This document is a Statement of Work (SOW) for the Kentucky Lock project, detailing the supply, delivery, and installation of a new 28'x60' modular office trailer at the Kentucky Lock Resident Office compound. The comprehensive scope of work includes preparing the trailer foundation with inground structural footers, installing the modular trailer with a matching two-tone exterior paint scheme, and supplying and installing all interior components such as furniture, appliances, HVAC, plumbing, lighting, and systems.
Additional requirements encompass utility connections to existing site infrastructure, construction of wood decking with ramp and stairs for trailer access, installation of a new gravel driveway, and routing a buried main fiber network line between existing and new office trailers. The project is specifically scoped for the U.S. Army Corps of Engineers (USACE), with a notable exclusion of USACE IT network equipment installation, except for the specified fiber network line routing. The document is dated 5-DEC-2025 and references attached sketches and photos for additional project details.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Kentucky Lock – New Conferencing Trailer Statement of Work
5-DEC-2025
Supply, delivery, and installation of a new 28'x60' modular oƯice trailer at Kentucky Lock Resident OƯice compound. Reference attached sketches for additional details.
Scope of work includes the following:
1) Preparation of trailer foundation area, including installation of inground structural footers to support and distribute the weight of the trailer.
2) Supply, delivery, and installation of new 28’x60’ modular oƯice trailer, in accordance with the floorplan/layout sketch. Includes exterior paint scheme to match existing Resident OƯice two-tone paint (reference attached photo).
3) Supply and installation of all furniture, appliances, HVAC, plumbing, appurtenances, flooring, lighting, cabinetry, fixtures, finishes, signage, and systems.
4) Installation and connection of all utilities, to include plumbing, sewer, and electric.
Utilities will tie-in to existing site utilities. Refence attached sketches for locations of existing site utilities.
5) Supply and construction of new wood decking, ramp, stairs, and railings for access/egress into the trailer.
6) Installation of new gravel access driveway in grassy roundabout area.
7) Installation and routing of buried main fiber network line from existing Resident
OƯice trailer to new oƯice trailer.
Note: This scope of work excludes installation, configuration, and connection of all USACE IT network equipment, except as described in number 7 above.