifications. Unless a different number is called for in the individual sections, submit six copies of each submittal, six copies of all operation and maintenance instructions, and four specimens of each sample requested, of which all but two copies will be retained by GOVERNMENT. The other copies will be returned to the CONTRACTOR along with the GOVERNMENT's comments. If the
CONTRACTOR wants more than two copies returned, submit the number of additional copies desired.
C. Cover Letter: Forward all submittals with a cover letter from the CONTRACTOR, identifying the project and the portion of the Project to which it applies. Submittals that are related to or affect each other shall be forwarded simultaneously as a package to facilitate a coordinated review. Uncoordinated submittals will be rejected. The GOVERNMENT reserves the right to require submittals in addition to those called for in individual sections.
3.02 GOVERNMENT'S APPROVAL:
The GOVERNMENT will indicate approval or disapproval of each submittal and, if not approved, will indicate reasons therefor. Any work done prior to approval shall be at the CONTRACTOR's own risk. Any work done, or materials provided, prior to approval will not be eligible for payment until approval is obtained. Approvals do not relieve the CONTRACTOR from responsibility for
05/05/2015 01300 - 2 complying with the requirements of this Contract. If submittals show variations from the Contract requirements, the CONTRACTOR shall describe such variations in writing, in the cover letter at the time of submission. The request for a variation shall include a proposal addressing the net effect on contract price and time.
3.03 REQUIRED SUBMITTALS:
A. Permits: Submit to the Contracting Officer at the preconstruction conference a copy of all permits required by the governing authorities not obtained by the Government.
B. Subcontractors: At the preconstruction conference, provide a list of all suppliers and subcontractors to be used on the project and a completed Form SF1413 (form provided at the end of this section) for each subcontractor.
C. Certificates: For those items called for in individual sections, furnish certificates from manufacturers, suppliers, or others certifying that materials or equipment being furnished under the Contract comply with the requirements of these specifications.
D. Work Schedule and Progress Payment Schedule: Submit a Work Schedule and an estimated
Progress Payment Schedule.
E. Operation and Maintenance Instructions: Include printed installation instructions, operating instructions, maintenance literature, lubrication requirements, and parts lists.
3.04 SUMMARY OF PROJECT- SPECIFIC REQUIRED SUBMITTALS: The following is a summary of submittals, by section, required by these specifications. Consult individual sections for a more complete description of individual requirements.
05/05/2015 01300 - 3
List of Submittals*
Submittal
Number Submittal
Specification
Reference Date Due**
01150-1 Schedule of Values for Lump Sum Items 01150 **
01300-1 Contractor-Obtained Permits 01300 Preconstruction Conf.
01300-2 List of Subcontractors & Suppliers with completed
Form SF1413 for each subcontractor
01300 Preconstruction Conf.
01300-3 Work Schedule 01300 Preconstruction Conf.
01300-4 Estimated Progress Payment Schedule 01300 **
01300-5 Operation and Maintenance Instructions 01300 At project closeout
02300-4 Embankment Construction Plan 02300 **
*This list is not intended to be exhaustive; consult individual sections.
**Due date for all submittals is 30 days prior needing approval or delivery to the site, unless stated otherwise.
05/05/2015 01300 - 4
END OF SECTION 01300
2015 Reservoirs Spillway Repair QUALITY CONTROL/ QUALITY ASSURANCE
05/05/2015 01400-1
DIVISION 1 - GENERAL SECTION 01400 - QUALITY CONTROL/
REQUIREMENTS QUALITY ASSURANCE
1.01 DEFINITIONS:
A. Quality Control - planned and specific actions or operations necessary to produce a product that complies with the contract documents. Quality control consists of actions, inspections, sampling and testing necessary to ensure the work is in compliance with the contract documents and to control production and construction processes. Quality control is keyed to the construction sequence to quickly determine when the work is out of compliance with the contract documents and to respond to correct the situation and bring the work into compliance. Quality control is the responsibility of the CONTRACTOR.
B. Quality Assurance – planned and systematic observations, testing and actions to verify that the work complies with the contract documents. Quality assurance includes oversight of the
CONTRACTOR’s quality control, verifying the results of the CONTRACTOR’s testing and additional assurance sampling and testing. The GOVERMENT will provide quality assurance at a level determined necessary by the Contracting Officer.
C. Verification/Compliance Testing – sampling and testing which is carried out independent of the CONTRACTOR’s quality control testing to confirm/verify that the work complies with the contract documents. The frequency of verification/compliance testing will be determined by the
Contracting Officer. Verification/compliance testing will not be used to determine construction procedures or operations (i.e. rolling patterns, lift thickness, etc.). Verification/compliance testing will be provided by the Contracting Officer.
3.01 COOPERATION WITH QUALITY ASSURANCE:
A. Assure that the GOVERNMENT and Contracting Officer have access to all work areas at all times work is in progress. Provide any special facilities or equipment to access work areas at
CONTRACTOR expense.
2015 Reservoirs Spillway Repair QUALITY CONTROL/ QUALITY ASSURANCE
05/05/2015 01400-2
B. Notify the Contracting Officer when the work is ready for quality assurance/quality control testing. Establish and update the construction schedule to provide the Contracting Officer estimated sampling/testing dates and times. Contracting Officer may choose to obtain a split and comparison test of any samples collected for quality control testing. Provide adequate notice of testing plans to coordinate collection of samples.
END OF SECTION 01400
2015 Reservoir Spillway Repair MATERIAL AND EQUIPMENT
05/05/2015 01600 - 1
DIVISION 1 - GENERAL REQUIREMENTS SECTION 01600 - MATERIAL AND EQUIPMENT
1.01 COMPLETION OF WORK:
It is understood that, except as otherwise specifically stated in the Contract Documents, the
CONTRACTOR shall provide and pay for all materials, labor, tools, equipment, water, light, power, transportation, supervision, temporary construction of any nature, and all other services and facilities of any nature whatsoever necessary to execute, complete, and deliver the Work within the specified time.
1.02 CONTRACTOR RESPONSIBILITY:
Store materials so as to insure the preservation of their quality and fitness for the Work. Locate stored materials to be incorporated in the Work so as to facilitate prompt inspection by the
GOVERNMENT. The CONTRACTOR is responsible for the condition and security of all materials furnished by CONTRACTOR, and shall replace all such material found to be defective or which has been damaged after delivery. This includes the replacement of material which is found to be defective at any time prior to expiration of the guarantee period.
1.03 MANUFACTURER'S RECOMMENDATIONS:
Apply, install, connect, erect, use, clean, and condition manufactured articles, materials and equipment as directed by the manufacturer.
1.04 SAMPLES:
Provide materials, supplies and equipment in accordance with samples submitted by the
CONTRACTOR and approved by the Contracting Officer.
2015 Reservoir Spillway Repair MATERIAL AND EQUIPMENT
05/05/2015 01600 - 2
END OF SECTION 01600
2015 Reservoirs Spillway Repair CONTRACT CLOSEOUT
05/05/2015 01700-1
DIVISION 1 - GENERAL REQUIREMENTS SECTION 01700 - CONTRACT CLOSEOUT
The work covered under this section includes items required in final closeout of this Project.
Included are items such as post-construction inspection, acceptance of the work, closeout records and Project record drawings.
Provide closeout submittals for approval prior to final payment. Items to be submitted are:
A. Project Record Documents - See Item 3.02 for requirements.
PART 2 - PRODUCTS
2.01 MISCELLANEOUS PRODUCTS:
Provide all maintenance materials, spare parts, tools, keys and other items either required in the
Contract Documents or furnished by the suppliers of the various products.
3.01 CLEANING:
Remove all tools, equipment, surplus materials, and rubbish. Repair all marred surfaces, and remove grease, dirt, stains and foreign materials from finished surfaces.
3.02 PROJECT RECORD DRAWINGS:
Using red colored ink, CONTRACTOR shall mark changes on a set of clean prints. Indicate all changes and revisions to the original design that affect the permanent structures and that exist in the completed work. Reference all underground facilities to permanent physical objects. Reference elevation of all existing lines on profile sheets or call out elevations in plan if no profile exists.
Keep record drawings current during construction activities. Certification of accuracy and completeness is required on monthly payment requisitions.
3.03 POST-CONSTRUCTION INSPECTION:
2015 Reservoirs Spillway Repair CONTRACT CLOSEOUT
05/05/2015 01700-2
Prior to expiration of the one-year correction period, the GOVERNMENT will inspect the Project to determine whether corrective work is required. The CONTRACTOR will be advised 5 days prior to inspection and notified in writing of all deficiencies. CONTRACTOR shall attend the post-construction inspection.
END OF SECTION 01700
2015 Reservoir Spillway Repair CLEARING
05/05/2015 02110-1
DIVISION 2 – SITEWORK SECTION 02110 - CLEARING
The work within this section consists of removing all trees, root balls, shrubs, brush, tall grass and similar vegetation as necessary to complete the Work.
3.01 REQUIREMENTS:
Remove all trees, shrubs, brush, tall grass, and similar vegetation in conflict with the Work.
Perform all clearing in a safe, prudent and lawful manner and only within the construction limits indicated on the Drawings and staked in the field. Dispose of all trees onsite in a slash pile at no additional cost to the GOVERNMENT. Trees will have their limbs removed and will be cut into 5 foot or shorter sections. Remove no trees from the site without approval from the CO. No trees shrubs or other vegetation will be buried.
END OF SECTION 02110
2015 Reservoirs Spillway Repair RIPRAP
05/05/2015 02275-1
DIVISION 2 – SITEWORK SECTION 02275 RIPRAP
Requirements for the placement of governments supplied riprap for the Projects.
1.02 REFERENCES:
The publication(s) listed below form a part of these specifications to the extent referenced. The publications are referred to by the basic designation only.
A. American Society of Testing and Materials (ASTM)
1. ASTM C88 Test Method for Soundness of Aggregates by
Use of Sodium Sulfate or Magnesium Sulfate
2. ASTM C127
3. ASTM C535
Test Method for Density, Relative Density, and
Absorption of Coarse Aggregate
Test Method for Resistance to Degradation of
Large-Size Coarse Aggregate by Abrasion and
Impact in the Los Angeles Machine
4. ASTM D4992 Standard Practice for Evaluation of Rock to be
Used for Erosion Control
5. ASTM D5312 Test Method for Evaluation of Durability of
Rock for Erosion Control Under Freezing and
Thawing Conditions
6. ASTM D6473 Test Method for Specific Gravity and
Absorption of Rock for Erosion Control
Riprap provided near the intersection of Rebate Reservoir road and Lark reservoir road and near
Taint Reservoir. See Government furnished property section 01019.
3.01 AREAS TO RECEIVE SLOPE PROTECTION
A. Place riprap erosion protection as indicated and staked in the field.
3.02 PLACING
A. Subgrade Preparation:
1. Excavate, fill, or grade foundation soils in accordance with Section 02300 so riprap
2015 Reservoirs Spillway Repair RIPRAP
05/05/2015 02275-2 limits are as indicated on the Drawings or as directed by the CO.
2. Install woven or non-woven geotextile fabric underlayment, on prepared surfaces, ensuring required manufacturer’s Recommendations for overlaps are maintained and outer edges of geotextile are buried a minimum of 1 foot below grade. Geotextile fabric specifications are outlines in section 02370, Geosynthetics
B. Slope-protection rock need not be hand-placed or compacted but shall be handled and dumped to avoid material segregation. Riprap should be placed with an average depth of 1.5 feet. Riprap should be placed consistently and evenly throughout the marked areas.
C. Place Class III rocks as indicated in the field to help construct small pools and dissipate energy. Place Class II rocks so that larger rocks are evenly distributed and small rock fragments fill the spaces.
D. Dump and smooth by moving rocks into position so that material, when in place, is stable.
E. Begin slope-protection at toe and proceed up the slope.
F. Leave no unfilled spaces within slope protection.
A. Units: RIP-RAP installation will be paid for by the cubic yard of rock installed measured using neat lines. Rip-Rap installation will include transportation of government supplied rip-rap from the storage site to the reservoir. Installation of geotextile and, placement of rip-rap as per specifications and drawings.
A. Payment: Prices and payment will be full compensation for the work described in this section, except as otherwise noted in part 4.1
B. Payment will be made under:
Pay Item: Pay Unit:
02275(1) RIP-RAP Installation Rebate YD3 02275(2) RIP-RAP Installation Rotator Cup YD3 02275(3) RIP-RAP Installation Spanky YD3
END OF SECTION 02275
2015 Reservoir Spillway Repair EARTHWORK
05/05/2015 02300-1
Division 2- SITEWORK Section 02300 – Earthwork
PART 1 - GENERAL
1.1 SECTION REQUIREMENTS
A. Unit prices for rock excavation are included in Division 1 Section "Price and Payment
Procedures."
B. Unauthorized excavation consists of excavation below subgrade elevations or beyond indicated lines and dimensions without direction by Contracting Officer. Unauthorized excavation, as well as remedial work directed by Contracting Officer, shall be without additional compensation.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Satisfactory Soil: ASTM D 2487 Soil Classification Groups GW, GP, GM, SW, SP, and SM;
free of rock or gravel larger than 2 inches (50 mm) in any dimension, debris, waste, frozen materials, vegetation, or other deleterious matter.
B. Unsatisfactory Soil: ASTM D 2487 Soil Classification Groups GC, SC, ML, MH, CL, CH, OL, OH, and PT.
C. Backfill and Fill: Satisfactory soil materials.
D. Riprap: Class II and class III riprap will be stockpiled at nearby locations by the government.
As designated in section 01019 Government furnished property.
2.2 Preparation/Spreading/Conditioning/Processing/Compacting Equipment
A. General: Maintain equipment in good working condition at all times, and according to manufacturers’ specifications.
B. Foundation Preparation/Cleaning Equipment:
1. Hand Tools: including but not limited to shovels, bars, picks, wedges, brooms and light power tools as approved by the Contracting Officer.
2. Earth Moving Equipment: Graders, backhoes, skid steers, loaders, excavators, and dozers capable of “benching” into natural materials on sloping surfaces steeper than
3:1 (horizontal to vertical) and into the existing embankment to remove loose and dry material and to provide adequate bonding with new embankment material.
C. Scarifying Equipment: Provide graders and dozers equipped with scarifying teeth and rippers capable of roughening horizontal surfaces and loosening of dry materials to a depth of 6 inches
05/05/2015 02300-2 for the addition of water and conditioning necessary to provide a good bond with the first layer of fill.
D. Spreading Equipment: Provide scrapers, graders, dozers, and other equipment to assist in spreading, aerating, and water conditioning of soil foundations and fill materials, as required.
E. Discing Equipment: Provide discs to break up, mix, aerate, and assist in water-conditioning fill in both in stockpiles and on the embankment fill, in place; and to assist in preparing soil-foundation surfaces, equipped with:
1. Depth adjustments and cut-angle adjustments that can be operated without dismount-ing vehicle.
2. At least two gangs hooked together in tandem in a total cutting width not less than 10 feet; and with serrated blades at least 24-inch in diameter, spaced no more than 16 inches apart.
3. Self-cleaning scrapers to prevent the accumulation of material on and between discs.
F. Compacted Embankment: Provide either 1 or 2:
1. Self-propelled sheepsfoot compactors equipped with:
a. Staggered, uniformly spaced tamping feet with an individual end area not less than 7 square inches or greater than 15 square inches, and tamping-feet length maintained not less than 6-inches (measured from drum to tamping head).
b. Maximum drum width: 84 inches
c. Two-drum or four-drum units separated by cab must have its static weight equally distributed to all compaction drums.
d. Static weight (on the drum) not less than 3,000 lb/ft of drum width.
2. Self-propelled tamping foot compactors equipped with:
a. Tamping feet with an individual end area not greater than 32 square inches, and tamping feet length maintained not less than 6 inches (measured from drum to tamping head). Static weight (on the drum) not less than 3,000 lb/ft of drum width.
b. Acceptable tamping feet compactors include Caterpillar Model 815 or Dyna-pac CT 262 or other compactor approved by the CO.
05/05/2015 02300-3
3.1 EARTHWORK
3.01 EXAMINATION
A. Verify Conditions
1. Prior to placing material in any section of the embankment, verify that the founda-tion for that portion has been cleared, stripped and water-conditioned. No materi-al will be placed on the foundation without prior written approval.
2. Scarify soil foundation areas so that the surface will bond and compact with the first layer of fill. Scarify by ripping and disking material 3 to 6 inches in depth, as determined by the Contracting Officer, so that no smooth surfaces remain.
3. Condition the foundation surface and previous lift surfaces to uniform water con-tent prior to placing fill. Pay particular attention to edges of fill against sloping ground and against abutment surfaces.
4. Do not allow water to accumulate on fill surfaces.
5. Do not place frozen materials, or place fill on frozen ground.
6. Do not place fill below water.
SCHEDULE 1 - Excavation
B. Classification: No classification as to class, nature, or condition will be made of any soil or rock from required excavations or borrow areas.
C. Excavate: Excavate according to the lines and grades shown on the Drawings, or written field clarifications.
D. Required excavation lines shown on the Drawings are the final or actual lines unless oth-erwise directed by the Contracting Officer. Final quantities may be higher or lower that those estimated in the Bid Schedule.
E. Strip the embankment foundation area, borrow areas and all areas to receive fill to a mini-mum depth of 6 inches or as shown on the Drawings and as required to remove all organic soils, vegetative matter, roots, and other perishable, loose or objectionable material that might interfere with compaction of embankment lift or the bonding of embankment to foundation. Objectionable material will be as determined by the Contracting Officer. Top-soil at the project site is limited. Perform stripping operations in a manner to conserve all topsoil that contains organics.
05/05/2015 02300-4
F. Transport stripped materials to stockpile areas outside of waterways and wetlands, subject to approval. Transport with a scraper or other approved wheeled vehicle. Locate piles so as not to affect the operation of the reservoir, or spillway interfere with the work, or detract from the appearance of the completed work.
G. Backfill unauthorized excavations, excessive soil excavations, and excavations for
CONTRACTOR convenience with approved materials as determined by the Contracting
Officer, at no additional cost to GOVERNMENT.
H. Take precautions to preserve, in a sound condition, the material below and beyond the lines of all excavations.
I. Perform operations so that the excavations will yield as much suitable material for construc-tion purposes as practicable.
J. Reuse, as much as is practicable, all suitable materials from required excavation in the per-manent construction. Separate unsuitable materials and remove them from the work area as soon as practicable.
K. It should be assumed that, in most cases, it will be necessary to stockpile and condition ex-cavated materials in temporary stockpiles prior to their being placed in the spillway em-bankments.
L. Spread out and allow materials to dry that are too wet for immediate compaction until the water content is reduced sufficiently for placement in the embankment. Aerating and dry-ing is incidental to the work.
M. Water-condition materials that are too dry for immediate compaction. Use water, discs, blades and other equipment to water condition materials directly in borrow areas and in temporary stockpiles prior to their being transported to fill areas.
N. Level and trim waste piles to reasonably regular lines, and slope to drain. Finished slopes shall be no more than 3H:1V.
O. Remove soft, wet, dry, objectionable, or otherwise unsuitable materials from the spillway foundation, as determined by the Contracting Officer.
SCHEDULE 2 - Preparation
P. Soil Foundation/Fill-Surface Preparation
1. Foundation preparation and water conditioning is critical. Maintain all exposed foun-dation surfaces in a moist condition (not saturated) at all times.
2. compact all foundation surfaces with a minimum of two passes by a sheep foot com-pactor a similar compactor that will provide equal or better compaction
05/05/2015 02300-5
3. Excavate overly dry, overly wet, soft/yielding, or otherwise unsuitable subgrade as de-termined by the Contracting Officer, and replace with appropriate, compacted, em-bankment fill for the location.
4. Scarify fill slopes and foundation surfaces equal to or flatter than 2.5H:1V (horizontal to vertical) so that the surface will bond and compact with the first…