Questions_and_Answers_Amend1.docx

DOCX document 14 KB Posted

Attached to
Roan Plateau Weed Treatment - Old Mountain Unit 2015 and 2016
Solicitation number
L15PS00525
Issued by

About this file

Questions and Answers_Amend1

View the file

Other files

File Type Posted
Sol_L15PS00525_Amd_000001.pdf PDF
Sol_L15PS00525.pdf PDF
76-1351.txt TXT text file
Solicitation_Clauses.docx DOCX document
lateauWeedTreatmentSOW_2015_2016_Williams.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

Q1. In the Scope of Work document, the third bullet point under “Additional Specifications” states that the Pesticide Use Proposal shall be submitted to the BLM office in Silt 1 month prior to work beginning. The work start time is the first week of July 2015, which would require a PUP submittal this week. The solicitation states a response deadline of June 19th, which would require that the PUP be submitted prior to the contract being awarded. How should companies responding to the solicitation proceed on this matter?

A1. The Pesticide Use Proposal (PUP) is required for this project, but because of the accelerated nature of the project, BLM will accept the PUP from the selected offeror as soon as the contract is awarded. BLM will then process the PUP as quickly as possible.

Q2. The BLM is providing a pre-bid site inspection tour on June 10, 2015. The Scope of work does not indicate whether the pre-bid is mandatory or optional. Can this be clarified?

A2. There is a pre-bid inspection tour on June 10, 2015 at 9 am. This is not a mandatory inspection, but offerors are highly encouraged to attend. BLM can schedule another time to meet with offerors before the offer due date of 6/19/15 if one is needed.