This document is a technical sketch for the roof replacement and restoration of the L-Dock at the Hopewell Marina, provided by the City of Hopewell Department of Economic Development. The scope of work includes the complete removal of the existing roof and structure, with replacement of the piles as needed. A new structural roof framing, deck, and metal roofing will be installed to provide a completed project, with the roof structure, materials, and fasteners specified by an engineer under a design-build contract. The work also includes the removal and reinstallation or replacement of the metal treatments on each end of the dock, and the rebuilding/reinforcement of the overhang structure with modern materials, connectors, and fasteners.

The document does not provide any information about pricing, set-asides, incumbents, funding requirements or sources, or contract terms and renewal options. It appears to be a technical drawing and specification for the roof and end treatments of the L-Dock, intended to be used as part of a larger design-build contract for the restoration of the marina facility.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

' • f, ... • • • • -.. 4)

(!)Roof Replacement:

* The existing roof and structure to be removed complete back to piles.

* Piles to be replaced or reinforced as a minimum as outlined on SK-01.

* New structural roof framing, deck and metal roofing will be installed to provide a completed project.

* Roof structure, material, fastener type and length to be specified by engineer under design build contract and will be appropriate for the environment where they will be installed.

@Roof end caps and walkway overhangs:

* Metal treatments on each end of dock to be removed and reinstalled or replaced to match existing appearance.

* Overhang structure to be rebuilt/reinforced with modern materials, connectors, fasteners as determined by engineer under design build contract.

,,111,::::::·, _

� .-Ii. __

• Ii -

' :; i ....._ t ...

City of Hopewell

Department of Economic Development

300 N. Main Street Suite 214

804-541-2270

Hopewell Marina L-Dock Restoration

Roof and End Plan

N awing for Seo e of work only.

Drawing by: as

Scale: None

Date: 10/23/2024

SK-02