About this file

This specification document is issued by the Maine Department of Transportation for the procurement of five loader-mounted snow blowers, consisting of four units for installation on John Deere 624K wheeled front-end loaders and one unit for a Caterpillar 972G loader. The snow blowers are self-contained, two-stage units powered by integral diesel engines designed for heavy-duty winter operations. Each unit must meet specific operational requirements including a minimum cutting width of 114 inches for the J.D. 624K application and 126 inches for the Caterpillar 972G, discharge rates between 1,500 and 2,000 tons per hour, casting distances of at least 60 feet, and maximum weights of 10,000 pounds. The specifications detail comprehensive requirements for materials, design, construction, frame specifications, paint finishes in Cat Highway Yellow, hydraulically-operated spot casting chutes with variable casting distances of 3 to 40 feet, and impeller and auger specifications. Engines must be heavy-duty, turbocharged, six-cylinder diesel units with minimum 250 net horsepower for the J.D. 624K and 300 net horsepower for the Caterpillar 972G application.

Bidders must submit specification sheets with their proposals and price quotes separately for each configuration option, with all pricing inclusive of shipping and delivery to Maine DOT Fleet Service in Caribou, Maine. The specification document indicates that evaluation will be based on price, warranty, manufacturers' performance data, delivery schedule, parts availability, and other relevant factors. Vendors must provide two sets of technical publications for each unit, including operator's manuals, parts manuals, and maintenance and service manuals, along with minimum tools and accessories such as shear pins and specialized service tools. Maine DOT reserves the right to pre-inspect equipment before delivery and may require vendor training within eight weeks of delivery. Any exceptions to the specifications must be clearly identified on separate documentation submitted with the bid proposal, as non-listed exceptions will be considered vendor agreement with all listed specifications.

View the file

Other files

File Type Posted
Solicitation_terms.doc DOC document
FooterPrint.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specification

Loader Mounted Snow Blower

Purpose and Intent:

It is the purpose and intent of these specifications to describe a snow blower that will be fitted to a wheeled front end loader.

The blower unit must comply with all applicable Federal and State of Maine laws. The snow blower shall be a self-contained two stage snow blower. It shall be powered with an integral diesel engine, and designed for installation on, and operation from a wheeled loader (application is for a J.D 624K with a 3 cu yard bucket for (4) snow blowers and a Caterpillar 972 G with a 5 cu yard bucket for (1) snow blower). The snow blower must be engineered and designed for a heavy duty application to work under extreme winter conditions.

1. Manufacturers Literature: The manufacturer’s literature shall include a general description of the snow blower, a listing of all standard equipment provided on the model being bid, and a listing of all optional equipment available for the snow blower.

2. Operational Requirements:

a. Width of Cut: Minimum of 114 inches for the J.D 624K application.

b. Width cut minimum of 126 inches for the 972G Caterpillar application (not to exceed a 6 inch flare total).

c. Discharge Rate: 1500 to 2000 ton per hour at full capacity.

d. Casting Distance: At least 60 feet, or the equipment manufacturers stated casting distance for the model bid, which ever is greater.

e. Weight: Maximum 10,000 lb.

f. Working Height: at least 60 inches.

g. Overall Length: Not more than 96 inches.

3. MATERIALS: Materials shall be of the highest quality available for their intended commercial use.

4. DESIGN: Design of equipment shall permit easy access for maintenance and service. All blower unit stress points shall be designed to distribute and dissipate shock forces. All auger and impeller assemblies shall be protected against sudden stops or damage that may be caused from foreign objects. Protection may be in the form of automatic clutches, release overrides, and/or shear fasteners.

5. Construction: Shall be heavy duty to provide maximum protection against structural member failures. Equipment shall withstand the cold, moisture, strains, jars, vibration, and other conditions that are likely to be encountered during operation. All oil, hydraulic lines, air lines and electrical wiring shall be protected and properly attached to the frame or body structure. Wherever these lines pass through structural members, they shall be protected with looms and / or grommets except where a through-frame connector is necessary.

6. Blower Frame:

a. Structural Members - The frame shall be made of either pressed or structural steel channel and reinforced as required to prevent distortion under maximum load conditions. All frames and stiffeners shall be treated with a corrosion inhibitor and shall be primed and painted before assembly, as per paint and finish specifications.

b. Fabrication shall be of heavy gauge welded alloy steel designed for the type of expected service.

c. Scraper blade - A full width scraper blade shall be fitted to the lower leading edge of the frame which shall be removable and made of high carbon steel.

d. Skates - The frame shall be fitted with bolt on, steel skates, in proper numbers and locations to be capable of supporting the weight of the blower unit in its normal operating configuration.

e. Side Cutters - The frame shall be fitted with bolt-on steel side cutters.

7. Paint and finish: Preparation - The snow blower and all mounting equipment shall be free of rust and mill scale, sandblasted, then treated with a corrosion inhibitor, primed with a two (2) part epoxy primer to the minimum thickness of 3-5 mils dry. The paint shall consist of not less than two coats of Cat Highway Yellow (Imron 3.5 HG or approved equal: Paint code # 42-3133) having a minimum thickness of 5-7 mils, dry.

8. Loading Chute: The blower unit shall be equipped with a hydraulically operated spot casting/loading chute. The chute shall be capable of loading into a truck with a side height of 10 ft. and shall have a casting distance variable from 3 ft to 40 ft. The loading chute shall have a hydraulic rotation or pivot capacity of at least 180°. Rotation and casting distance shall be fully controlled from within the cab of the wheel loader carrier vehicle.

9. Impeller and Impeller Casing: The impeller capacity shall be at least equal to the capacity of the input augers. The impeller blades shall be made of high tensile steel and be balanced to reduce vibration and shock damage. The impeller shall be a 4 blade (min.) unit with easily replaceable concave blades at least ¼ inch thickness. The impeller casing shall be constructed of high strength steel at least 3/8 inch in thickness.

10. Augers: The augers shall be constructed of at least 3/8-inch high strength steel, and shall be at least 16 inches in diameter. Three auger heads may also be provided as long as the augers provide a total of at least 32 inches of coverage. When three auger heads are provided, the auger material thickness may be reduced to 5/16 inch. The augers shall be equipped with solid auger drive shafts, and shall be balanced and supported by bearings on the discharge end.

11. Blower Engine:

a. The blower engine shall be a heavy duty 4 cycle, turbocharged, water cooled, six cylinder, diesel engine with a minimum of 250 Net HP for the J.D 624K application.

b. The blower engine shall be a heavy duty 4 cycle, turbocharged, water cooled, six cylinder, diesel engine with a minimum of 300 Net H.P for the 972G Caterpillar application.

c. The engines shall be able to meet the performance characteristics specified herein on commercial grade fuel. The engine shall develop sufficient torque and horsepower to meet its normal operational requirements without exceeding the no-load speed at the peak of its certified gross brake horsepower curve.

d. Exhaust emission and noise level shall comply with all applicable Federal and State of Maine standards.

e. The engine shall be equipped with:

1) Extreme duty oil filtration with spin-on cartridge.

2) A 110-120 volt engine heater.

3) A low oil pressure / high temperature warning shut / down system wired so that it is visible to the operator in the wheel loader cab.

4) A cold weather starting aid (glow plug type preferred).

f. The engine shall be equipped with a 12-volt negative ground electrical system with at least two (2) 750 CCA batteries and an alternator with at least 90 amp capacity. All electrical components shall be mounted in a weatherproof, sealed electrical box.

g. Fuel filter (with water drain preferred).

h. Due to working conditions the blower engine and gear box must be located as close to center of unit as possible (engines and gear boxes mounted to the edge of the unit is not acceptable).

12. Instrumentation and Controls: Instrument/control panels with full controls for the blower unit shall be mounted in the tool carrier, and shall be connected to the tool carrier through the quick disconnect harness. The vendor shall provide a separate umbilical cord with all of the control and instrument functions shown below that can be attached to the snow blower unit with a weather proof canon plug and run into a replacement carrier vehicle on a temporary basis. The instrument/control panel shall also be connected to its wiring harness with a canon plug, and shall be capable of being removed and installed on the spare umbilical cord provided here. Vendors shall provide a bid price for a spare instrument/control panel. The instrument/control panel shall include at least the following:

a. Tachometer.

b. Hour meter.

c. Voltmeter.

d. Oil pressure gauge.

e. Coolant temperature gauge.

f. Fuel gauge.

g. Ignition switch.

h. Warning light and alarm for low oil pressure and high coolant temperature levels.

i. Clutch engagement controls and a warning system indicating when the clutch is engaged.

j. Controls for snow blower hydraulic functions, including loading chute and impeller casing.

k. Blower speed control.

13. Miscellaneous:

a. Quick Disconnect - The blower unit shall be equipped with a quick disconnect system compatible with the tool carrier coupler system to be acquired with this bid package and compatible with the JRB system. The coupler system shall allow the operator to complete changes without leaving the operating cab, including connection of hydraulics. The wiring harness may have a single quick connect plug.

b. Name, Service, and Instruction Plates. All information plates shall be made of either noncorrosive metal or plastic with the information engraved, stamped, or etched thereon. Plates shall be mounted in a conspicuous place with screws, bolts, rivets, or exterior-type pressure sensitive tape.

c. Plastic plates. Plastic plates are acceptable only in locations that are not exposed to the elements and subject to weathering or excessive heat.

d. Information plates shall identify make, model, serial number, and any other relevant data.

14. Technical Publications: Prior to acceptance of the blower units, the manufacturer shall furnish two (2) sets of the following publications for each unit; (CD’s are acceptable).

1) Operator's Manual: The operator's manual includes lubrication charts and instructions.

2) Parts Manual: The parts manual identifies and lists all parts, components, and sub-assemblies used in the fabrication of the blower unit.

3) Maintenance and Service Manual: A maintenance and service manual provides guidance to non-specialists performing routine services. The manual should also describe in detail with appropriate schematics the overhaul and major maintenance procedures required to maintain the unit.

15. Accessories and Tools:

The blower unit shall be equipped with the following tools and accessories. They shall be kept in a secure and readily accessible enclosure that is permanently affixed to the vehicle.

Shear Pins: A minimum of two (2) sets of pins shall be provided in support of each shear pin located on the blower.

Specialized Tools:

Specialized tools required for routine servicing of the blower and its auxiliary equipment.

16. Options for Price Quotes (please quote each separately).

1. Four (4) Snow Blowers for installation on a John Deere 624K with attachments.

2. One (1) unit for installation on a Caterpillar 972G with attachments.

Item #17 General:

17.1 Bidders shall supply a specification sheet with their bid proposals.

17.2 These specifications are a minimum and that bids will be evaluated based on price, warranty, manufacturers performance data, delivery schedule, parts availability and other items deemed appropriate.

17.3 Vendor may be asked to provide training at a later date, but within eight (8) weeks of delivery.

17.4 Maine DOT reserves the right to pre-inspect the equipment before delivery.

17.5 All bid pricing will include shipping and delivery to:

Maine DOT Fleet Service, 145 Bennet Drive Caribou, Maine, 04736.

17.6 Exceptions to specifications shall be listed on a separate paper and noted as exceptions and submitted with bid proposal. If exceptions are not listed as such it shall be considered that the vendor will comply with all specifications as listed.

17.7 Upon delivery of unit or units all necessary paper work such as Certificate of Origin (title), dealer’s certificate, and invoices shall accompany unit or units.

If you have a question regarding this RFQ, you must submit your questions thru the Question and Answer link on the Solicitation Details View page. Your answer will appear there as well. It is the vendor’s responsibility to log in to view all questions and answers posted there. Questions and Answers obtained any other way will not be valid for this RFQ.

esb:

REV: 11/1/11

File details come from the government source that posted it. Updated .